About this file

This Invitation for Bids (IFB) issued by the Maryland School for the Deaf seeks a qualified HVAC contractor to provide monthly preventative maintenance services at its Frederick campus located at 101 Clarke Place, Frederick, Maryland 21701. The scope of work includes monthly HVAC inspections and preventative maintenance on multiple boilers, chillers, cooling towers, water heaters, air compressors, and related equipment across various campus buildings. The contractor must also perform semi-annual pneumatics and controls calibration, annual chiller and cooling tower preparation and maintenance in April, annual boiler preparation for state inspection in July, and seasonal boiler preparation in September. The contractor must provide emergency service on a 24/7 basis with a four-hour response time. A pre-bid conference is scheduled for July 27, 2026, at 1:00 p.m. local time at the Support Services Building. Questions must be submitted by August 7, 2026, at 5:00 p.m., and bids are due by August 21, 2026, at 10:00 a.m. local time with public bid opening at that same time and location. The contract term runs from September 1, 2026, through June 30, 2027, with two optional one-year renewal periods extending through June 30, 2029.

Bidders must demonstrate minimum qualifications including at least ten years of HVAC servicing experience and a current Maryland HVACR license, along with familiarity with all specified equipment and three professional references submitted on Attachment L. Pricing shall be submitted on a Firm Fixed Price basis with Work Orders available on a Time & Materials or Fixed Price basis, with separate hourly rates for normal business hours and after-hours service (before 7:00 a.m., after 3:30 p.m. Monday-Friday, and all day Saturday-Sunday). This procurement has been designated for a small business preference, allowing small businesses to submit bids up to 5 percent higher than the lowest non-small-business bid, with higher preferences for veteran-owned (7 percent) and disabled-veteran-owned (8 percent) small businesses. No federal funding is involved, and no MBE, DBE, or VSBE subcontracting goals have been established. The contractor must maintain commercial general liability insurance of $1,000,000 per occurrence/$3,000,000 aggregate and workers' compensation insurance of $1,000,000 per occurrence, with the State listed as an additional insured. Award will be made to the responsible bidder submitting the lowest responsive bid price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HVAC Preventative Maintenance Frederick Solicitation #: MSDFC27FAC01 IFB Document

IFB for Maryland School for the Deaf Page 1 of 32

STATE OF MARYLAND

MARYLAND SCHOOL FOR THE DEAF

(MSD)

INVITATION FOR BIDS (IFB)

HVAC PREVENTATIVE MAINTENANCE FREDERICK

IFB NUMBER MSDFC27FAC01

ISSUE DATE: JULY 15, 2026

A Prospective Bidder that has received this document from a source other than eMarylandMarketplace Advantage (eMMA) https://procurement.maryland.gov should register on eMMA https://emma.maryland.gov/

NOTICE TO BIDDERS

SMALL BUSINESS PREFERENCE PROCUREMENT

This procurement has been designated for a small business preference under COMAR 21.11.01.05. The procurement agency will accept the most favorable responsive bid from a responsible small business (COMAR 21.01.02.01B(80)) if the bid of the small business does not exceed the most favorable responsive bid received from a responsible bidder who is not a small business by: (1) more than 5 percent;

(2) more than 7% for a veteran-owned small business; (3) more than 8% for a disabled-veteran-owned small business; or (4) the percentage otherwise identified in the solicitation as the small business preference.

MINORITY BUSINESS ENTERPRISES ARE ENCOURAGED TO RESPOND TO THIS

SOLICITATION.

https://procurement.maryland.gov/ https://emma.maryland.gov/

IFB for Maryland School for the Deaf Page 2 of 32

KEY INFORMATION SUMMARY SHEET (KISS)

Invitation for Bids Maintenance – HVAC Preventative Maintenance Frederick

Solicitation Number:

MSDFC27FAC01

IFB Issue Date: July 15, 2026

IFB Issuing Office:

Maryland School for the Deaf (MSD or the “Agency”)

Procurement Officer:

Chloe Moyer 101 Clarke Pl Frederick, MD 21701

Email:

Phone Number:

chloe.moyer@msd.edu

301-360-2011

Bids are to be sent to:

Submit on emma.maryland.gov under Solicitation Number

MSDFC27FAC01

To submit a bid, bidders must first register on emma.maryland.gov. We recommend registering in advance to become acquainted with the site.

No Bid Notice Feedback Form

If you are not submitting a bid for this solicitation, submit Attachment 1 with your reasons why.

Pre-Bid Conference:

July 27th, 1:00pm Local Time, at Maryland School for the Deaf Support Services Building 240 S Market St Frederick, MD 21701 See Section 4.3 for additional details.

See Attachment 2 to RSVP by July 24th. At 5pm EST Local Time

Scheduled Site Visit

The Site Visit will be conducted at the Pre-Bid Conference. There will not be a separate Site Visit.

Questions Due Date and Time:

August 7th, 5:00 pm Local Time

IFB for Maryland School for the Deaf Page 3 of 32

Bid Due (Closing) Date and Time:

August 21st, 10:00 am Local Time Bidders are reminded that a completed Feedback Form is requested if a no-bid decision is made (see Attachment 1 - No Bid Notice/Vendor Feedback Form).

Public Bid Opening Date, Time, and Location

August 21st, 10:00 am Local Time 101 Clarke Pl Frederick, MD 21701

MBE or DBE Subcontracting Goal:

An overall Minority Business Enterprise (MBE) or Disadvantaged Business Enterprise (DBE) subcontract participation goal of _0%____ percent of the total contract dollar amount, including all renewal option terms, if any, has been established for this procurement. The overall MBE or DBE subcontract participation goal includes the following subgoals, which have been established for this procurement:

_____% for African-American MBEs;

_____% for Asian-American MBEs;

_____% for Hispanic-American MBEs; and

_____% for Woman-Owned MBEs.

VSBE

Subcontracting Goal:

This solicitation includes a VSBE participation Goal of ____0%

Procurement Method:

A Contract will be awarded in accordance with the Competitive Sealed Bidding method under COMAR 21.05.02.

Multiple or Alternate Bids:

Multiple or alternate Bids will not be accepted.

Contract Type: Firm Fixed Price with Work Orders of Time & Materials and Fixed Price

Contract Duration:

One year base period with two option periods of one year each.

Base period is from September 1st, 2026 to June 30th, 2027.

First option period is from July 1st, 2027 to June 30th, 2028.

Second option period is from July 1st, 2028 to June 30th, 2029.

IFB for Maryland School for the Deaf Page 4 of 32

Primary Place of Performance:

101 Clarke Pl Frederick, MD 21701

SBR Designation: No

Federal Funding: No

IFB for Maryland School for the Deaf Page 5 of 32

Table of Contents - IFB

1 7

1.1 7

2 8

2.1 8

2.2 8

2.4 12

3 15

3.1 15

3.2 15

3.3 15

3.4 17

3.5 17

3.6 19

3.7 19

3.8 19

3.9 19

3.10 20

3.11 20

3.12 20

3.13 20

4 22

4.1 22

4.2 22

4.3 22

4.4 23

4.5 23

4.6 23

4.7 23

4.8 24

4.9 24

4.10 24

IFB for Maryland School for the Deaf Page 6 of 32

4.11 24

4.12 24

4.13 25

4.14 25

4.15 25

4.16 26

4.17 26

4.18 26

4.19 26

4.20 29

4.21 29

4.22 29

4.23 29

4.24 30

4.25 30

5 32

5.1 32

5.2 33

IFB for Maryland School for the Deaf Page 7 of 32

1 Minimum Qualifications

1.1 Bidder Minimum Qualifications

The Bidder must document in its Bid that it satisfies the following Minimum Qualifications:

A. The Bidder shall have been in the business of servicing HVAC equipment for at least ten (10) years and be licensed in the State of Maryland. The Bidder shall provide a HVACR (Heating, Ventilation, Air Conditioning, and Refrigeration) license for the State of Maryland.

B. The bidder must be familiar/trained with all Equipment listed in 2.3.29 of this solicitation.

C. The Bidder shall provide with its Bid "Attachment L Reference Checks" with three (3) references filled out.

THE REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK.

IFB for Maryland School for the Deaf Page 8 of 32

2 Contractor Requirements: Scope of Work

2.1 Summary Statement

2.1.1 This Invitation for Bids (IFB) is issued to procure the goods or services, as specified in this Section 2, from a contract between the successful bidder(s) and the State of Maryland (“State”): the Maryland School for the Deaf is seeking a vendor to provide monthly HVAC preventative maintenance at its Frederick campus.

It is the State’s intention to obtain goods and services, as specified in this IFB, from a contract between the selected Bidder and the State.

2.1.2 This is a single IFB award. See IFB Section 4.21 Bid Evaluation Criteria and Award Basis for more Contract award information.

2.1.3 A Contract award does not ensure a Contractor will receive all or any State business under the Contract.

2.2 Background and Purpose

Monthly preventative maintenance is essential to keep the HVAC systems operating properly. A lack of preventative maintenance can lead to disruptions in operation, and/or unnecessary future maintenance costs due to neglected issues.

2.2.1 Project Goals

The vendor will provide thorough HVAC preventative maintenance completed by experienced technicians. The vendor must report all deficiencies to the Maintenance Department with proper diagnosis and resolutions that will keep the HVAC equipment operating.

2.2.2 State Staff and Roles

In addition to the Procurement Officer and Contract Monitor, the Maintenance Supervisor will be a point of contact with the vendor.

The Maintenance Supervisor is responsible for:

A. Coordinating and scheduling monthly visits from the vendor.

B. Receiving reports from the vendor about any issues identified with the machinery.

C. Approving Work Orders for repairs under $5,000.

2.2.3 Other State Responsibilities

Not applicable to this IFB

2.3 Contractor Responsibilities and Tasks

2.3.1 Send a schedule of checklist for equipment to the Maintenance Supervisor before the start of HVAC contract.

2.3.2 The contractor must provide a list of deficiencies at the end of their first yearly inspection/service. Any item not listed as a deficiency at that time the vendor assumes responsibility for the repair/replacement up to $5,000. The school reserves the right to repair/replace or not to repair/replace at that time. The school also can obtain other vendors to provide the corrective

IFB for Maryland School for the Deaf Page 9 of 32 measures. The school has the right to verify the list of deficiencies. All repairs must be approved by the Maintenance Supervisor.

2.3.3 Annually prepare all campus boilers for State inspection after the heating season is over, including cleaning both fire and water sides, installing gauge glasses, gasketing and making necessary repairs to the fire box. Clean flue and intake piping as necessary. These inspections should be done in July of each year.

2.3.4 Prepare all boilers for seasonal operation in September of each contract year including cleaning and adjusting burners to ensure peak efficiency utilizing a Bacharach or similar combustion analyzer, checking all pumps and valves (including relief, control and pressure regulator valves) for leaks and proper operation. Lubricate pumps and motors per recommended practice. Provide the school with a written report of the combustion analyzer report. This inspection report should be complete in October or November.

2.3.5 All Monthly Preventative Maintenance inspections should be completed by the end of the 2nd full week, if the vendor cannot meet this commitment, it must be mutually agreed upon with the Maintenance Supervisor to move the inspection to another date.

2.3.6 Perform system analysis on all domestic water heaters 2x per year.

2.3.7 Perform a system check once a month during the heating season (heating season is October - April.

2.3.7a Perform a system check once a month during the cooling season (May - September) on all equipment listed in Section 2.3.29. The list will include Chillers, Cooling towers, etc.

2.3.8 Servicing and calibrating pneumatics and all controls, including T-stats and air compressors in this HVAC/PM contract. MSD will have this inspection completed semiannually, in July and December of each year of the contract.

2.3.9 Emergency service may be required to keep the School operational. Emergency service shall be provided on a twenty-four (24) hour per day, seven (7) days per week basis. The contractor shall respond within four (4) hours on the same day after receiving a request for emergency service by providing a qualified service technician to accomplish necessary emergency repairs. The contractor shall provide one telephone number where a designated representative can be contacted in case of an emergency. The Hourly rate will be the rate listed on the bid form for service during normal business hours. For after-hours, rate will be the rate listed on the bid form for after-hours service after normal business hours.

2.3.10 After hours is considered to be before 7:00 am and after 3:30 pm Monday thru Friday, and all day on Saturday and Sunday. Any work performed after hours, the rate(s) will be those on the bid form. These rates will be for the duration of the contract.

2.3.11 Appropriate, non-offensive clothing is to be worn by any and all contractors, subcontractors, and their representatives.

2.3.12 There is no tobacco use on school grounds.

2.3.13 All Contractors must sign in/out and must wear a contractor badge.

2.3.14 Work must be inspected by the Maintenance Supervisor before payment will be made.

2.3.15 On the monthly inspection report information must include: Date of inspection, Time of Inspection (clock in and clock out), and List of equipment inspected.

IFB for Maryland School for the Deaf Page 10 of 32

2.3.16 Contractor must be familiar with the Metasys system and the Siemens system including HVAC and BAS systems.

2.3.17 The Maryland School for the Deaf reserves the right to accept or reject any contractor’s employee during the contract.

HVAC Preventive Maintenance/start up for chillers and cooling towers:

2.3.18 Clean and prepare all campus chillers and cooling towers annually. in the month of April, or other date by the maintenance supervisor. This includes flushing of all water systems checking cooling tower belts and motors for proper wear and operation. Also, the contractor must check alignment of all belts. Including the inspection of bolts, which should be changed after 3 years of operation. Checking spray nozzles on the cooling towers for proper flow, verifying that they are working correctly, cleaning if needed.

2.3.19 Contractor will lubricate all bearings where applicable. Brush all tubes using a wet type power brush, no dry brushes allowed. Per manufacturer's recommendations the contractor will be cleaning the strainers, water filters and checking pumps for proper operation. Clean cooling towers by flushing down fill kit, cleaning sumps and sump strainers out.

2.3.19 Contractor must provide the maintenance supervisor with a written list of deficiencies and necessary repairs. All repairs, if approved by the Maryland School for the Deaf will be handled on a time and material basis.

2.3.20 Contractor must perform an annual laboratory oil analysis for each chiller and provide the school with a written report on the oil production.

2.3.21 Contractor must check freon levels in each chiller. if found low, notify the maintenance supervisor in writing. If more freon or repairs are needed, then this will be done on a time and material basis. Start up and run all chillers and cooling towers, checking for proper operation. This could require a second trip to the school if weather conditions prevent the start up on the day they are being serviced.

On call/emergency maintenance:

2.3.22 Contractor will Provide hourly rate and material markup percentage to perform emergency on call repairs.

2.3.23 Rates should be provided for normal working hours as well as after hours, weekend and holiday rates. Contractor will be required to respond to campus within 4 hours of a trouble call.

2.3.24 Emergency service may be required to keep the School operational. Emergency service shall be provided on a twenty-four (24) hour per day, seven (7) days per week basis. The contractor shall respond within four (4) hours on the same day after receiving a request for emergency service by providing a qualified service

IFB for Maryland School for the Deaf Page 11 of 32 technician to accomplish necessary emergency repairs.

2.3.25 The contractor shall provide one telephone number where a designated representative can be contacted in case of an emergency.

2.3.26 The Hourly rate will be the rate listed on the bid form for service during normal business hours. For after-hours, rate will be the rate listed on the bid form for after-hours service after normal business hours.

2.3.27 After hours is considered to be before 7:00 am and after 3:30 pm Monday thru Friday, and all day on Saturday and Sunday. Any work performed after hours will be paid based on the after hours rate on the bid form.

These rates will be for the duration of the contract.

2.3.28 Examples of typical call ins:

• No heat in a campus building

• Boiler not cycling on

• No hot water in dormitory building

2.3.29 Equipment Serviced:

• Ambrosen building:

1. Boiler: Patterson Kelly Boilers model #SONIC - SC650

• Bjorlee Museum:

1. Boiler: Weil McClain model #P-578-W-steam

• Ely Building:

1. 2- Boilers: Thermal Solutions Model# EVH2000BN1-UAF.

2. I-Water Heater: A.O. Smith Model# BTH 150 966

3. I-Water Heater: A.O. Smith Model# BTH 150 200

4. Air Compressor: Honeywell model# 230

5. Air Compressor: Honeywell model #230

6. Cooling Tower: EvapCo model# ESW4 12-46N12-SP

7. Chiller: WaterFurnace TruClimate 300 model# SPLC4050U240B

• Faupel Hall, Foxwell Moylan, Klipp Redmond dormitories:

1. Boiler: Patterson Kelly Boilers model #SONIC - SC650 (2 units in each building) for a total of 6

• ljams-Vance Cafeteria:

1. Boiler: Lochinvar Power-Fin Model# PBN1002

IFB for Maryland School for the Deaf Page 12 of 32

2. Water Heater: A.O. Smith Model# BT 65 200

• Benson Gymnasium:

1. Boiler: Smith Model 28A08 (3 units in building) - hot water

2. Burner: Power Flame Model C2-GO-20A(3)

3. Air Dryer: Quincy Dual Pump Model# NA

• Kent McCanner Building:

1. Boilers: Smith Cast Iron Model 3500A-S/W-10 (2 in building)

2. Burner: Power Flame Model # C2-G-20B (2 in building)

3. Chiller: York Model# YKCQCQQ3-CHG

4. Cooling Tower: B.A.C. Model# VTL-272

• Veditz Building:

1. Boilers: Lochinvar Model FBN2001 (2 in building)

2. Chiller: York Model# YLAA0139HJ17

2.3.30 The listing of maintenance tasks and procedures to be performed is not intended to be All Inclusive. Rather, it is intended to be representative of the scope of maintenance service to be provided. Omission of the description of specific task or of identification of specific equipment or system components does not relieve the Contractor of the responsibility for maintenance of any part of the HVAC systems and all associated operating, distributing and controlling equipment, devices or components.

2.3.31 All equipment must be serviced to manufacturer's specifications or The Maryland School for the Deaf’s Maintenance Dept.

2.4 Contract Information

A. Payment Information

See Section 3.3 for Invoicing and Sections 3.6 and 3.7 for Payment Policies B. Work Orders

See Section 3.5 for Work Orders C. Security Requirements

See Section 2.5.1 for Security Requirements D. Insurance Requirement

See Section 3.13 for Insurance Requirement

IFB for Maryland School for the Deaf Page 13 of 32

2.5 Supplemental Category of Work Requirements and Responsibilities: Facilities Maintenance Supplemental

This supplemental contains additional requirements under Section 2 of the solicitation.

2.5.1 Security Requirements

The following requirements are applicable to the Contract:

2.5.1.1 Employee Identification

a. Contractor Personnel shall display his or her company ID badge in a visible location at all times while on State premises. Upon request of authorized State personnel, each Contractor Personnel shall provide additional photo identification.

b. Contractor Personnel shall sign in at the Maintenance Office at the beginning of each site visit.

c. Contractor shall remove any Contractor Personnel from working on the Contract where the State determines, in its sole discretion, that Contractor Personnel has not adhered to the Security requirements specified herein.

d. The State reserves the right to request that the Contractor submit proof of employment authorization of non-United States Citizens, prior to commencement of work under the Contract.

2.5.2 Security Clearance / Criminal Background Check

The State reserves the right to refuse any individual Contractor Personnel to work on State premises, based upon certain specified criminal convictions, as specified by the State.

A criminal background check is not required for Contractor Personnel.

A security clearance is not required for Contractor Personnel.

2.5.3 On-Site Security Requirement(s)

THIS SECTION IS INAPPLICABLE TO THIS IFB.

2.5.4 Mercury and Products That Contain Mercury

All products or equipment provided pursuant to this solicitation shall be mercury-free products. The Bidder/Offeror must submit a Mercury Affidavit in the form of Attachment J with its Bid/Proposal.

2.5.5 Department of Human Services (DHS) Hiring Agreement

This solicitation does not require a DHS Hiring Agreement.

IFB for Maryland School for the Deaf Page 14 of 32

IFB for Maryland School for the Deaf Page 15 of 32

3 Standard Terms and Conditions

3.1 Contract Initiation Requirements

Once all approvals have been obtained and the Contract is fully executed, the Procurement Officer may schedule a kickoff meeting to be held prior to commencement of Contract performance.

3.2 End of Contract Transition

The Contractor shall cooperate in the orderly transition of services from it to a subsequent contractor at the end of the contract term or upon receipt of a Notice of Termination from the State. Transition shall be provided in a prompt and timely manner and shall proceed in accordance with the schedule provided to the Contractor by the State in the Notice of Transition. Additional instructions regarding transition services may be provided in the event of a Notice of Termination issued by the State.

3.3 Invoicing

Submission of an invoice constitutes the Contractor’s verification that the information in the invoice is accurate as of the time of submission.

An invoice not satisfying the requirements of a Proper Invoice (as defined in COMAR 21.06.09) will not be processed for payment. To be considered a Proper Invoice, invoices must include the following information, without error:

A. Contractor name and address;

B. Remittance address;

C. Federal taxpayer identification (FEIN) number, social security number, as appropriate;

D. Invoice period (i.e. time period during which services covered by invoice were performed);

E. Invoice date;

F. Invoice number;

G. State assigned Contract number;

H. State assigned (Blanket) Purchase Order number(s);

I. Goods or services provided;

J. Amount due; and

K. Any additional documentation required by regulation or the Contract.

Invoices that contain both fixed price and labor hour or time and material items shall clearly identify each item as either fixed price, and labor hour, or time and material billing.

The State reserves the right to reduce or withhold Contract payment in the event the Contractor does not provide all required deliverables within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.

IFB for Maryland School for the Deaf Page 16 of 32

The State is generally exempt from federal excise taxes, Maryland sales and use taxes, District of Columbia sales taxes and transportation taxes. The Contractor, however, is not exempt from such sales and use taxes and may be liable for the same.

Invoices for final payment shall be clearly marked as “FINAL” and submitted when all work requirements have been completed and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than 60 calendar days from the Contract termination date.

3.3.1 Invoice Submission Schedule

The Contractor shall submit invoices in accordance with the following schedule:

A. For Items of work for which there is annual pricing (see Attachment B–The Price Form), those items shall be billed in equal monthly installments for the applicable Contract year in the month following the performance of the services.

B. Invoices for work performed on a labor hour or time and materials basis shall be submitted on or before the 10th business day of the month following the end of the invoice period.

3.3.2 Deliverable Invoicing

Not applicable to this Solicitation.

3.3.3 Labor Hour/Time and Materials Invoicing

All labor hour/time and material invoices shall be accompanied by a timesheet signed by the Contract Monitor as described below and notice(s) of acceptance issued by the State: DPAF for each time period invoiced (see online example at http://doit.maryland.gov/contracts/Documents/_procurementForms/DeliverableProductAccept anceForm-DPAFsample.pdf)>>. Include for each person covered by the invoice the following, individually listed per person: name, hours worked, hourly labor rate, invoice amount and a copy of each person’s timesheet for the period signed by the Contract Monitor.

1. Materials Reporting

Submit evidence to support the cost of materials and that billing on the invoice is consistent with the requirements stated in Section 2 of the IFB.

A. For the purposes of the Contract an amount will not be deemed due and payable if:

B. The amount invoiced is inconsistent with the Contract;

C. The proper invoice has not been received by the party or office specified in the

Contract;

D. The invoice or performance is in dispute or the Contractor has failed to otherwise comply with the provisions of the Contract;

E. The item or services have not been accepted;

F. The quantity of items delivered is less than the quantity ordered;

G. The items or services do not meet the quality requirements of the Contract;

H. If the Contract provides for progress payments, the proper invoice for the progress payment has not been submitted pursuant to the schedule;

I. If the Contract provides for withholding a retainage and the invoice is for the retainage, all stipulated conditions for release of the retainage have not been met; or J. The Contractor has not submitted satisfactory documentation or other evidence reasonably required by the Procurement Officer or by the Contract concerning performance under the Contract and compliance with its provisions.

IFB for Maryland School for the Deaf Page 17 of 32

3.3.4 Travel Reimbursement

Travel will not be reimbursed under this IFB.

3.4 Liquidated Damages

3.4.1 MBE Liquidated Damages

Inapplicable because there is no MBE goal for this IFB.

3.4.2 Liquidated Damages other than MBE

This section is inapplicable to this IFB.

3.4.3 Problem Escalation Procedure

No later than ten (10) Business Days after notice of recommended award or after the date of the Notice to Proceed, whichever is earlier, the Contractor must provide, and thereafter, maintain a Problem Escalation Procedure (PEP) for both routine and emergency situations. The PEP must state how the Contractor will address problem situations as they occur during the performance of the Contract, especially problems that are not resolved to the satisfaction of the State within appropriate timeframes and must include:

A. Contact information B. The process for establishing the existence of a problem;

C. Names, titles, and contact information for progressively higher levels of personnel in the Contractor’s organization who would become involved in resolving a problem;

D. For each individual listed in the Contractor’s PEP, the maximum amount of time a problem will remain unresolved with that individual before the problem escalates to the next contact person listed in the Contractor’s PEP;

E. Expedited escalation procedures and any circumstances that would trigger expediting them;

F. The method of providing feedback on resolution progress, including the frequency of feedback to be provided to the State;

G. Contact information for persons responsible for resolving issues after normal business hours (e.g., evenings, weekends, holidays) and on an emergency basis; and

H. A process for updating and notifying the Contract Monitor of any changes to the PEP.

I. The PEP must be updated within ten (10) Business Days after any change in circumstance which changes the PEP but not less than annually within ten (10) Business Days after the start of each Contract year .

Nothing in this section shall be construed to limit any rights of the Contract Monitor or the State which may be allowed by the Contract or applicable law.

3.5 Work Orders

A. Additional services and resources will be provided via a Work Order process. Work shall not begin in advance of a fully executed Work Order. A Work Order may be issued for either fixed price or time and material contract (T&M). T&M Work Orders will be issued in accordance with pre-approved Labor Categories with the fully loaded rates on the Attachment B – The Price Form.

B. Work Order Requests (See sample at http://doit.maryland.gov/contracts/Documents/_procurementForms/WorkOrderSample.pd http://doit.maryland.gov/contracts/Documents/_procurementForms/WorkOrderSample.pdf

IFB for Maryland School for the Deaf Page 18 of 32

f) for the provision of services or resources that are within the scope of this IFB will be issued to the Contractor. The Work Order Request will include:

1) Technical requirements and description of the service or resources needed;

2) Performance objectives and/or deliverables, as applicable;

3) Due date and time for submitting a response to the request; and

4) Required place(s) where work must be performed.

C. The Contractor shall e-mail a response to the Contract Monitor within the specified time and include at a minimum:

1. A response that details the Contractor’s understanding of the work;

2. A price to complete the Work Order Request using the format provided (see online sample).

3. A description of proposed resources required to perform the requested tasks, with labor categories listed in accordance with Appendix 3.

4. An explanation of how tasks shall be completed. This description shall include proposed subcontractors and related tasks.

5. Contractor’s expectations for State-furnished information, work site, and/or access to equipment, facilities, or personnel

6. The proposed personnel resources, including any subcontractor personnel, to complete the task.

D. For a T&M Work Order, the Contract Monitor will review the response and will confirm the proposed labor rates are consistent with this IFB. For a fixed price Work Order, the Contract Monitor will review the response and will confirm the proposed prices are acceptable.

E. The Contract Monitor may contact the Contractor to obtain additional information, clarification or revision to the Work Order, and will provide the Work Order to the Procurement Officer for a determination of compliance with the Contract and a determination whether a change order is appropriate. Written Procurement Officer approval is required before Work Order execution by the State.

F. Proposed personnel on any type of Work Order shall be subject to the State’s prior approval. The Contractor shall furnish resumes of proposed personnel specifying the labor category(ies) proposed. The Contract Monitor shall have the option to interview the proposed personnel and, in the event of an interview or not, shall notify the Contractor of acceptance or denial of the personnel.

G. Performance of services under a Work Order shall commence consistent with an NTP issued by the Contract Monitor for such Work Order.

The Blanket Purchase Order (BPO) issued as a result of this solicitation, and any subsequent amendments, modifications or options issued relevant to this solicitation or BPO, complies with all the terms, conditions and specifications issued with this solicitation and is incorporated in and made part of the Contract – see Exhibit 2 - Sample Contract.

http://doit.maryland.gov/contracts/Documents/_procurementForms/WorkOrderSample.pdf

IFB for Maryland School for the Deaf Page 19 of 32

3.6 Payments by Electronic Funds Transfer

By submitting a Bid in response to this solicitation, the Bidder, if selected for award:

Agrees to accept payments by electronic funds transfer (EFT) unless the State Comptroller’s Office grants an exemption. Payment by EFT is mandatory for contracts exceeding $200,000. The successful Bidder shall register using the COT/GAD X-10 Vendor Electronic Funds (EFT) Registration Request Form.

Any request for exemption must be submitted to the State Comptroller’s Office for approval at the address specified on the COT/GAD X-10 form, must include the business identification information as stated on the form, and must include the reason for the exemption. The COT/GAD X-10 form may be downloaded from the Comptroller’s website at:

http://comptroller.marylandtaxes.com/Vendor_Services/Accounting_Information/Static_Files/GA DX10Form20150615.pdf.

3.7 Prompt Payment Policy

This procurement and the Contract(s) to be awarded pursuant to this solicitation are subject to the Prompt Payment Policy Directive issued by the Governor’s Office of Small, Minority & Women Business Affairs (GOSBA) and dated August 1, 2008. Promulgated pursuant to Md. Code Ann., State Finance and Procurement Article, §§ 11-201, 13-205(a), and Title 14, Subtitle 3, and COMAR 21.01.01.03 and 21.11.03.01, the Directive seeks to ensure the prompt payment of all subcontractors on non-construction procurement contracts. The Contractor shall comply with the prompt payment requirements outlined in the Contract, Section 31 “Prompt Pay Requirements” (see Exhibit 2 - Sample Contract). Additional information is available on GOSBA’s website at:

http://www.gomdsmallbiz.maryland.gov/documents/legislation/promptpaymentfaqs.pdf.

3.8 Federal Funding Acknowledgement

This Contract does not contain federal funds.

3.9 Conflict of Interest Affidavit and Disclosure

The Bidder shall complete and sign the Conflict of Interest Affidavit and Disclosure (Attachment I) and submit it with its Bid.

By submitting a Conflict of Interest Affidavit and Disclosure, the Contractor shall be construed as certifying all Contractor Personnel and subcontractors are also without a conflict of interest as defined in COMAR 21.05.08.08A.

Additionally, a Contractor has an ongoing obligation to ensure that all Contractor Personnel are without conflicts of interest prior to providing services under OR individual Task Orders issued under the Contract. For policies and procedures applying specifically to Conflict of Interests, the Contract is governed by COMAR 21.05.08.08.

Participation in Drafting of Specifications: Disqualifying Event: Bidders are advised that Md. Code Ann. State Finance and Procurement Article §13-212.1(a) provides generally that “an individual who assists an executive unit in the drafting of specifications, an invitation for bids, a request for proposals for a procurement, or the selection or award made in response to an invitation for bids or a request for proposals, or a person that employs the individual, may not: (1) submit a bid or proposal for that procurement; or (2) assist or represent another person, directly or indirectly, who is submitting a bid

IFB for Maryland School for the Deaf Page 20 of 32 or proposal for that procurement.” Any Bidder submitting a Bid in violation of this provision shall be classified as “not responsible.”

3.10 Non-Disclosure Agreement

3.10.1 Non-Disclosure Agreement (Bidder/Offeror)

A Non-Disclosure Agreement (Bidder/Offeror) is not required for this procurement.

3.10.2 Non-Disclosure Agreement (Contractor)

A Non-Disclosure Agreement (Contractor) is not required for this procurement.

3.11 Maryland Healthy Working Families Act Requirements

On February 11, 2018, the Maryland Healthy Working Families Act went into effect. All Bidders should be aware of how this Act could affect your potential contract award with the State of Maryland. See the Department of Labor, Licensing and Regulations website for Maryland Healthy Working Families Act Information: https://dllr.state.md.us/paidleave/.

3.12 The State of Maryland’s Commitment to Purchasing Environmentally Preferred Products and Services (EPPs)

Maryland’s State Finance & Procurement Article §14-410 defines environmentally preferable purchasing as “the procurement or acquisition of goods and services that have a lesser or reduced effect on human health and the environment when compared with competing goods or services that serve the same purpose.” Accordingly, Bidders are strongly encouraged to offer EPPs to fulfill this contract, to the greatest extent practicable.

3.13 Insurance Requirements

The Contractor shall maintain, at a minimum, the insurance coverages outlined below, or any minimum requirements established by law if higher, for the duration of the Contract, including option periods, if exercised:

3.13.1 The following type(s) of insurance and minimum amount(s) of coverage are required:

A. Commercial General Liability - One million dollars ($1,000,000) combined single limit per occurrence for bodily injury, property damage, and personal and advertising injury and three million dollars ($3,000,000) annual aggregate. The minimum limits required herein may be satisfied through any combination of primary and umbrella/excess liability policies.

B. Worker’s Compensation - The Contractor shall maintain such insurance as necessary or as required under Workers’ Compensation Acts, the Longshore and Harbor Workers’ Compensation Act, and the Federal Employers’ Liability Act, to not be less than. one million dollars ($1,000,000) per occurrence (unless a state’s law requires a greater amount of coverage). Coverage must be valid in all states where work is performed.

3.13.2 The State shall be listed as an additional insured on the faces of the certificates associated with the coverages listed above, including https://dllr.state.md.us/paidleave/ https://trackbill.com/bill/maryland-house-bill-629-environmentally-preferable-procurement-maryland-green-purchasing-committee/647077/

IFB for Maryland School for the Deaf Page 21 of 32 umbrella policies, excluding Workers’ Compensation Insurance and professional liability.

3.13.3 All insurance policies shall be endorsed to include a clause requiring the insurance carrier to provide the Procurement Officer, by certified mail, not less than 30 days’ advance notice of any non-renewal, cancellation, or expiration. The Contractor shall notify the Procurement Officer in writing, if policies are canceled or not renewed within five (5) days of learning of such cancellation or nonrenewal. The Contractor shall provide evidence of replacement insurance coverage to the Procurement Officer at least 15 days prior to the expiration of the insurance policy then in effect.

3.13.4 Any insurance furnished as a condition of the Contract shall be issued by a company authorized to do business in the State.

3.13.5 The recommended awardee must provide current certificate(s) of insurance with the prescribed coverages, limits and requirements set forth in this section within five (5) Business Days from notice of recommended award. During the period of performance for multi-year contracts, the Contractor shall provide certificates of insurance annually, or as otherwise directed by the Contract Monitor.

3.13.6 Subcontractor Insurance

The Contractor shall require any subcontractors to obtain and maintain comparable levels of coverage and shall provide the Contract Monitor with the same documentation as is required of the Contractor.

IFB for Maryland School for the Deaf Page 22 of 32

4 Bid Submission Information and Instructions

4.1 eMaryland Marketplace Advantage (eMMA) eMMA is the electronic commerce system for the State of Maryland. The IFB, Pre-Bid Conference (Conference)summary and attendance sheet, Bidders’ questions and the Procurement Officer’s responses, addenda, and other solicitation-related information will be made available via eMMA.

To receive a contract award, a vendor must be registered on eMMA. Registration is free. Go to emma.maryland.gov, click on “New Vendor? Register Now” to begin the process, and then follow the prompts.

4.2 Electronic Means

The following transactions related to this procurement and any Contract awarded pursuant to it are not authorized to be conducted by electronic means:

A. Submission of Bond documents determined by the State to require original signatures; or

B. Any transaction, submission, or communication where the Procurement Officer has specifically directed that a response from the Contractor or Offeror be provided in writing or hard copy.

Any e-mail transmission is only authorized to the email addresses for the identified person as provided in the solicitation, the Contract, or in the direction from the Procurement Officer or Contract Monitor.

“Electronic means” refers to exchanges or communications using electronic, digital, magnetic, wireless, optical, electromagnetic, or other means of electronically conducting transactions.

Electronic means includes e-mail, internet-based communications, electronic funds transfer, specific electronic bidding platforms (e.g., https://procurement.maryland.gov), and electronic data interchange.

4.3 Pre-Bid Conference

If a Conference will be held, the date, time, and location is indicated on the Key Information Summary Sheet. Attendance at the Conference is not mandatory, but all interested parties are encouraged to attend in order to facilitate better preparation of their Bids. If the solicitation includes an MBE participating goal, failure to attend the Conference will be taken into consideration as part of the evaluation of a bidder’s good faith efforts if there is a waiver request.

It is highly recommended that all Prime Contractors bring their intended subcontractors to the Conference/Site Visit to ensure that all parties understand the IFB requirements and the socio-economic goals for this solicitation.

MBE subcontractors are encouraged to attend the Conference to market their participation to potential prime contractors.

In order to assure adequate accommodations at the Conference, please email the completed Attachment 2 for those expected to attend the Conference to the Procurement Officer no later than the time and date indicated on the Key Information Summary Sheet. In addition, if there is a need for sign language interpretation or other special accommodations due to a disability, please notify the Procurement Officer at least five (5) Business Days prior to the Conference date. Reasonable effort will be made to provide such special accommodation.

https://emma.maryland.gov/page.aspx/en/usr/login?ReturnUrl=%2fpage.aspx%2fen%2fbuy%2fhomepage https://procurement.maryland.gov/

IFB for Maryland School for the Deaf Page 23 of 32

If the Conference is in person, attendees should bring a copy of the solicitation and a business card to help facilitate the sign-in process.

4.4 Questions

All questions, including concerns regarding any applicable MBE or VSBE participation goals, shall identify in the subject line the Solicitation Number and Title for this IFB and must be submitted in writing via e-mail or eMMA to the Procurement Officer no later than the date and time specified in the Key Information Summary Sheet. The Procurement Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.

4.4.1 Answers to all questions that are not clearly specific only to the requestor will be distributed via the same mechanism as for IFB amendments and posted on eMMA.

4.4.2 The statements and interpretations contained in responses to any questions, whether responded to verbally or in writing, are not binding on the State unless it issues an amendment to the solicitation in writing.

4.5 Bid Due (Closing) Date and Time

Bids must be received by the Procurement Officer no later than the Bid due date and time indicated on the Key Information Summary Sheet to be considered. Except as provided in COMAR

21.05.02.10. Bids received after that date will not be considered. Requests for an extension of this date or time shall not be granted.

For Bids accepted via email, the time stamp to indicate receipt of the Bid by the State, is the posted date and time in the Procurement Officer’s email inbox.

Bids may be modified or withdrawn by written notice received by the Procurement Officer before the time and date set forth in the Key Information Summary Sheet for receipt of Bids.

Potential Bidders not responding to this solicitation are requested to submit the “No Bid/Proposal Notice/Vendor Feedback” form Attachment 1, which includes company information and the reason for not responding (e.g., too busy, cannot meet mandatory requirements).

4.6 Receipt, Opening and Recording of Bids

Upon receipt, each Bid and any timely modification(s) to a Bid shall be stored in a secure place until the time and date set for Bid opening. Before Bid opening, the State may not disclose the identity of any Bidder.

Bids shall be opened publicly at the time, date and place designated in the Key Information Summary Sheet.

The name of each Bidder, the Total Bid Price, and such other information as is deemed appropriate shall be read aloud or otherwise made available and recorded at the time of Bid opening.

4.7 Duration of Bids

Bids submitted in response to this IFB are irrevocable for the latest of the following: 120 days following the Bid due date and time or the date any protest concerning this IFB is finally resolved.

IFB for Maryland School for the Deaf Page 24 of 32

This period may be extended at the Procurement Officer’s request only with the Bidder’s written agreement.

4.8 Revisions to the IFB

4.8.1 All revisions to the IFB before the due date for Bids will be published in an addendum to the IFB and posted on eMMA and reasonable effort will be made to provide such addenda to all prospective Bidders that were sent this IFB or are otherwise known by the Procurement Officer to have obtained this IFB. It is the responsibility of all prospective Bidders to check eMMA for any addenda issued prior to the submission of Bids.

4.8.2 Bidders shall acknowledge in the Bid the receipt of all addenda to this IFB issued before the Bid due date.

4.8.3 Failure to acknowledge receipt of an addendum does not relieve the Bidder from complying with the terms, additions, deletions, or corrections set forth in the addendum, and may cause the Bid to be deemed not responsive.

4.9 Cancellations

4.9.1 This IFB may be cancelled as provided in COMAR 21.06.02.02

4.9.2 The State reserves the right to cancel this IFB, accept or reject any and all Bids, in whole or in part, received in response to this IFB and to waive or permit the cure of minor irregularities.

4.9.3 In the event a government entity proposes and receives the recommendation for award, this procurement may be canceled, and the award processed in accordance with COMAR 21.01.03.01.A(4).

4.9.4 If the services that are the subject of the IFB are currently being provided under an interagency agreement with a public institution of higher education and the State determines that the services can be provided more cost effectively by the public institution of higher education, then the IFB may be canceled in accordance with Md. Code Ann., State Finance and Procurement Art., § 3-207(b)(2).

4.10 Incurred Expenses

The State will not be responsible for any costs incurred by any Bidder in preparing and submitting a Bid or performing any other activities related to submitting a Bid in response to this solicitation.

4.11 Protest/Disputes

Any protest or claim related to this IFB or the Contract award hereunder shall be subject to the provisions of COMAR 21.10 (Administrative and Civil Remedies).

4.12 Bidder Responsibilities

4.12.1 A Bidder, either directly or through its subcontractor(s), must be able to provide all goods and services and meet all of the requirements requested

IFB for Maryland School for the Deaf Page 25 of 32 in this solicitation and the successful Bidder (the Contractor) shall remain responsible for Contract performance regardless of subcontractor participation in the work.

4.12.2 If the Bidder is the subsidiary of another entity, all information submitted by the Bidder, including but not limited to references, financial reports, or experience and documentation (e.g., insurance policies, bonds, letters of credit) used to meet minimum qualifications, if any, shall pertain exclusively to the Bidder, unless the parent organization will guarantee the performance of the subsidiary. If applicable, the Bidder’s Bid shall contain an explicit statement, signed by an authorized representative of the parent organization, stating that the parent organization will guarantee the performance of the subsidiary.

4.12.3 A parental guarantee of the performance of the Bidder under this section will not automatically result in crediting the Bidder with the experience or qualifications of the parent under any evaluation criteria pertaining to the actual Bidder’s experience and qualifications. Instead, the Bidder’s responsibility will be assessed to the extent to which the State determines that the experience and qualifications of the parent are applicable to and shared with the Bidder, any stated intent by the parent to be directly involved in the performance of the Contract, and the value of the parent’s participation as determined by the State.

4.13 Acceptance of Terms and Conditions

By submitting a Bid in response to this IFB, the Bidder, if selected for award, is deemed to have accepted the terms and conditions of this IFB and the Contract, attached hereto as Exhibit 2 – Sample Contract. Any questions or exceptions to this IFB or the Contract must be submitted by the “Questions Due Date and Time” prior to Bid submission. Changes to the solicitation, including the Bid Form or Contract, made by the Bidder may result in Bid rejection.

4.14 Compliance with Laws/Arrearages

By submitting a Bid in response to this IFB, the Bidder, if selected for award, agrees that it will comply with all federal, State, and local laws applicable to its activities and obligations under the Contract.

By submitting a response to this solicitation, each Bidder represents that it is not in arrears in the payment of any obligations due and owing the State, including the payment of taxes and employee benefits, and shall not become so in arrears during the term of the Contract if selected for Contract award.

4.15 Verification of Registration and Tax Payment

Before a business entity can do business in the State, it must be registered with the State Department of Assessments and Taxation (SDAT). SDAT is located at State Office Building, Room 803, 301 West Preston Street, Baltimore, Maryland 21201. For registration information, visit https://egov.maryland.gov/BusinessExpress/.

https://egov.maryland.gov/BusinessExpress/

IFB for Maryland School for the Deaf Page 26 of 32

It is strongly recommended that any potential Bidder complete registration prior to the Bid due date and time. The Bidder’s failure to complete registration with SDAT may disqualify an otherwise responsive successful Bidder from final consideration and recommendation for Contract award.

4.16 False Statements

Bidders are advised that Md. Code Ann., State Finance and Procurement Article, § 11-205.1 provides as follows:

In connection with a procurement contract a person may not willfully:

A. Falsify, conceal, or suppress a material fact by any scheme or device;

B. Make a false or fraudulent statement or representation of a material fact;or C. Use a false writing or document that contains a false or fraudulent statement or entry of a material fact.

A person may not aid or conspire with another person to commit an act under this section.

A person who violates any provision of this section is guilty of a felony and on conviction is subject to a fine not exceeding $20,000 or imprisonment not exceeding five (5) years or both.

4.17 Confidentiality of Bids / Public Information Act Notice

The Bidder should give specific attention to the clear identification of those portions of its Bid that it considers to contain confidential and/or proprietary commercial information or trade secrets, and provide justification why such materials, upon request, should not be disclosed by the State under the Public Information Act, Md.