Conduct NTCRA under CERCLA at El Capitan former dump site Yosemite NP FORM 2 Price Schedule.
Offerors are required to submit, at minimum, an offer that conforms to the solicitation documents with pricing for base items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of an error in the calculation of extended prices, the unit price governs. In case of an error in summation, the total of the corrected amounts governs. Round totals and extended prices to whole dollars. Complete this page and return with other documents described in Section L.
CONTRACT PRICE SCHEDULE
All work shall be performed in accordance with the attached Statement of Work, referenced documents, and wage determination. Refer to Attachment 1 for line item definitions.
*Unit-priced CLINs show an estimated quantity; see Paragraph H.8.
| Contract Line Item |
| Quantity* and Unit |
| Unit Price |
| Price |
| 1: Contract support tasks |
| 1 lump sum |
| -- |
| $______________ |
| 2: Mobilization, clearing/grubbing, site restoration, and demobilization |
| 1 lump sum |
| -- |
| $______________ |
| 3: Excavate soil (estimated 9,520 cubic yards) |
| 15,430 tons |
| $___________ |
| $______________ |
| 4: Transport and dispose of non-RCRA (California) hazardous soil |
| 4,930 tons |
| $___________ |
| $______________ |
| 5: Transport and dispose of RCRA (California) hazardous soil |
| 9,320 tons |
| $___________ |
| $______________ |
| 6: Transport and dispose of non-hazardous soil |
| 1,180 tons |
| $___________ |
| $______________ |
| 7: Sampling |
| 1 lump sum |
| -- |
| $______________ |
| 8: Monitoring wells and groundwater monitoring |
| 1 lump sum |
| -- |
| $______________ |
| TOTAL PRICE FOR BASE ITEMS 1 through 8: |
| $______________ |
The Government reserves the right to unilaterally award any or no options at or after time of award. See Paragraphs H.7 and M.1 C for details.
| Option A – Import and place clean soil (ordered in full truckloads). Option may be exercised multiple times. |
| 10 cubic yards |
| $___________ |
| $_____________ |
| Option B – Additional soil confirmation samples. Quantity in this table is an estimate only. Option may be exercised multiple times in increments of one (1). |
| 1 each |
| $___________ |
| $_____________ |
Option C – Biobased hydraulic fluid in earth-moving equipment. Option will be per piece of equipment; combine all machines listed in Form 7 into one LS price here.
| TOTAL FOR ALL ITEMS and ALL OPTIONS |
| $____________ |