Attachment_M_FINANCIAL_REPORTING_533.pdf

PDF 92 KB Posted

Attached to
Facilities Operations and Maintenance Services Federal contract opportunity
Solicitation number
NNG16572637R-1
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

Attachment M Financial Management Reporting 533

View the file

Other files for this federal contract opportunity

Other files attached to Facilities Operations and Maintenance Services, newest first.
File Type Posted
Signed_SSA_Letter.pdf PDF
Set_5_Questions_and_Answers_FOMS_III.pdf PDF
Set_4_Questions_and_Answers_FOMS_III_(2).pdf PDF
Revised_SECTION_K.pdf PDF
Appendix_8_-_Asset_Condition_Code.pdf PDF
FOMS_III_SOW_rev_2-16-17.pdf PDF
SF30_Amendment_4.pdf PDF
Amendment_2_NNG16572637R.pdf PDF
SF30.pdf PDF
Attachment_P_Wage_Determination.pdf PDF
Attachment_N_Collective_Bargaining_Agreement.pdf PDF
Attachment_Q_Concrete_Paving_and_Traffic_Control_Bid_Schedule_-_Clean.pdf PDF
Enclosure_1_QASP_Cost-Type_Contract.pdf PDF
Appendix_6_-_Installation_Accountable_Government_Property.pdf PDF
Attachment_Q_Asbestos_bid_Schedule_-_Clean.pdf PDF
Attachment_K_Contract_Historical_Data.pdf PDF
SF33.pdf PDF
Appendix_5_-_Installation_Accountable_Government_Materials.pdf PDF
Cover_Letter_FOMS_III_RFP.pdf PDF
Appendix_7_-_Chemical_Treatment.pdf PDF
Attachment_D_DD_254_Pg_3_Continuation.pdf PDF
Attachment_G_Quality_Control_Plan.pdf PDF
Attachment_O_Wage_Determination.pdf PDF
Attachment_L_Safety_and_Health_Plan.pdf PDF
NNG16572637R_RFP.pdf PDF
Attachment_E_PIV.pdf PDF
Attachment_I_IT_Security_Management_Plan.pdf PDF
Appendix_2_-_Acronyms.pdf PDF
Attachment_Q_Roofing_Bid_Schedule_-_Clean.pdf PDF
FOMS_III_Site_Visit_Attendees.pdf PDF
Appendix_4_-_Installation_Provided_Government_Facilities_Summary.pdf PDF
Appendix_7_-_Chemical_Treatment.pdf PDF
Appendix_8_-_Listing_of_Asset_Quantities_and_PM_Requirements.pdf PDF
Appendix_1_-_Appendix_and_Attachment_List.pdf PDF
Enclosure_2_IT_Security_Management_Plan.pdf PDF
Attachment_L_Safety_and_Health_Plan.pdf PDF
Attachment_F_-_FOMS_III_Tech_Performance_Incentive_Fee_Plan.pdf PDF
Attachment_Q_Concrete_Paving_and_Traffic_Control_Bid_Schedule.pdf PDF
Attachment_F_TPIF.pdf PDF
NNG16572637R_FOMS_III_DRFP.pdf PDF
Exhibits_1-16_FOMS_III_Cost.pdf PDF
Attachment_E_PIV.pdf PDF
Attachment_D_DD254_Form.pdf PDF
Enclosure_3_RTOs.pdf PDF
Exhibit_18_Pricing_Charts.pdf PDF
Attachment_Q_Roofing_Bid_Schedule.pdf PDF
Attachment_C_Installation_Accountable_Government_Property.pdf PDF
Attachment_P_Wage_Determination.pdf PDF
Attachment_Q_Asbestos_Bid_Schedule.pdf PDF
Amendment_5_SF30.pdf PDF
Show all 50

Facilities Operations and Maintenance Services has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT M

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

RFP NN16572637R

CONTRACT TBD

Contract TBD

Attachment M

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

This contract will have two sections: a Core Element section (CPFF and CPIF), and an

IDIQ Task Order section (CPIF, CPFF, or FFP). The Core Elements will include the following breakout:

SCHEDULED MAINTENANCE:

CORE

DDL

UPS

UNSCHEDULED MAINTENANCE

OPERATIONS:

BUILDING OPERATIONS

CENTRAL PLANT OPERATIONS

OTHER FACILITY SERVICES:

SERVICE REQUESTS

PLANNING/ESTIMATING

The IDIQ Task Order section will be broken out as follows:

IDIQ TASK SUMMARY

TASK 1

TASK 2

TASK 3, etc.

For the Core Elements portion of the contract, the Contractor’s 533 Reports shall contain an individual 533 Report for each Core element and a summary 533 Report of all Core element costs.

For the IDIQ portion of the contract, an individual 533 Report shall be provided for each

Task Order and a summary 533 Report summarizing all Task Orders issued.

The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d, below.

(06/2014) 3

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 5 percent (+/- 5%) between the Total

Direct Labor Hours (prime and subcontractors) and Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and Actual Total Cost amount shown in the current month for each individual Core Element and for each individual IDIQ Task Order. (For example, the Total Estimated Cost amount shown for

June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the

Core elements and each individual task order’s estimated costs, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533 Q format within 30 working days after contract award.

Initial NF533 M reporting shall begin NO LATER than 10 days following the close of the contractor’s accounting period after initial incurrence of cost. After the initial report, the NF 533 M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period. The NF533 Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost and hour data by the following elements of cost categories:

1. Prime Direct Labor Hours:

Total Prime Direct Labor Regular Hours

Total Prime Direct Labor Overtime Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Regular Hours

Subcontractor A Direct Labor Overtime Hours

Subcontractor B Direct Labor Regular Hours

Subcontractor B Direct Labor Overtime Hours

(06/2014) 4

Subcontractor C Direct Labor Regular Hours

Subcontractor C Direct Labor Overtime Hours

Total Subcontractors Direct Labor Regular Hours

Total Subcontractors Direct Labor Overtime Hours

3. Total Prime and Subcontractors Direct Labor Regular Hours

Total Prime and Subcontractors Direct Labor Overtime Hours

TOTAL HOURS

4. Prime Direct Labor Costs:

Total Prime Direct Labor Regular Costs

Total Prime Direct Labor Overtime Cost

TOTAL PRIME DIRECT LABOR COST

5. Prime Overhead Expense

6. Other Direct Costs (ODCs):

a. Subcontractor A

b. Subcontractor B

c. Subcontractor C, etc.

d. Subtotal Subcontractor Cost

e. Uniforms

f. Supplies

g. Vehicles

h. Vehicle Expenses

i. Elevator Maintenance Service

j. Chemical Water Treatment

k. Fuel Oil Cleaning

l. Fencing Repairs

m. Energy Management & Control Systems Maintenance

n. Consulting

o. Miscellaneous

p. Other (specify)

Total ODC’s

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

(06/2014) 5

11. Subtotal Cost-Plus-Fixed-Fee (CPFF)

12. Technical Performance Incentive Fee Earned

13. Total Cost Plus Fixe Fee Plus Technical Performance Incentive Fee