This document provides answers to questions from potential offerors regarding solicitation number N3220521R4170 for regular overhaul and dry docking of the USNS ZEUS (T-ARC 7). The Military Sealift Command seeks performance of various joiner bulkhead panel removals and replacements, with approximately 140 panels required and additional scope available if needed. Photos of work areas are available via DoD Safe, and all joiner doors will be removable. For specification 902, offerors should price the solicitation requirements of sixty-four ZHC-23 anodes as stated in paragraph 3.2.1. For specification 104, the additional 10,000 square feet of coating referred to in various paragraphs applies to longitudinal and overhead surfaces not within the interior of the ship.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N3220521R4170
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
QUESTION: Specification 613
1. Paragraphs 7.1.11 through 7.1.14. How many joiner blkhd panels are to be removed and replaced?
ANSWER:
Not all the panels are full 4 by 8 pannels. Some will need to be cut to fit and there will be unsualble drops.
There are approximately 140 pannels, and 7.1.14/ 7.1.23 are for additional scope if required. Stainless panels are the shower walls(3 in each head) and will need to be laminated on the opposite side.
QUESTION: Specification 613/614
2. Please provide pictures of the following areas:
1. Picture of AFT Passage Way – Boat Deck
2. Picture of AFT SR’s and T/S – Boat Deck
3. Picture Two Midship Passage Ways – 3rd Deck
4. Picture Midship Passage Way Adjacent to Trimming Room/Steward Dry Stores – 3rd Deck
5. Picture Midship Crew SR’s and T/S – 3rd Deck
6. Picture Store Rooms, CG LKR’s, etc – 3rd Deck
7. Picture of Bulkhead Panels/Profiles
8. Picture of Ceiling Panel System
9. Picture of Joiner Doors (Will all be removable?)
ANSWER:
9. Yes, various photos are provided via Dod Safe for many work items.
QUESTION: Specification 902, various
3. Please clarify number of anodes and type (size) to be used.
Paragraph 3.2.1 notes sixty-four (64) ZHC-23.
Paragraph 7.2.2.3 notes to use ref. 2.2 dwg. 5503940 as guidance, which shows seven (7) ZHC-23 and forty-one (41) ZHC-47.
ANSWER:
Price the item as stated in 3.2.1
QUESTION: Specification 104, various
4. Please clarify paragraphs 3.1.2.2, and 7.3.3. In paragraph 7.2.2 the customer designates the 10,000 sq ft and paragraph 7.2.4 designates 10,000 sq feet IAW 3.1.2.1. Paragraph 7.3.2 refers to paragraph 7.2.4 but paragraph 7.3.4 indicates the entire superstructure get a stripe coat and a full coat. Is this a correct assessment? Please clarify this item.
ANSWER:
The additional 10, 000 for additional surfaces not included in the difined super structure in 3.1.1.1. i.e.
longitudinals and overhead surfaces not in the interior of the ship.