This document provides details for a federal solicitation requesting proposals for a CERCLA removal action at Yosemite National Park in California. The National Park Service is seeking a contractor to implement a previously developed Non Time-Critical Removal Action work plan to remove approximately 15,000 tons of contaminated soil from a former waste dump site, transport it to approved disposal facilities, install five groundwater monitoring wells and conduct groundwater monitoring for one year, and prepare a Response Action Completion Report. Offerors must visit SAM.gov for any amendments to the solicitation documents. Proposals are due by the date and time specified in the Standard Form 1442. The government will make award to the offeror representing the best value based on technical capability and price. This is a small business set-aside requiring compliance with limitations on subcontracting. The work will be performed under a single firm-fixed-price construction contract subject to prevailing wage requirements.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Offeror: | |||||
| CLIN | Quantity | Unit | Unit Price | CLIN Price | |
| 1 | Contract support tasks | LS | $ - 0 | ||
| Project meetings and conference calls, develop project schedule | 1 | LS | |||
| Site Health and Safety Plan (SHASP) | 1 | LS | |||
| Stormwater pollution prevention plan (SWPPP) | 1 | LS | |||
| PFAS work plan | 1 | LS | |||
| Pre-Design Investigation (PDI) Work Plan and PDI report | 1 | LS | |||
| Response Action Completion Reports (RACR) and Response Action Completion Report Fact Sheets | 1 | LS | |||
| Groundwater Monitored Natural Attenuation (MNA) work plan and report | 1 | LS | |||
| General contract administration and project oversight (do not include removal action site superintendent in this line) | 1 | LS |
| 2 | Mobilization, clearing/grubbing, site restoration, and demobilization | LS | $ - 0 | |
| Mobilization | 1 | LS | ||
| Erosion control | 1 | LS | ||
| Clearing and grubbing | 1 | LS | ||
| Temporary Site Access Road - improve for use, return to natural condition; restore trail. | 1 | LS | ||
| Dust monitoring and control | 1 | LS | ||
| Transport and place NPS-furnished soil (~9,520 cubic yards) | 1 | LS | ||
| Backfill and contour/restore site | 1 | LS | ||
| Demobilization | 1 | LS | ||
| 3 | Excavate soil (estimated 9,520 bank cubic yards) | 15,430 | TN | $ - 0 |
4 Transport and dispose of non-RCRA (California) hazardous soil (estimated quantity) 4,930 TN $ - 0
5 Transport and dispose of RCRA hazardous soil (estimated quantity) 9,320 TN $ - 0
6 Transport and dispose of non-hazardous soil (estimated quantity) 1,180 TN $ - 0
| 7 | Sampling | LS | $ - 0 | |
| Waste characterization | 1 | LS | ||
| Confirmation sampling | 1 | LS | ||
| Groundwater sampling | 1 | LS | ||
| 8 | Monitoring wells and groundwater monitoring | LS | $ - 0 | |
| Remove one existing well | 1 | LS | ||
| Install five new wells | 1 | LS | ||
| Groundwater monitoring (four quarters) | 1 | LS |
TOTAL 1 - 8 $ - 0
| OPTION A | Import and place clean soil (ordered in full truckloads) | |||
| Purchase clean soil | 10 | CY | $ - 0 | |
| Transport, place, and contour imported soil | 10 | CY | $ - 0 |
| OPTION B | Additional soil confirmation samples (each) | 1 | EA | $ - 0 |
| Quantity in this table is an estimate only. |
| OPTION C | Biobased hydraulic fluid in earth-moving equipment | |||
| [List specific equipment and associated price.] | 1 | LS | ||
| [List specific equipment and associated price.] | 1 | LS | ||
| [List specific equipment and associated price.] | 1 | LS | ||
| OPTION D | Transport and place NPS soil (ordered in full truckloads) | |||
| Load, transport, place, and contour NPS-furnished soil. | 10 | CY | $ - 0 |
&"-,Bold"FORM 7: Additional Price Details for RFP #140P2123R0005 (will be the basis for post-award Schedule of Values).
Refer to Section 11 of Attachment 1, Statement of Work, for line item definitions.
Page &P