About this file
This document contains a Contract Data Requirements List (CDRL) for a federal contract to produce C-HOBS fuzes. The CDRL requires the contractor to submit 29 different data items related to engineering, quality assurance, testing, program management, and other areas. Key deliverables include engineering change proposals, test plans and reports, failure analyses, program schedules and status reports, and documentation of quality assurance processes and certifications. Submission dates and approval timelines are provided for each data item. The federal agency requiring the data is the Air Force Materiel Command Lifecycle Management Center.
Exhibit D CDRLS
View the file
Other files for this federal contract opportunity
Show all 50
C-HOBS FA8213-18-R-3015 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
CONTRACT ID: C-HOBS PRODUCTION
CONTRACT NO. : FA8213-18-D-3046
SYSTEM ITEM: EXHIBIT D
SEQUENCE
NUMBER
DID/TITLE
PAGE
NO.
D001 DI-SESS-80639D
ENGINEERING CHANGE PROPOSAL (ECP)
D002 DI-SESS-80640D
REQUEST FOR VARIANCE (RFV)
D003 DI-SESS-80858C
SUPPLIER’S CONFIGURATION MANAGEMENT PLAN (CMP)
D004 DI-MGMT-81435A
DATA ACCESSION LIST (DAL)
D005 DI-SESS-81253C
CONFIGURATION STATUS ACCOUNTING (CSA)
INFORMATION
D006 DI-SAFT-80102C
SAFETY ASSESSMENT REPORT (SAR)
D007 DI-SAFT-80105C
SYSTEM SAFETY PROGRAM PROGRESS REPORT (SSPPR)
D008 DI-SAFT-81626
SYSTEM SAFETY PROGRAM PLAN (SSPP)
D009
DI-SAFT-80101C
SYSTEM SAFETY HAZARD ANALYSIS REPORT (SSHAR)
D010
D011
DI-SAFT-80931B
EXPLOSIVE ORDRIANCE DISPOSAL DATA
DI-SAFT-81299C
EXPLOSIVE HAZARD CLASSIFICATION DATA
D012 DI-SESS-81785A
SYSTEM ENGINEERING MANAGEMENT PLAN (SEMP)
D013 DI-IPSC-81431A
SYSTEM/.SUBSYSTEM PERFORMANCE SPECIFICATION
(SPS)
D014
DI-ADMIN-81306
PROGRAM PROTECTION IMPLEMENTATION PLAN (PPIP)
DRAFT
TABLE OF CONTENTS
CONTRACT ID: C-HOBS PRODUCTION
CONTRACT NO. : FA8213-18-D-3046
SYSTEM ITEM: EXHIBIT D
SEQUENCE
NUMBER
DID/TITLE
PAGE
NO.
D015 DI-SESS-81315B
FAILURE REPORTING, ANALYSIS AND CORRECTIVE
ACTION SYSTEM REPORT (FRACAS)
D016 DI-QCIC-81794
QUALITY ASSURANCE PROGRAM PLAN (QAPP)
D017
DI-QCIC-81187
QUALITY ASSESSMENT REPORT (QAR)
D018 DI-MGMT-81889
MANUFACTURING PLAN (MP)
D019 DI-ADMIN-81249B/T, DI-ADMIN-81250B
CONFERENCE AGENDA/MINUTES
D020 DI-MISC-80043B/T
AMMUNITION DATA CARD
D021 DI-SAFT-81640
AMMUNITION DEMILIITARIZATION AND DISPOSTITION
PLAN
D022 DI-NDTI-80566A/T
TEST PLANS (TPs)
D023
D024
D025
D026
D027
DO28
D029
DI-NDTI-80809B/T
TEST / INSPECTION REPORTS (TIPs)
DI-MGMT-81772
LEAD-FREE CONTROL PLAN (LFCP)
DI-SESS-81585B
REIABILITY AND MAINTAINABILITY TEST PLAN (RMTP)
DI-MGMT-81334D/T
CONTRACT WORK BREAKDOWN STRUCTURE (CWBS)
DI-FNCL81566C
COST DATA SUMMARY REPORT (CDSR)
DI-MGMT-81468/T
CONTRACT FUNDS STATUS REPORT (CFSR)
DI-MGMT-81861A/T
INTEGRATED PROGRAM MANAGEMENT REPORT (IPMR)
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item) Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
D
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
FA8213-18-D-3046
F. CONTRACTOR
1. DATA ITEM NO.
D001
2. TITLE OF DATA ITEM
ENGINEERING CHANGE PROPOSAL
3. SUBTITLE
ECP
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80639D
5. CONTRACT REFERENCE
SOO Para, 2.7,2.10.3;3.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: SHALL INCLUDE BOM AS A PART OF THE ECP. ECN’S, ECR’S AND ECO’S
ETC. SHALL ALSO BE ATTACHED IN FULL AS BACKGROUND INFORMATION. ALL
ECPs SHALL BE SUBMITTED USING DD FORM 1692.
BLK 8: GOVERNMENT APPROVAL OF MAJOR (CLASS I) CHANGES REQUIRED FOR
CONTROL OF THE SYSTEM LEVEL DESIGN REQUIREMENT CHANGES.
GOVERNMENT RESPONSES ARE AS FOLLOWS: EMERGENCY ECPs, 48 HOURS;
URGENT ECPs, 30 CALENDAR DAYS; ROUTINE ECPs, 90 CALENDAR DAYS, RESUBMITTAL, IF REQUIRED, IS DUE 30 DAYS AFTER RECEIPT OF GOVERNMENT
COMMENTS.
BLKS 10, 12, 13: DELIVER AFTER SUCCESSFUL FAAT AND WHEN PROPOSED
CHANGES TO APPROVED BASELINED ENGINEERING DATA OCCUR. ALL MAJOR
ECPs SHALL BE APPROVED BY USG FOR MAJOR CHANGES IMPLEMENTATION.
MAJOR ECPs SHALL CONTAIN A SAFETY IMPACT ASSESSMENT THAT INCLUDES A
SYSTEM, SUBSYSTEM, AND OPERATING AND SUPPORT HAZARD ANALYSIS.
PREPARATION COSTS OF MAJOR ECPs SHALL BE PRICED AS PART OF THE ECP
IMPLEMENTATION COSTS BUT SHALL BE SEPARATELY IDENTIFIED IN THE ECP.
DI-CMAN-80642B (NOR) SHALL BE USED IN CONJUNTION WITH THIS DID.
MINOR (CLASS II) ECPs SHALL BE NO COST.
VECPs ARE DUE AT COMPLETION OF APPLICABLE PRODUCIBILITY ENHANCEMENT
ANALYSIS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN ELECTRONICALLY
TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR HAS GIVEN NOTICE OF
DELIVERY TO THE GOVERNMENT, AND THE GOVERNMENT HAS GIVEN NOTICE TO
CONTRACTOR OF SUCCESSFUL TRANSMITTAL OF SAID DATA.
*AFLCMC/EBHC LT 1
DATA
15. TOTAL
G. PREPARED BY
RONALD G SACCO II
H. DATE
05-17-17
I. APPROVED BY
J. DATE
17. PRICE GROUP 18. ESTIMATED TOTAL PRICE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D002
2. TITLE OF DATA ITEM
REQUEST FOR VARIANCE
3. SUBTITLE
RFV
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80640D
5. CONTRACT REFERENCE
SOO Para, 2.7, 2.10.3; 3.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: PCO APPROVAL IS REQUIRED FOR MAJOR/CRITICAL DEVIATION
PRIOR TO IMPLEMENTATION. GOVERNMENT RESPONSES ARE AS
FOLLOWS: CRITICAL OR MAJOR DEVIATIONS, 30 CALENDAR DAYS AFTER
RECEIPT. RESUBMITTAL, IF REQUIRED, IS DUE 30 DAYS AFTER RECEIPT OF
GOVERNMENT COMMENTS.
BLKS 10, 12, 13: DELIVER AS REQUIRED.
ALL MAJOR AND CRITICAL DEVIATIONS SHALL CONTAIN A SAFETY
IMPACT ASSESSMENT WHICH INCLUDES A SYSTEM, SUBSYSTEM, AND
OPERATING AND SUPPORT HAZARD ANALYSIS.
NOTE: THIS IS A NO COST DATA ITEM.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
H. DATE
17. PRICE GROUP
18. ESTIMATED TOTAL PRICE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D003
2. TITLE OF DATA ITEM
CONFIGURATION MANAGEMENT PLAN
3. SUBTITLE
CMP
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80858C
5. CONTRACT REFERENCE
SOO Para, 2.7
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS ACCEPTABLE.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT AND FORMAT.
GOVERNMENT APPROVAL/DISAPPROVAL PROVIDED 30 DAYS AFTER
RECEIPT OF DOCUMENT.
BLK 10, 12, 13: SUBMITTAL DUE 30 DAYS AFTER JPF CONTRACT AWARD.
UPDATE CHANGES OCCUR.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D004
2. TITLE OF DATA ITEM
DATA ACCESSION LIST/INTERNAL DATA
3. SUBTITLE
DAL
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81453A
5. CONTRACT REFERENCE
SOO Para, 2.2; 2.2.2-7; 2.3-4; 2.6-8; 2.10.1;2.10.5;
2.10.8; 2.11.8; 3.3-4
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: THE DAL SHALL INCLUDE, BUT NOT BE LIMITED TO INTERNAL
DATA, PRODUCTION PROCESSES, WORK INSTRUCTIONS, PRODUCTION
SCHEDULES, WORK IN PROCESS, CONFIGURATION STATUS ACCOUNTING
INFORMATION, RAW MATERIAL INVENTORY, AND SCRAP RATES ETC.
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 DAYS AFTER CONTRACT
AWARD. SUBSEQUENT SUBMITTALS DUE NLT THE 15TH OF EVERY MONTH
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-MGMT-81453A.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D005
2. TITLE OF DATA ITEM
CONFIGURATION STATUS ACCOUNTING INFORMATION
3. SUBTITLE
CSA
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81253C/T
5. CONTRACT REFERENCE
SOO Para, 2.7
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
AS REQ
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
AS REQ
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS ACCEPTABLE.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT AND FORMAT.
GOVERNMENT APPROVAL/DISAPPROVAL PROVIDED 30 DAYS AFTER
RECEIPT OF DOCUMENT.
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 DAYS AFTER CONTRACT
AWARD. SUBSEQUENT SUBMITTALS DUE NLT THE 15TH OF EVERY MONTH
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D006
2. TITLE OF DATA ITEM
SAFETY ASSESSMENT REPORT
3. SUBTITLE
SAR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80102C
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT ACCEPTABLE.
BLK 10, 12, 13: UPDATE AS CHANGES OCCUR.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
AFLCMC/EBHC LT 1
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-CMAN-81248A.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D007
2. TITLE OF DATA ITEM
SYSTEM SAFETY PROGRAM PROGRESS REPORT
3. SUBTITLE
SSPPR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80105C
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE / R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 CALENDAR DAYS AFTER
CONTRACT AWARD. UPDATE AS REQUIRED DUE TO CHANGES.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D008
2. TITLE OF DATA ITEM
SYSTEM SAFETY PROGRAM PLAN
3. SUBTITLE
SSPP
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-81626
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 10, 12, 13: UPDATE AS REQUIRED DUE TO CHANGES. SUBMIT WHEN
UPDATED AND/OR AT GOVERNMENT REQUEST.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR
HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT, AND THE
GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF SUCCESSFUL
TRANSMITTAL OF SAID DATA.
*AFLCMC/EBHC- LT 1
1 1
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-MGMT-81398A.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
D
C. CATEGORY
OTHER
D. SYSTEM/ITEM
JPF FOLLOW-ON PRODUCTION
E. CONTRACT/PR NO.
D009
2. TITLE OF DATA ITEM
System Safety Hazard Analysis Report (SSHAR)
3. SUBTITLE
SSHAR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80101C
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
MTHLY
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT ACCEPTABLE.
BLK 9: APPLY AND USE DISTRIBUTION STATEMENTS IN ACCORDANCE WITH
ATTACHMENT 3 OF THE CONTRACT.
BLKS 10, 12, 13: UPDATE AS CHANGES OCCUR AND/OR AT GOVERNMENT
REQUEST.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR
HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT, AND THE
GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF SUCCESSFUL
TRANSMITTAL OF SAID DATA.
*AFLCMC/EBHC- LT 1
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-MGMT-81453A.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D010
2. TITLE OF DATA ITEM
EXPLOSIVE ORDNANCE DISPOSAL DATA
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80931B
5. CONTRACT REFERENCE
SOO Para, 2.3 and 2.11.8
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
AS REQ
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT.
RESUBMITTAL, IF REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS
AFTER RECEIPT OF GOVERNMENT COMMENTS.
BLK 9: APPLY AND USE DISTRIBUTION STATEMENTS IN ACCORDANCE
WITH ATTACHMENT 3 OF THE CONTRACT.
BLK 10: SUBMIT AS REQUIRED DUE TO CHANGES IN EXPLOSIVE
ORDNANCE DISPOSAL DATA AND/OR AT GOVERNMENT REQUEST.
BLK 13: UPDATES SHALL BE SUBMITTED IF CHANGES OCCUR.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
AFLCMC/EBHC LT 1
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D011
2. TITLE OF DATA ITEM
EXPLOSIVE HAZARD CLASSIFICATION DATA REPORT
3. SUBTITLE
EHCDR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-81299C
5. CONTRACT REFERENCE
SOO Para, 2.3; 2.11.8
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT.
RESUBMITTAL, IF REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS
AFTER RECEIPT OF GOVERNMENT COMMENTS.
BLKS 10, 12, 13: UPDATE AS REQUIRED DUE TO CHANGES AFTER
CONTRACT AWARD AND/OR AT GOVERNMENT REQUEST. RESUMITTAL, IF
REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D012
2. TITLE OF DATA ITEM
SYSTEMS ENGINEERING MANAGEMENT PLAN
3. SUBTITLE
SEMP
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81785A
5. CONTRACT REFERENCE
SOO Para, 2.2
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE / R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUENO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT. RESUBMITTAL,
IF REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE NO LATER THAN 90 CALENDAR
DAYS AFTER CONTRACT AWARD. RESUBMITTAL, IF REQUIRED, IS DUE NO
LATER THAN 30 CALENDAR DAYS AFTER RECEIPT OF GOVERNMENT
COMMENTS. UPDATE ANNUALLY DUE TO CHANGES.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D013
2. TITLE OF DATA ITEM
SYSTEM/SUBSYSTEM PERFORMANCE SPECIFICATION
3. SUBTITLE
SPS
4. AUTHORITY (Data Acquisition Document No.)
DI-IPSC-81431A
5. CONTRACT REFERENCE
SOO Para, 2.2; 2.2.1; and 3.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK : CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE
CONTENTSOF THE DID ARE MET.
BLKS 8, 10 AND 13: DRAFT PLAN DUE TO GOVERNMENT FOR REVIEW AND
APPROVAL NO LATER THAN 30 CALENDAR DAYS AFTER CONTRACT
AWARD. THE CONTRACTOR HAS 21 CALENDAR DAYS TO INCORPORATE
COMMENTS INTO PLAN AND RES-RESUBMIT TO GOVERNMENT FOR
APPROVAL. ANY CHANGES TO THE PERFORMANCE OF THE HARDWARE
AND SOFTWARE SHALL BE DOCUMENTED IN REVISIONS TO THE SYSTEMS
SPECIFICATION AND SUBMITTED TO THE GOVERNMENT FOR REVIEW AND
APPROVAL.
BLK 14: *DATA IETMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
D
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D014
2. TITLE OF DATA ITEM
PROGRAM PROTECTION IMPLENTATION PLAN
3. SUBTITLE
PPIP
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81306
5. CONTRACT REFERENCE
SOO Para, 2.10.2
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE
CONTENTS OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED TO ENSURE COMPLETE AND
CORRECT CONTENT. THE GOVERNMENT WILL HAVE 30 CALENDAR DAYS
FOR REVIEW AND COMMENT. THE CONTRACTOR SHALL HAVE 15
CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS AND
RESUBMIT FOR APPROVAL.
BLK 12: INTIAL SUBMITTAL DUE NO LATER THAN CRITICAL DESIGN
REVIEW (CDR).
BLK 13: ANY CHANGES SHALL BE DOCUMENTED IN REVISIONS AND
SUBMITTED TO THE GOVERNMENT FOR REVIEW AND CONCURRENCE.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D015
2. TITLE OF DATA ITEM
FAILURE SUMMARY AND ANALYSIS REPORT
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81315B
5. CONTRACT REFERENCE
SOO Para, 2.3; 2.5
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: GOVERNMENT APPROVED CONTRACTOR FORMAT ACCEPTABLE.
BLKS 10, 12, 13: A PRELIMINARY EMAIL NOTIFICATION (INDICATING C-HOBS LAT, LOT#,
DAY/DATE OF THE LAT, PASS/FAIL STATUS, QUANTITY, QUANTITY TESTED, AND FACILITY
LOCATION) SHALL BE SUBMITTED WITHIN TWENTY-FOUR (24) HOURS OF A LAT. IF A
FAILURE OCCURS DURING LAT OR RE-LAT, FINAL FRACAS REPORTS ARE DUE WITHIN 45
CALENDAR DAYS OF THE FAILURE. AFTER RECEIPT OF A FRACAS REPORT, THE
GOVERNMENT HAS NO LESS THAN 5 BUSINESS DAYS (NOT TO EXCEED 15 BUSINESS DAYS)
TO REVIEW AND RESPOND WITH AN APPROVAL/DISAPPROVAL OF THE FRACAS REPORT. IF
DISAPPROVED, THE FINAL FRACAS REPORT MUST BE RESUBMITTED WITHIN 15 CALENDAR
DAYS AFTER DISAPPROVAL NOTICE IS RECEIVED. THE TIMEFRAME FOR GOVERNMENT
REVIEW/RESPONSE TO THE RESUBMITTED REPORT REMAINS THE SAME AS PREVIOUSLY
STATED. IF THE INTENT IS TO RETURN TO LAT PRIOR TO FRACAS APPROVAL, A
DETERMINATION (TO INCLUDE RATIONALE AND RISK ASSESSMENT) MUST BE CONCURRED
UPON BY THE GOVERNMENT PRIOR TO LAT RESUMPTION. AFTER RECEIPT OF A LAT
CONTINUATION DETERMINATION, THE GOVERNMENT HAS NO LESS THAN 2 BUSINESS DAYS
(NOT TO EXCEED 4 BUSINESS DAYS) TO REVIEW AND RESPOND WITH CONCURRENCE/NON-
CONCURRENCE OF THE DETERMINATION.
NOTE: IF A LOT IS PRESENTED FOR LAT WITH USG REPRESENTATION, THEN THAT LOT WILL
BE COUNTED TOWARD RELIABLITY AND A FRACAS REPORT WILL BE REQUIRED IN THE
EVENT OF A FAILURE REGARDLESS OF FUTURE DISPOSITION INTENTIONS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN ELECTRONICALLY
TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR HAS GIVEN NOTICE OF DELIVERY
TO THE GOVERNMENT, AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D016
2. TITLE OF DATA ITEM
QUALITY ASSURANCE PROGRAM PLAN
3. SUBTITLE
QAPP
4. AUTHORITY (Data Acquisition Document No.)
DI-QCIC-81794
5. CONTRACT REFERENCE
SOO Para, 2.11.5
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N /A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
BLKS 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE
CONTENTS OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 DAYS AFTER RECEIP. RESUBMITTAL, IF
REQUIRED. IS DUE NO LATER THANK 30 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 10, 12, 13: INITIAL SUBMITTAL DUE NO LATER 30 CALENDAR DAYS
AFTER CONTRACT AWARD. SUSEQUENT SUBMITTALS TO BE PROVIDED AS
THE QUALITY ASSURANCE PLAN IS UPDATED.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D017
2. TITLE OF DATA ITEM
QUALITY ASSESSMENT REPORT
3. SUBTITLE
QAR
4. AUTHORITY (Data Acquisition Document No.)
DI-QCIC-81187
5. CONTRACT REFERENCE
SOO Para, 2.11.6
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 DAYS AFTER RECEIPT. RESUBMITTAL, IF
REQUIRED, IS DUE NO LATER THAN 15 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-SAFT-80931B.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D018
2. TITLE OF DATA ITEM
MANUFACTURING PLAN
3. SUBTITLE
MP
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81889
5. CONTRACT REFERENCE
SOO Para, 2.11
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
BLK 4: CONTRACTOR FORMAT AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET.
BLK 8: GOVERNMENT WILL HAVE 30 CALENDAR DAYS FOR REVIEW AND
COMMENT. THE CONTRACTOR SHALL HAVE 15 CALENDAR DAYS TO
INCORPORATE GOVERNMENT COMMENT AND RESUBMIT.
BLK 10, 12, 13: INITIAL SUBMITTAL DUE 90 CALENDAR DAYS AFTER
CONTRACT AWARD. SUBSEQUENT SUBMITTALS DUE AS REQUESTED
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D019
2. TITLE OF DATA ITEM
CONFERENCE AGENDA/MINUTES
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81249B/T; DI-ADMIN-81250B
5. CONTRACT REFERENCE
SOO Para, 2.2, 2.6, 2.11.1, 2.11.7
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
A
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET
BLK 8: APPROVAL REQUIRED FOR FINAL SUBMISSION ONLY.
GOVERNMENT WILL HAVE 30 CALENDAR DAYS FOR REVIEW AND
COMMENT. THE CONTRACTOR SHALL HAVE 15 CALENDAR DAYS TO
INCORPORATE GOVERNMENT COMMENT AND RESUBMIT.
BLKS 10, 12, 13: DRAFT SUBMITTAL DUE NLT 15 BUSINESS DAYS AFTER
CLOSE OF SCHEDULED EVENT. MEETING MINUTES ARE REQUIRED FOR
ALL MEETINGS AS DEFINED IN THE CONTRACT. GOVERNMENT
COMMENTS DUE NO LATER THAN 5 BUSINESS DAYS AFTER RECEIPT.
FINAL SUBMITAL DUE NO LATER THAN 5 BUSINESS DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D020
2. TITLE OF DATA ITEM
AMMUNITION DATA CARD
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80043B/T
5. CONTRACT REFERENCE
SOO Para, 2.11.8
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
AS REQ
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
AS REQ
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: SUBMIT ADCs FOR C-HOBS.
ADC’S SHALL BE PREPARED IAW MIL-STD-1168, THE STATEMENT OF WORK, AND THIS CDRL
BY ACCESSING THE WORLDWIDE AMMUNITION DATA REPOSITORY PROGRAM (WARP)
WHICK IS LOCATED ON THE ARMY ELECTRONIC PRODUCT SUPPORT (AEPS) WEBSITE AT
http://mhp.redstone.army.mil
HARD COPY ADCs PROVIDED WILL LOT SHIPMENTS SHALL BE GENERATED FROM THE WARP
PROGRAM AND ELECTRONICALLY SIGNED AND DATED BY THE DCMA QUALITY ASSURANCE
REPRESENTATIVE. COMPONENTS DETAILED ON THE ADC WILL BE DESIGNATED BY THE PCO.
A COPY OF THE DD1149 (INVOICE/SHIPPING DOCUMENT) SHALL BE UPLOADED TO THE
GOVERNMENT SERVER (SEE BLK 14)
BLK 7: DELIVER DD-250 WITH ONE COPY OF THE ADC. ANNOTATE THE DD-250 WITH LOT
NUMBER AND NOMENCLATURE AND WETHER FINAL SUBMITTAL OR ADDITIONAL
SUBMITTALS WILL BE MADE.
BLK 10, 12, 13: DELIVER CONCURRENT WITH DELIVERY OF EACH PRODUCTION LOT, EXCEPT
AS NOTED IN BLK 14 BELOW
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN ELECTRONICALLY
TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR HAS GIVEN NOTICE OF DELIVERY
TO THE GOVERNMENT, AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
G. PREPARED BY
RONALD G SACCO II
http://mhp.redstone.army.mil/
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D021
2. TITLE OF DATA ITEM
AMMUNITION DEMILITARIZATION AND DISPOSITION
PLAN
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-81640
5. CONTRACT REFERENCE
SOO Para, 2.11.8
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE / R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 CALENDAR DAYS AFTER
CONTRACT AWARD. RESUBMITTAL, IF REQUIRED, IS DUE NLT 30 DAYS
AFTER RECEIPT OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
D022
2. TITLE OF DATA ITEM
TEST PLANS
3. SUBTITLE
TPs
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80566A/T
5. CONTRACT REFERENCE
SOO Para, 3.3, 3.4, 3.5, 3.6
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 3: SHALL INCLUDE LOT ACCEPTANCE TEST PLAN (LAT), FIRST
ARTICLE ACCEPTANCE TEST PLAN (FAAT) AND DESIGN QUALIFICATION
TEST PLAN.
BLK 4: DELETE PARAGRAPHS 4.3 AND 4.4 OF THE DID.
BLK 8: GOVERNMENT APPROVAL REQUIRED TO ENSURE COMPLETE AND
CORRECT CONTENT. APPROVAL DUE 15 DAYS AFTER RECEIPT.
RESUBMITTAL, IF REQUIRED, IS DUE 15 DAYS AFTER RECEIPT OF
GOVERNMENT COMMENTS.
BLKS 10, 12, 13: SUBMITTAL DUE 30 DAYS BEFORE START OF TEST. DRAFT
CHANGE PAGES ONLY REQUIRED IF CHANGES OCCUR. FINAL,
INCORPORATING GOVERNMENT COMMENTS DUE 30 DAYS AFTER
RECEIPT.
BLK 14: DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC…
This is the start of the file's text. The full file is on GovTribe.