Sheet1
| Number | RFP Document | Section # | Context/Issue | Question | Answer |
| 1 | P-Spec Rear Door | 3.13.21 | Requirement 3.13.22 is the only one that indicates a weight restriction ‘per door.’ However, 3.13.23 is not specific enough to understand if ‘the system’ is a single door or the entire rear door system (possibly two doors).• “3.13.21 The system shall not exceed 700 lbs excluding those major subsystems which do not articulate with the door.(T)” |
“3.13.22 The system shall not exceed 660 lbs per door excluding those major sub-systems which do not articulate with the door.(O)” “3.13.23 The system shall not exceed 800 lbs.”
| Requirement 3.13.21 does not specify if the 700 lbs is for a single door or for the entire rear door system. Is the 3.13.21 weight for a single door? | If the Offeror's design solution is a single door than the weight is for a single door. If the Offeror's design includes multiple doors, than it would include the weight of all doors in the system. | ||||
| 2 | P-Spec Rear Door | 3.13.21 & 3.13.23 | “3.13.21 The system shall not exceed 700 lbs excluding those major subsystems which do not articulate with the door.(T)” “3.13.23 The system shall not exceed 800 lbs.” | Requirement 3.13.23 does not specify if this weight is for both doors or for a single door. Does this door weight conflict with the required weight of 3.13.21? | If the Offeror's design solution is a single door than the weight is for a single door. If the Offeror's design includes multiple doors, than it would include the weight of all doors in the system. |
| 3 | Attachment 4: CDRL_to_CLIN_Matrix | Various | Some CDRL to CLIN references in Attachment 4 (CDRL_to_CLIN_Matrix) do not match those in Attachment 2. | Please confirm the applicable CLINs for each of the following CDRLs. |
CDRL A006
Attachment 4: All CLINS Attachment 2: CLINS 1 through 4
CDRL A007
Attachment 4: All CLINS Attachment 2: CLINS 0001 - 0002 - 0003 - 0004
CDRL A011
Attachment 4: CLIN 0001 Attachment 2: CLINS 0001 - 0003 - 0005 - 0007
CDRL A037
Attachment 4: CLIN 0003 Attachment 2: CLIN 0001
CDRL B002
Attachment 4: CLIN 0001
| Attachment 2: CLIN 0003 | Attachment 4 will be removed from the solicitation package. | ||
| 4 | Attachment 2 | Section B of the solicitation identifies: |
CLIN 0001: Design and Development CLIN 0005: First Article Production Egress Kits (option) CLIN 0009: Technical Data Package (TDP) (option)
CDRL B017, Technical Data Package (TDP) identifies option CLIN 0005.
| Does the Government intend for the TDP to be an optional requirement or was the intention to map CDRL B017 to CLIN 0001. | An updated CDRL B017 reflecting CLIN 0009 will be provided. All costs associated with the TDP and providing the TDP shall be included within the cost of CLIN 0009. This CLIN will remain an option CLIN. | ||||
| 5 | Egress_-_SF33_Solicitation_-_22_Nov_2013 | L.2.1 | 1. Front driver door, front commander door, rear door(s), hinges, primary/service handles and locks, secondary/combat handles and locks, door assists, transparent armor, opaque ballistic armor, …. | Will the test buck undergo blast/ballistic testing? | The test buck will only undergo the 5 tests defined in Section L. |
| 6 | Egress_-_SF33_Solicitation_-_22_Nov_2013 | L.2.1 | 1. Front driver door, front commander door, rear door(s), hinges, primary/service handles and locks, secondary/combat handles and locks, door assists, transparent armor, opaque ballistic armor, …. | Can surrogate armor panels be used for the test buck? | The system should be production representative. If any parts are not production representative, it shall be clearly documented. Refer to L.2.1(6). |
| 7 | Attachments 5 and 6 P-Spec (both) | 3.6.2 (Front and rear) | The systems door assist shall be able to perform 20 cycles (1 |
cycle = open and close) independent of vehicle power while the vehicle is upright on ground with a 5% (1:20) crown at 12
| hours after vehicle power interruption (T) | Does the system need to meet this requirement at the full range of operational temps as indicated in the requirements section 3.12 Durability, Strength, and Performance? | Yes, the system needs to meet the requirements at all temperature thresholds. | ||||
| 8 | Attachment 8 - Test Buck Illustration | N/A | Only nominal dimensions are given for the test buck. | What are the units for the dimensions shown? | The unit of measurement is in inches. | |
| 9 | Attachment 8 - Test Buck Illustration | N/A | Only nominal dimensions are given for the test buck. | What tolerance(s) should be applied to the these dimensions? | The tolerance is dependent on your design and manufacturing capabilities. The Government recommends +/- 1 inch maximum. | |
| 10 | Egress_-_SF33_Solicitation_-_22_Nov-2013 | L.1.1 | Volume 1 Content | Are the draft written installation instructions described in section L.1.1 of the solicitation counted against the total page count for Volume 1? | ||
| If the answer is no, then is there a page limit on the Draft Written Installation instructions? | No. The draft installation instructions are not counted in the page count. There is no limit to the number of pages in your installation instructions, it is dependent on your instruction. | |||||
| 11 | Solicitation | L.2.2 | Test Buck Installation Instructions. Per SoW, the design test buck will come installed. | Does the Government require instructions on how the Egress modifications were installed on the Test Buck as it will be delivered to the Government, or does the Government require instructions describing the Test Buck interface requirements for operation during Government testing? | The Government requires installation instructions that also describe the test buck interface requirements for operation during Government testing. | |
| 12 | Attachment 8 - Test Buck Illustration | N/A | Test Buck cube geometry is a fully enclosed box. However, the solicitation indicates that the test buck "must be open to allow for continuous fluid flow around the components as experienced in submersion testing." | Can the Offeror omit the bottom plate depicted in the Test Buck illustration to achieve this fluid flow? | Yes, the Offeror can omit the bottom plate. | |
| 13 | Attachment 8 - Test Buck Illustration | N/A | The test buck illustration has no material thickness called out. | How thick is the material used for construction of the test buck required to be? | The front and rear door systems should be production intent. The test buck should be of material size to maintain structural rigidity during operation and movement. | |
| 14 | Attachment 8 - Test Buck Illustration | N/A | The test buck illustration has no material thickness called out. | Does the test buck structure have to be made out of a specific material? | The front and rear door systems should be production intent. The test buck should be of material and size to maintain structural rigidity during operation and movement. Material is the Offerors choice. | |
| 15 | Attachment 8 - Test Buck Illustration | N/A | The test buck illustration does not locate the front doors in the vertical direction. | Is there a specific location that is required for the vertical placement of the front doors? | No specific location in the vertical direction is required for the front doors, as long as it is encompassed by a door frame. | |
| 16 | Attachment 8 - Test Buck Illustration | N/A | The test buck illustration does not locate the rear doors in the horizontal direction. | Is there a specific location that is required for the horizontal placement of the rear doors? | No specific location in the horizontal direction is required for the Rear doors, as long as it is encompassed by a door frame. | |
| 17 | Attachment 8 - Test Buck Illustration | N/A | The test buck contains no internal cross-bracing or reinforcement. | Is the Offeror permitted to reinforce the interior of the test buck box to improve the rigidity of the walls? | The Offeror can construct the test buck in any fashion to support the Offeror's design solution. However, the dimensions of the test buck must be in accordance with attachment 8. | |
| 18 | Attachment 8 - Test Buck Illustration | N/A | The test buck does not provide vehicle representative features for mounting of the actuator system underneath the windshield. | Is the Offeror permitted to add features to the front of the test buck to accommodate this mounting location? | The Offeror can construct any features required to install a production representative design on the test buck. | |
| 19 | Attachment 8 - Test Buck Illustration | N/A | The test buck does not include performance specification details for the lifting eyes. | Is a specific lifting eye system required? If not, is there a required load rating or factor of safety required? | The lifting eyes should be sufficient to support the weight of the Offerors test buck to facilitate the lifting, loading, and moving of the test buck to execute testing. No specific lifting eye system is required or will be evaluated. | |
| 20 | Solicitation | L.2.1 | Item 3 in section L.2.1 indicates that the test buck must allow all doors to be activated and fully opened simultaneously. | Is this an additional performance requirement for the operation of the egress upgrades? | In accordance with the performance specifications for the door assist section for both the front and rear doors, each door system must have their own activation device capable of operating independently. However, both front and rear doors must be able to activated and fully opened simultaneously. | |
| 21 | Solicitation | L.2.1 | Item 3 in section L.2.1 indicates that the test buck must allow all doors to be activated and fully opened simultaneously. | What performance specification applies to this requirement? | Refer to answer of question 20. | |
| 22 | Solicitation | L.2.1 | Item 3 in section L.2.1 indicates that the test buck must allow all doors to be activated and fully opened simultaneously. | It is not clear what is required of the Offeror to achieve simultaneous opening. Is it the customer's intent to have the Offeror modify their system to support this? | Refer to answer of question 20. | |
| 23 | Solicitation | L.2.2 | Section L.2.1 does not mention the inclusion of the exhaust modification in the test buck. | Is the exhaust re-route/modification required to be installed on the test buck? | The exhaust reroute/modification is not required to be installed on the test buck. | |
| 24 | Solicitation | L.1.4.1 | Section 2.0 states "Offeror's shall submit one (1) complete test buck with fully functional door solution installed, and draft written instructions and integration of the buck kit on the test buck." |
| Section L.1..4.1 states "The Offeror’s test buck must be shipped to the Aberdeen Proving Grounds. Each crate should be marked “Cougar Egress Doors Source Selection, Vendor XXX, crate Y of Z." | Please clarify the Government's requirement for multiple crates when the Egress modifications are required to be installed on the test buck. | If the Offeror is providing one crate it will be marked as "Cougar Egress Doors Source Selection, Vendor XXX, crate 1 of 1". If there are additional crates they would be marked "Cougar Egress Doors Source Selection, Vendor XXX, crate Y of Z". | ||||
| 25 | Attachments 5 and 6 P-Spec (both) | All | The entire list of MIL-STD-810 environment requirements state the system “shall retain material safety, integrity, and performance” during and after exposure to the specific environmental condition. | Does performance include actuation times and number of actuation cycles? | Yes, the number of actuation cycles and times should be consistent in all environments. | |
| 26 | Egress_-_SF33_Solicitation_-_22_Nov_2013 | L.3.2 | Offerers shall include details on ballistic coupon test to include ballistic certifications or coupon data regarding the opaque and transparent armor built into their test buck. | Are third party certifications required? | Yes, transparent Armor certifications from an independent test facility are required. |