RFC QandA 1 Solicitation N3220521R4170.pdf
PDF 103 KB Posted
- Attached to
- ZEUS ROH/DD Federal contract opportunity
- Solicitation number
- N3220521R4170
About this file
This document contains questions and answers regarding solicitation N3220521R4170 for the regular overhaul and dry docking of the USNS ZEUS (T-ARC 7). The Military Sealift Command will modify clause 52.211-11 in the solicitation to cap liquidated damages at 50% of the contract value not exceeding $107,508 per calendar day of delay. The requirement is for the regular overhaul and dry docking of the USNS ZEUS (T-ARC 7) to be conducted in accordance with the terms set forth in solicitation N3220521R4170 and its attachments.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N3220521R4170
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
QUESTION:
1. 52.211-11 LIQUIDATED DAMAGES--SUPPLIES, SERVICES, OR RESEARCH AND
DEVELOPMENT (SEP 2000)
(a) If the Contractor fails to deliver the supplies or perform the services within the time specified in this contract, the Contractor shall, in place of actual damages, pay to the Government liquidated damages of $107,508.00 per calendar day of delay [Contracting Officer insert amount].
MSC has agreed to modifying the above paragraph to cap the liquidated damages to 50% of the contract value. Can this be reflected in this solicitation?
ANSWER:
Clause 52.211-11 will be changed to the following:
52.211-11 LIQUIDATED DAMAGES--SUPPLIES, SERVICES, OR RESEARCH AND
DEVELOPMENT (SEP 2000)
(a) If the Contractor fails to deliver the supplies or perform the services within the time specified in this contract, the Contractor shall, in place of actual damages, pay to the Government liquidated damages not exceeding $107,508.00 per calendar day of delay. Total Liquidated Damages shall not exceed 50% of the contract value.
(b) If the Government terminates this contract in whole or in part under the Default--Fixed-Price Supply and Service clause, the Contractor is liable for liquidated damages accruing until the Government reasonably obtains delivery or performance of similar supplies or services. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(c) The Contractor will not be charged with liquidated damages when the delay in delivery or performance is beyond the control and without the fault or negligence of the Contractor as defined in the Default--Fixed-Price Supply and Service clause in this contract.
(End of clause)