Attachment_Q_Asbestos_Bid_Schedule.pdf

PDF 175 KB Posted

Attached to
Facilities Operations and Maintenance Services Federal contract opportunity
Solicitation number
NNG16572637R-1
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

Attachment Q Asbestos Bid Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Facilities Operations and Maintenance Services, newest first.
File Type Posted
Set_6_Questions_and_Answers_FOMS_III.pdf PDF
Revised_SECTION_K.pdf PDF
Appendix_8_-_Asset_Condition_Code.pdf PDF
Appendix_8_-_SHOP_(Craft)_Codes.pdf PDF
Appendix_8_-_Quantity_of_Assets_Incl_Plus_and_Minus.pdf PDF
Set_3_Questions_and_Answers_FOMS_III.pdf PDF
Amendment_3_SF30.pdf PDF
Amendment_2_NNG16572637R.pdf PDF
SF30.pdf PDF
Questions_and_Answers.pdf PDF
Attachment_P_Wage_Determination.pdf PDF
Attachment_N_Collective_Bargaining_Agreement.pdf PDF
Attachment_Q_Concrete_Paving_and_Traffic_Control_Bid_Schedule_-_Clean.pdf PDF
Enclosure_1_QASP_Cost-Type_Contract.pdf PDF
Appendix_6_-_Installation_Accountable_Government_Property.pdf PDF
Attachment_Q_Asbestos_bid_Schedule_-_Clean.pdf PDF
Attachment_K_Contract_Historical_Data.pdf PDF
SF33.pdf PDF
Appendix_3_-_Building_Descriptions.pdf PDF
Exhibit_17_PastPerfQues.pdf PDF
Attachment_C_-_Installation_Accountable_Government_Property.pdf PDF
Exhibits_1-16_FOMS_III_Cost_Exhibits.pdf PDF
Appendix_4_-_Installation_Provided_Government_Facilities_Summary.pdf PDF
Attachment_D_DD254.pdf PDF
Attachment_F_TPIF.pdf PDF
Attachment_F_-_FOMS_Tech_Performance_Incentive_Fee_Plan.pdf PDF
Attachment_J_OCI_Avoidance.pdf PDF
Attachment_A_FOMS_III_SOW.pdf PDF
FOMS_III_Site_Visit_Attendees.pdf PDF
Appendix_4_-_Installation_Provided_Government_Facilities_Summary.pdf PDF
Appendix_6_-_Installation_Accountable_Government_Property.pdf PDF
Appendix_5_-_Installation_Accountable_Government_Materials.pdf PDF
Appendix_3_-_Building_Descriptions.pdf PDF
Enclosure_2_IT_Security_Management_Plan.pdf PDF
Attachment_L_Safety_and_Health_Plan.pdf PDF
Attachment_F_-_FOMS_III_Tech_Performance_Incentive_Fee_Plan.pdf PDF
Attachment_Q_Concrete_Paving_and_Traffic_Control_Bid_Schedule.pdf PDF
Attachment_F_TPIF.pdf PDF
NNG16572637R_FOMS_III_DRFP.pdf PDF
Exhibits_1-16_FOMS_III_Cost.pdf PDF
Attachment_M_FINANCIAL_REPORTING_533.pdf PDF
Attachment_J_OCI_Avoidance.pdf PDF
Exhibit_17_Past_Performance_Questionnaire.pdf PDF
Attachment_I_IT_Security_Management_Plan.pdf PDF
Attachment_A_FOMS_III_SOW.pdf PDF
Attachment_N_Collective_Bargaining_Agreement.pdf PDF
Enclosure_1_QASP.pdf PDF
Attachment_H_IT_Security_Applicable_Documents_List.pdf PDF
Attachment_O_Wage_Determination.pdf PDF
Amendment_5_SF30.pdf PDF
Show all 50

Facilities Operations and Maintenance Services has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOMS III

Asbestos Abatement Bid Schedule Attachment Q

Units Unit Price Unit Price Unit Price Unit Price Unit Price

Contract

Year 1

Contract

Year 2

Contract

Year 3

Contract

Year 4

Contract

Year 5

PREPARATION

A.1 Furnish all labor and materials to fabricate and install a THREE-STAGE decontamination facility in accordance with federal requirements.

each

A.2 Furnish all labor and materials to fabricate and install a TWO-STAGE (no shower) decontamination facility in accordance with current federal requirements.

each

A.3 Furnish all labor and materials to construct a temporary partition. The partition must be at least seven feet in height and constructed of plywood, sheetrock or similar material. This line item includes dismantling of the partition at the completion of all work.

sf

A.4 Install 6-mil thick polyethylene sheeting for use in constructing containment, covering items, as a drop cloth, etc. This line item includes encapsulation, dismantling and disposal.

sf

A.5 REMOVE asbestos-contaminated debris from floor. Includes HEPA vacuum and wet wipe.

sf

CEILING / WALLS

A.6 REMOVE asbestos-contaminated debris from suspended ceiling. Includes

HEPA vacuum and wet wipe.

sf

REMOVE asbestos-containing or asbestos-contaminated suspended acoustical lay-in ceiling tile, including suspension system and accessories.

a Height up to 12’ sf b Height above 12’ sf

CEILING TILE

A.7 REMOVE asbestos-containing materials from planar surfaces (ceiling and walls) down to bare substrate.

sf a Up to 2000 SF sf

A.8 REMOVE layer of VAT Friable ACM floor tiles.

a Up to 1000 SF sf b over 1000 SF sf

A.9 REMOVE layer of VAT Non Friable ACM floor tiles.

Item Description

Attachment Q a Up to 1000 SF sf b over 1000 SF sf c REMOVE layer of VAT Non Friable ACM floor tiles, with carpet tiles attached.

sf

A.10 FLOORS/WALLS/CEILINGS

Remove asbestos-containing mastic from floor, wall or ceiling a Up to 1000 SF sf b Over 1000 SF sf

A.11 Cut access holes in ACMs walls or ceilings to include gaining access to ACMs sf

A.12 DRYWALL PARTITIONS

a REMOVE existing wood or metal stud drywall partitions where the partition abuts asbestos-containing material. This includes the removal of doors, door frames, electrical outlets, clocks, and switches, and all wiring back to the next junction box or outlet box. Return all doors, frames and hardware to the government.

sf

A.13 REMOVE horizontal or vertical pipe enclosure covers to gain access to asbestos-containing pipe insulation material. These covers are typically single sheeted, three-sided sheet metal, and are screwed together.

sf

DUCTWORK

A.14 ENCAPSULATE ACM on ductwork, including all hangers or other type of fasteners. Encapsulation is to be accomplished via an airless sprayer and an

EPA-approved lockdown encapsulant. Diameters listed below include insulation.

sf

A.15 REMOVE ACM from ductwork, fan enclosures, or similar equipment. sf

A.16 ENCAPSULATE asbestos-containing material on piping. Encapsulation is to be accomplished using lagging material and EPA-approved bridging mastic.

a Less than 2 inch lf b 2 inch - 6 inches lf c 7 inch to 12 inches lf d 14 inch to 20 inches lf

A.17 REMOVE and DISPOSE of Asbestos Insulation from Piping and Hangers.

b Less than 2 inch lf c 2 inch - 6 inches lf

Attachment Q d 7 inch - 12 inches lf e 14 inch to 20 inches lf

A.18 ENCAPSULATE asbestos-containing materials on tanks, boilers, breaching, heat exchangers and related equipment.

sf

A.19 REMOVE asbestos-containing materials from tanks, boilers, breaching, heat exchangers and related equipment. Encapsulate utilizing bridging encapsulant or lagging.

sf

A.20 Remove ACM from pipe or valves using GLOVEBAGS each

A.21 MISCELLANEOUS

a APPLY wet-wrap, material to exposed asbestos edges, whole edges or damaged asbestos-containing materials.

sf

A.22 DECONTAMINATE horizontal and vertical surfaces by HEPA-vacuuming, wet-wiping and encapsulating surface with an EPA approved lock-down encapsulant and an airless sprayer. This line item is intended for surfaces within full containments where there are not substantial visible quantities of debris on the surfaces.

a Surfaces up to 10 feet in height sf b Surfaces greater than 10 feet. in height sf

A.23 Provide an industrial hygienist to conduct asbestos abatement oversight and air monitoring services to conform to all applicable OSHA and EPA regulations and to sign asbestos oversight and air monertering reports.

hr

A.24 Conduct on-site asbestos air sample analysis in accordance with NIOSH

Method 7400 Phase Contract Microscopy.

each