Q_AND_A_Responses_9.pdf

PDF 7 KB Posted

Attached to
USNS RICHARD E. BYRD: REGULAR OVERHAUL and DRY DOCKING (ROH/DD) Federal contract opportunity
Solicitation number
N32205-17-R-4207
Issued by
Department of the Navy Military Sealift Command

About this file

Q & A Responses 9

View the file

Other files for this federal contract opportunity

Other files attached to USNS RICHARD E. BYRD: REGULAR OVERHAUL and DRY DOCKING (ROH/DD), newest first.
File Type Posted
Q_AND_A_Responses_10.pdf PDF
N32205-17-R-4207_Amendment_0005.pdf PDF
Q_AND_A_Responses_8.pdf PDF
J_-_2_Category_A_Items_Rev.xlsx XLSX spreadsheet
N32205-17-R-4207_Amendment_0004.pdf PDF
Q_AND_A_Responses_7.pdf PDF
Q_AND_A_Responses_4_revised.pdf PDF
Q_AND_A_Responses_6.pdf PDF
Q_AND_A_Responses_5.pdf PDF
Q_AND_A_Responses_4.pdf PDF
Q_AND_A_Responses_3.pdf PDF
Q_AND_A_Responses_2.pdf PDF
N32205-17-R-4207_Amendment_0003.pdf PDF
N32205-17-R-4207_Amendment_0002.pdf PDF
J_-_3_Category_B_Items_USNS_RICHARD_BYRD.xls XLS spreadsheet
J_-_2_Category_A_Items_Rev.xlsx XLSX spreadsheet
Q_AND_A_Responses_1.pdf PDF
N32205-17-R-4207_Amendment_0001.docx DOCX document
J_Attachments.zip ZIP file
RICHARD_BYRD_FBO_Solicitation.pdf PDF
J-6_BYRD_CDRLS.zip ZIP file
USNS_RICHARD_E_BYRD_J&A.pdf PDF
N32205-17-R-4207_Non-Disclosure_Agreement.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-17-R-4207

QUESTIONS AND ANSWERS #9

The following are answers to questions received from potential offerors. The answers provide clarification only and DO

NOT constitute an amendment to the solicitation.

QUESTION #1:

In Q&A Response #3, Contractors were directed to procure the material in as stated in paragraph Work Item 1001, Paragraph

4.4 from Lake Shore Systems.

Contractor has received pricing for the materials, but wanted to advise the Government that some of the components have lead times of 11 week or more.

Recommend these be procured as soon as possible by the Government.

ANSWER:

Government will make efforts to procure the material but advise Contractor to procure material as stated in the Work Item.