N3220521R4170-0003.docx
DOCX document 46 KB Posted
- Attached to
- ZEUS ROH/DD Federal contract opportunity
- Solicitation number
- N3220521R4170
About this file
This document provides the statement of work for the USNS ZEUS Regular Overhaul/Dry Docking opportunity. The contractor will be responsible for preparing and accomplishing the vessel repair and overhaul work items according to the work item package and schedule. Key responsibilities include management, procurement, quality assurance, configuration control, material storage, and subcontractor oversight. The contractor must have experience in ship repair and necessary facilities, certifications, and technical capabilities. Work must be completed within 90 days of contract award at the contractor's facility. The opportunity was issued by the Department of the Navy Military Sealift Command.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220521R4170
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
SUBCLIN 0001AB
The CLIN extended description has changed from:
USNS ZEUS (T-ARC-7) ROH/DD NUWC FUNDED CAT A WIsCAT A WORK ITEMS 701, 702, 703, 704, 705, 706, 707, 708
To:
USNS ZEUS (T-ARC-7) ROH/DD NUWC FUNDED CAT A WIsCAT A WORK ITEMS 701, 703, 704, 705, 706, 707, 708
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
ACRONYM TABLE
| ABIH |
| American Board of Industrial Hygiene |
| ABR |
| Agreement for Boat Repair |
| ABS |
| American Bureau of Shipping |
| ACO |
| Administrative Contracting Officer |
| AGR |
| Additional Government Requirements |
| AIHA |
| American Industrial Hygiene Association |
| ALT |
| Alternate |
| AMT |
| Amount |
| BLDG |
| Building |
| CCO |
| Contract Change Order |
| CD |
| Compact Disc |
| CDRL |
| Contract Data Requirements List |
| CD-ROM |
| Compact Disc Read-Only Memory |
| CFM |
| Contractor Furnished Material |
| CFP |
| Contractor Furnished Property |
| CFR |
| Condition Found Report |
| CHENG |
| Chief Engineer |
| CFR |
| Code of Federal Regulations |
| CIH |
| Certified Industrial Hygienist |
| CLIN |
| Contract Line Item Number |
CONUS
CPARS
Contiguous United States Contractor Performance Assessment Reporting System
| DBIDS |
| Defense Biometric Identification Systems |
| DFARS |
| Defense Federal Acquisition Regulation Supplement |
| DOD |
| Department of Defense |
| DOD SAFE |
| Department of Defense Secure Access File Exchange |
| DON |
| Department of the Navy |
| Electronic Mail |
| ESRS |
| Electronic Subcontract Report System |
| FAPIIS |
| Federal Awardee Performance and Integrity Information System |
| FAR |
| Federal Acquisition Regulation |
| FBLR |
| Fully-Burdened Labor Rate |
| F/CC |
| Fibers Per Cubic Centimeter |
| FPCON |
| Force Protection Condition |
| FTR |
| Federal Travel Regulations |
| G&A |
| General and Administrative |
| GFI-TD |
| Government Furnished Information – Technical Data |
| GFM |
| Government Furnished Material |
| GFP |
| Government Furnished Property |
| GPE |
| Governmentwide Point of Entry |
| IAW |
| In Accordance With |
| ID |
| Identification |
| ISO |
| International Organization for Standardization |
| JTR |
| Joint Travel Regulations |
| KO |
| Contracting Officer |
| KWh |
| Kilowatt Hour |
| LLTM |
| Long Lead Time Material |
| LPTA |
| Lowest Price Technically Acceptable |
| M&IE |
| Meals and Incidental Expenses |
| MSC |
| Military Sealift Command |
| MSCREP |
| Military Sealift Command Representative |
| MM |
| Millimeter |
| MSRA |
| Master Ship Repair Agreement |
| MTA |
| Mid-Term Availability |
| N/A |
| Not Applicable |
| NCACS |
| Navy Commercial Access Control System |
| NDA |
| Non-Disclosure Agreement |
| NO |
| Number |
| NSP |
| Not Separately Priced |
| ODC |
| Other Direct Costs |
| PAT |
| Proficiency in Analytical Testing |
PII
Portable Document Format Personally Identifiable Information
| PM |
| Program Manager |
| PPE |
| Principle Port Engineer |
| PRIME |
| Prime Contractor |
| QA |
| Quality Assurance |
| QC |
| Quality Control |
| REV |
| Revision |
| RFC |
| Request for Specification Clarification |
| RFP |
| Request for Proposal |
| ROH/DD |
| Regular Overhaul/Dry-Docking |
| SECNAV |
| Secretary of the Navy |
| SF |
| Standard Form |
| SUB |
| Subcontractor |
| TPSN |
| Time Phased Sequencing Network |
| TWA |
| Time-Weighted Average |
| USC |
| United States Code |
| USCG |
| United States Coast Guard |
| USNS |
| United States Naval Ship |
| VR |
| Voyage Repair |
| WAWF |
| Wide Area Workflow |
| WI |
| Work Item |
SCOPE OF WORK
1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS ZEUS (T-ARC 7) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.
2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):
a. Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.
b. Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR 52.245-1 and DFARS 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.
c. Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.
d. Using management procedures and systems to identify behind-schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.
e. Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 0013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted IAW the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 0013.
f. Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.
g. Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.
h. Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.
i. Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.
j. Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.
k. Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.
3. Contract work shall be performed by an eligible contractor as defined below.
a. The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.
b. The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:
1) Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.
2) Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.
3) Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.
4) Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.
5) Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.
6) Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.
7) Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.
8) Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.
9) Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records which indicate type of material, date, and place of disposal.
10) Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:
· Pier, with services in place, accessible to the CLASS size ship for berthing
· Structural Shop
· Machine Shop
· Pipe Shop
· Electrical/Electronic Shop
· Carpentry Shop
· Rigging Equipment
· Dry-dock – when required for docking of vessel in performance of the specification
11) Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.
c. The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.
4. Asbestos removal requirements.
a. During the performance of this contract the contractor and subcontractors may be required to perform work which involves the removal or disturbance of asbestos or asbestos-containing products. This requirement applies to each instance of asbestos removal or disturbance.
b. The contractor shall comply with the precautions required in 29 CFR 1910.1001, 29 CFR 1926.58 and 40 CFR Part 61 and all other applicable Federal, state, and local restrictions. The contractor shall forward a copy of all required notices, licenses and permits to the KO immediately upon issuance or receipt.
c. The latest change to the Federal, state, and local regulations in effect at the time of issuance of the contract shall govern. Compliance with these regulations is mandatory and is necessary to protect the employees of the contractor and Naval personnel from exposure to asbestos fibers in excess of the OSHA Action level airborne concentration (currently 0.1 f/cc of air).
d. During removal or disturbance, the contractor shall control airborne asbestos concentrations outside the removal boundary to less than 0.1 f/cc at all times.
e. After removal or disturbance is complete, the areas within the removal boundary shall not be released for re-occupancy until clearance air sampling demonstrates these spaces have concentrations of asbestos less than 0.1 f/cc.
f. In all respects, the performance of air sampling and analysis shall be performed IAW the OSHA Reference Method (Appendix A of 29 CFR 1910.1001), with the following additional specifications:
1) Aggressive clearance sampling shall be performed on 25 mm cassettes at 2.0 liters per minute for a minimum of four (4) hours.
2) In performing the clearance sampling, the pump shall be placed within the compartment where the removal or disturbance occurred. When this operation is conducted in a multilevel space, at least one pump shall be placed on each level.
3) Air sampling shall be performed by a person competent in sampling procedures and overseen by a CIH by the ABIH.
4) Laboratory analysis of samples shall be performed by a participant in the AIHA PAT Program rated proficient for asbestos and air.
g. Personal sampling shall be conducted using breathing zone air samples which are representative of the 8-hour TWA exposure of each individual. Samples shall be collected and analyzed using the OSHA Reference Method contained in either 29 CFR 1910.1001 (as amended) or 29 CFR 1926.58 (as amended).
h. The contractor agrees to indemnify MSC for any fines assessed by Federal, state, or local agencies, for the contractor's failure to properly follow applicable regulations.
i. The contractor shall insert this instruction in all subcontracts entered into under this contract.
5. Post-award substitution of any major subcontractor should not be effected unless the proposed substitution is submitted to the KO and official approval is obtained. The post-award substitution or insertion of a second-tier subcontractor will be treated in the same manner as the substitution of a major subcontractor and requires specific approval by the KO.
6. Substitution of key personnel.
a. The contractor agrees to assign to this contract those persons identified as key personnel who are necessary to fulfill the requirements of this contract and whose resumes were submitted with the proposal. No substitution of key personnel shall be made except IAW these instructions.
b. All proposed substitutions must be submitted, in writing, at least seven (7) days in advance of the proposed substitutions to the KO and must provide the information required by paragraph “c” below.
c. All requests for substitution must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the KO. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person to be replaced. The KO or his authorized representative will evaluate such requests and promptly notify the contractor of the approval or disapproval thereof.
7. It is anticipated the ship will arrive at the contractor’s yard on or about 03 January 2022. All work shall be completed in no more than 90 calendar days from the actual start date designated by the Government at the time of contract award.
8. The place of performance for this contract shall be the contractor’s facility.
Table 1: List of WIs:
| ITEM NUMBER |
| TITLE |
| CATEGORY |
| SECTION 0000 |
| GENERAL SERVICES AND REQUIREMENTS |
INTENT SCOPE GENERAL CONDITIONS AND DEFINITIONS
TECHNICAL AND MANUFACTURER’S REPRESENTATIVES
APPROACH, BERTH, AND MOORING REQUIREMENTS
TESTING AND QUALITY ASSURANCE
ELECTRICAL SAFETY PROCEDURE REQUIREMENTS
HEAVY WEATHER PLAN
COLD WEATHER PLAN
FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM
FURNISH GENERAL SERVICES
TELEPHONE SERVICES
PROJECT PLANNING AND PRODUCTION STATUS MONITORING
REPORTS
PREPARATION OF WEIGHT AND MOMENT REPORT
INTEGRATED LOGISTICS AND GFM SUPPORT REQUIREMENTS
FIRE PROTECTION AND SHIP’S SAFETY PROGRAM
HANDLING SHIP’S STORES
DELIVERY AND REDELIVERY OF THE VESSEL
SHIPBOARD ACCESS AND SECURITY
GAS FREE CERTIFICATES
MACHINERY SPACE TURN-OVER DOCK TRIALS AND SEA TRIAL
HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR’S FACILITY
PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY
PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY
VESSEL FINAL CLEANING COVID
CONTINUATION OF SERVICES
DAILY COVID – 19 PREVENTION AND CONTROL
NSP
NSP
NSP
NSP
NSP
NSP
NSP
NSP
A A A
A A A A A A A A A
NSP
B B B A
| SECTION 0100 |
| HULL AND STRUCTURAL |
CLEAN, GAS FREE AND TEST TANKS
NON-SKID AND DECK PRESERVATION
TANK PRESERVATION
SUPERSTRUCTURE PRESERVATION
ULTRASONIC GAUGING
CRANE PRESERVATION
BULWARK AND APPENDAGE PRESERVATION
ULTRASONIC GAUGING
STRUCTURAL REPAIRS
KICK PIPES
LADDER REPAIRS
A A A A A A A B A
| SECTION 0200 |
| PROPULSION MACHINERY |
| 0202 | INSPECT MAIN PROPULSION MOTORS | A |
| 0208 | MDG REILIANT MOUNT REPLACEMEMT | A |
| SECTION 0300 |
| ELECTRICAL |
| 0301 | SWITCHBOARD CLEANING | A | |||
| 0302 | UNDERWATER THERMOGRAPHY SURVEY | A | |||
| 0303 | THRUSTER SEALS | A | |||
| 0399 | MISCELLANEOUS MOTOR OVERHAUL | B |
| SECTION 0400 |
| COMMUNICATION AND NAVIGATIONAL AIDS |
| 0401 | GMDSS SAFETY RADIO ANNUAL CERTIFICATION | A | |
| 0402 | RADAR AND ECDIS ANNUAL INSPECTION | A | |
| 0403 | GYRO COMPASS AND STEERING SERVICE | A |
| SECTION 0500 |
| AUXILIARY SYSTEMS |
| 0501 | HALON AND CO2 EXTINGUISHER SYSTEM ANNUAL INSPECTION | A | |||||
| 0502 | PORTABLE EXTINGUISHER TEST AND INSPECTION | A | |||||
| 0503 | FIRE ALARM ANNUAL INSPECTION | A | |||||
| 0505 | FIRE DAMPER INSPECTION | A | |||||
| 0506 | GAUGE CALIBRATION | A | |||||
| 0508 | AUX BOILER INSPECTION AND LAY UP | A | |||||
| 0510 | OWS ANNUAL INSPECTION | A | |||||
| 0512 | CONE 4 & 5 BILGE & BALLAST MANIFOLD VALVES OVERHAUL | A | |||||
| 0520 | MISC PIPING REPLACMENT | B | |||||
| 0521 | STBD AFT CABLE DRUM PRESERVATION – REV B | A | |||||
| 0522 | INSPECTION OF VARUOUS HOIST | A | |||||
| 0523 | CD BRIDGE CRANE | A |
| SECTION 0600 |
| OUTFIT, FURNISHINGS AND HABITABILITY |
| 0601 | ANNUAL ACCOMMODATION LADDER INSPECTION AND TEST | A | |||||
| 0602 | ANNUAL SCBA COMPRESSOR RECERTIFICATION | A | |||||
| 0604 | ANNUAL FIRE HOUSE HYDROSTATIC TEST | A | |||||
| 0605 | CARGO ELEVATOR INSPECTION AND CERTIFICATION | A | |||||
| 0606 | ANNUAL LIFE RAFT CERTIFICATION | A | |||||
| 0607 | ANNUAL RESCUE BOAT AND DAVIT INSPECTION | A | |||||
| 0608 | ANNUAL LIFEBOAT AND DAVIT INSPECTION | A | |||||
| 0609 | FORWARD CRANE REPAIR AND ANNUAL CERTIFICATION | A | |||||
| 0610 | AFT CRANE REPAIR AND ANNUAL CERTIFICATION | A | |||||
| 0611 | REPLACE VARIOUS FIRE SAFETY DOORS | B | |||||
| 0613 | SHOWER STALL REPLACEMENT | A | |||||
| 0614 | INSULATION INSTALLATION AT DESIGNATED LOCATIONS – REV B | A | |||||
| 0655 | IMMERSION SUIT SERVICE | A |
| SECTION 0700 |
| NUWC EQUIPMENT |
| 0701 | CRANE LIFTS AND SCAFFOLDING SUPPORT – REV A | A | ||
| 0703 | MISSION IDS UPGRADE REV B | A | ||
| 0704 | DC COMPUTER UPGRADE WI REV A | A | ||
| 0705 | ADCP REFURBISHMENT WI REV B | A | ||
| 0706 | CCTV CAMERA UPGRADE REV C | A | ||
| 0707 | HiPAP REFURBISHMENT WI B | A | ||
| 0708 | TEST ROOM FO CABLING | A |
| SECTION 0900 |
| DRYCODKING AND DOCKING |
| 0901 | DOCKING AND UNDOCKING | A | ||||
| 0902 | SEA CHEST AND STRAINER PLATES | A | ||||
| 0903 | UNDERWATER HULL PRESERVATION | A | ||||
| 0904 | ANCHORS AND CHAINS INSPECTION | A | ||||
| 0905 | RUDDER AND BILGE KEEL EXAMINATION | A | ||||
| 0907 | CATHODIC PROTECTION SYSTEM INSPECTION | A | ||||
| 0908 | PROPELLOR POLISH AND EXAMINATION | A | ||||
| 0909 | TRANSDUCER DOMES CLEAN AND INSPECT | A | ||||
| 0911 | DOCKING EXTENSION | B | ||||
| 0926 | STEEL RENEWAL | B |
(End of Summary of Changes) image1.wmf