This document contains pricing matrices and ordering procedures for the C-HOBS program under solicitation FA8213-17-R-DSU33 issued by the Department of the Air Force Materiel Command Lifecycle Management Center. The pricing applies to delivery orders awarded over six ordering periods for quantities of C-HOBS units between 3,437 and 16,000, as well as cable kits between 3,437 and 8,000. Prices will decrease as cumulative quantities ordered increase within defined bands. Additional quantities added to existing delivery orders within 90 days will retain the original order's pricing and period of performance.
Pricing Matrix and Ordering Procedures
View the file
Other files for this federal contract opportunity
Show all 50
C-HOBS FA8213-18-R-3015 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 3
C-HOBS ORDERING PERIODS 1-6 PRICING MATRIX AND ORDERING
PROCEDURES
Pricing in this matrix applies to all delivery orders issued under this ID/IQ against CLINs 3000- 7006.
Quantities added to an existing delivery order (via modification) within 90 calendar days from award of that delivery order will be considered as cumulative for purposes of the applicable price from the Table 2 “Pricing Matrix,” so that either the unit price remains the same as in the original delivery order issued, with the extended amount increased to reflect the new higher quantity, or the unit price will be adjusted downward as the cumulative quantity total for the delivery order extends into another pricing band. Additional quantities added to delivery orders (via modification) within 90 calendar days will still retain the 1 year period of performance form the time the original delivery order was issued. Additional quantities required after 90 days from an existing delivery order will be awarded as its own separate delivery order and the quantities shall not be cumulative and the PoP will be 12 months from award of that delivery order.
In the event the contractor accomplishes Design and Development and passes First Article Test prior to the end of ordering period 1, ordering period 2 price will be applied to delivery orders placed from that time through the end of ordering period 2.
Table 1 –Ordering Periods
Ordering Period Cumulative Ordering Period Order Period 1 (Design and Development) – two consecutive years from award of contract
90 calendar days from issuance of Delivery order
Order Period 2 – the day after the end of Order Period 1 through one consecutive year
90 calendar days from issuance of Delivery order
Order Period 3 – one year from completion of Order Period 2
90 calendar days from issuance of Delivery order
Order Period 4 – one year from completion of Order Period 3
90 calendar days from issuance of Delivery order
Order Period 5 – one year from completion of Order Period 4
90 calendar days from issuance of Delivery order
Order Period 6 – one year from completion of Order Period 5
90 calendar days from issuance of Delivery order
DRAFT
Table 2 – C-HOBS Pricing Matrix
C-HOBS ORDERING PERIODS 2-6
UNIT PRICES
ORDER PERIOD PRICE BAND
PRICE BAND
PRICE BAND
PRICE BAND
PRICE BAND
QUANTITIES
3,437 – 6,875 6,876 – 10,312 10,313 – 13,750 13,751 – 16,000
2 $ $ $ $ 3 $ $ $ $ 4 $ $ $ $ 5 $ $ $ $ 6 $ $ $ $
Table 3 – Cable Kits Pricing Matrix
C-HOBS ORDERING PERIODS 2-6
UNIT PRICES
ORDER PERIOD PRICE BAND 1 PRICE BAND
PRICE BAND QUANTITIES 3,437 – 5,718 5,719 – 8,000
2 $ $ 3 $ $ 4 $ $ 5 $ $ 6 $ $