This document contains a Contract Data Requirements List (CDRL) specifying 34 data items required under a federal contract for the C-HOBS system.
The CDRL outlines technical requirements for deliverables such as engineering change proposals, configuration management plans, safety reports, test plans and reports, program schedules and status updates. It specifies delivery timelines for initial and updated submissions, distribution statements, and approval processes for government sign-off. Key deliverables include a Systems Engineering Management Plan due within 90 days of award, and Reliability and Maintainability Test Plans to be submitted prior to commencing related testing. The CDRL also provides formatting and submission instructions, noting electronic delivery to the government server and distribution of draft and final versions to contracting parties.
Exhibit A CDRLS
View the file
Other files for this federal contract opportunity
Show all 50
C-HOBS FA8213-18-R-3015 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
CONTRACT ID: C-HOBS
CONTRACT NO. : FA8213-D-18-3046
SYSTEM ITEM: EXHIBIT A
SEQUENCE
NUMBER
DID/TITLE
PAGE
NO.
A001 DI-SESS-80639D
ENGINEERING CHANGE PROPOSAL (ECP)
A002 DI-SESS-80640D
REQUEST FOR VARIANCE (RFV)
A003 DI-SESS-80858C
SUPPLIERS CONFIGURATION MANAGEMENT PLAN
A004 DI-MGMT-81453A
DATA ACCESSION LIST/INTERNAL DATA (DAL)
A005 DI-SESS-81253C/T
CONFIGURATION STATUS ACCOUNTING (CSA)
INFORMATION
A006 DI-SAFT-80102C
SAFETY ASSESSMENT REPORT (SAR)
A007 DI-SAFT-80105C
SYSTEM SAFETY PROGRAM PROGRESS REPORT (SSPPR)
A008 DI-SESS-81495A
FAILURE MODE, EFFECTS, CRITICALITY ANALYSIS (FMECA)
A009 DI-SAFT-81626
SYSTEM SAFETY PROGRAM PLAN (SSPP)
A010 DI-SAFT-80101C
SYSTEM SAFETY HAZARD ANALYSIS REPORT (SSHAR)
A011 DI-SAFT-80931B
EXPLOSIVE ORDNANCE DISPOSAL DATA
A012 DI-SAFT-81299C
EXPLOSIVE HAZARD CLASSIFICATION DATA
A013
DI-SESS-81785A
SYSTEMS ENGINEERING MANAGEMENT PLAN (SEMP)
A014 DI-IPSC-81431A
SYSTEM/SUBSYSTEM PERFORMANCE SPECIFICATIONS
(SPS)
A015 DI-ADMIN-81306
PROGRAM PROTECTION IMPLENTATION PLAN (PPIP)
A016 DI-SESS-81315B
FAILURE SUMMARY AND ANALYSIS REPORT (FRACAS)
DRAFT
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-CMAN-81248A.PDF
NO.
A017
DI-MGMT-80790
CONTRACTORS PRODUCTION TRANSITION PLAN (CPTP)
A018 DI-QCIC-81794
QUALITY ASSURANCE PROGRAM PLAN (QAPP)
A019 DI-QCIC-81187
QUALITY ASSESSMENT REPORT (QAR)
A020 DI-MGMT-81949
DMSMS IMPLEMENTATION PLAN
A021 DI-MGMT-81889
MANUFACTURING PLAN (MP)
A022 DI-ADMIN-81249B/T; DI-ADMIN-81250B
CONFERENCE AGENDA/MINUTES
A023 DI-MISC-80043B/T
AMMUNITION DATA CARD
A024 DI-SAFT-81640
AMMUNITION DEMILITARIZATION AND DISPOSITION
PLAN
NO.
A025
DI-NDTI-80566A/T
TEST PLANS (TPs)
A026 DI-NDTI-80809B/T
TEST/INSPECTION REPORTS (TIPs)
A027 DI-ENVR-81375
ENVIROMENTAL HEALTH AND SAFETY PLAN (EHSP)
A028 DI-MGMT-81809
CONTRACTOR RISK MANAGEMENT STATUS REPORT
(CRMSR)
A029 DI-MGMT-81722/T
LEAD FREE CONTROL PLAN (LFCP)
A030 DI-SESS-81585B
RELIABILITY AND MAINTAINABILITY TEST PLAN (RMTP)
A031
DI-MGMT-81334D/T
CONTRACT WORK BREAKDOWN STRUCTURE (CWBS)
A032
DI-FNCL-81566C
COST DATA SUMMARY REPORT (CDSR)
A033
A034
DI-MGMT-81468/T
COST FUNDS STATUS REPORT (CFSR)
DI-MGMT-81861A/T
INTEGRATED PROGRAM MANAGEMENT REPORT (IPMR)
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
E. CONTRACT/PR NO.
FA8213-18-D-3046
F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
ENGINEERING CHANGE PROPOSAL
3. SUBTITLE
ECP
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80639D
5. CONTRACT REFERENCE
SOO Para, 2.7,2.10.3;3.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: SHALL INCLUDE BOM AS A PART OF THE ECP. ECN’S, ECR’S AND ECO’S ETC.
SHALL ALSO BE ATTACHED IN FULL AS BACKGROUND INFORMATION. ALL ECPs
SHALL BE SUBMITTED USING DD FORM 1692.
BLK 8: GOVERNMENT APPROVAL OF MAJOR (CLASS I) CHANGES REQUIRED FOR
CONTROL OF THE SYSTEM LEVEL DESIGN REQUIREMENT CHANGES.
GOVERNMENT RESPONSES ARE AS FOLLOWS: EMERGENCY ECPs, 48HOURS;
URGENT ECPs, 30 CALENDAR DAYS; ROUTINE ECPs, 90 CALENDAR DAYS, RESUBMITTAL, IF REQUIRED, IS DUE 30 DAYS AFTER RECEIPT OF GOVERNMENT
COMMENTS.
BLKS 10, 12, 13: DELIVER AFTER SUCCESSFUL FAAT AND WHEN PROPOSED
CHANGES TO APPROVED BASELINED ENGINEERING DATA OCCUR. ALL MAJOR
ECPs SHALL BE APPROVED BY USG FOR MAJOR CHANGES IMPLEMENTATION.
MAJOR ECPs SHALL CONTAIN A SAFETY IMPACT ASSESSMENT THAT INCLUDES A
SYSTEM, SUBSYSTEM, AND OPERATING AND SUPPORT HAZARD ANALYSIS.
PREPARATION COSTS OF MAJOR ECPs SHALL BE PRICED AS PART OF THE ECP
IMPLEMENTATION COSTS BUT SHALL BE SEPARATELY IDENTIFIED IN THE ECP.
DI-CMAN-80642B (NOR) SHALL BE USED IN CONJUNTION WITH THIS DID.
MINOR (CLASS II) ECPs SHALL BE NO COST.
VECPs ARE DUE AT COMPLETION OF APPLICABLE PRODUCIBILITY ENHANCEMENT
ANALYSIS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN ELECTRONICALLY
TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR HAS GIVEN NOTICE OF
DELIVERY TO THE GOVERNMENT, AND THE GOVERNMENT HAS GIVEN NOTICE TO
CONTRACTOR OF SUCCESSFUL TRANSMITTAL OF SAID DATA.
*AFLCMC/EBHC LT 1
DATA
15. TOTAL
G. PREPARED BY
RONALD G SACCO II
H. DATE
05/17/2017
I. APPROVED BY
J. DATE
17. PRICE GROUP 18. ESTIMATED TOTAL PRICE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A002
2. TITLE OF DATA ITEM
REQUEST FOR VARIANCE
3. SUBTITLE
RFV
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80640D
5. CONTRACT REFERENCE
SOO Para, 2.7, 2.10.3; 3.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: PCO APPROVAL IS REQUIRED FOR MAJOR/CRITICAL DEVIATION
PRIOR TO IMPLEMENTATION. GOVERNMENT RESPONSES ARE AS
FOLLOWS: CRITICAL OR MAJOR DEVIATIONS, 30 CALENDAR DAYS AFTER
RECEIPT. RESUBMITTAL, IF REQUIRED, IS DUE 30 DAYS AFTER RECEIPT OF
GOVERNMENT COMMENTS.
BLKS 10, 12, 13: DELIVER AS REQUIRED.
ALL MAJOR AND CRITICAL DEVIATIONS SHALL CONTAIN A SAFETY
IMPACT ASSESSMENT WHICH INCLUDES A SYSTEM, SUBSYSTEM, AND
OPERATING AND SUPPORT HAZARD ANALYSIS.
NOTE: THIS IS A NO COST DATA ITEM.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
H. DATE
05/17/17
17. PRICE GROUP
18. ESTIMATED TOTAL PRICE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A003
2. TITLE OF DATA ITEM
SUPPLIERS CONFIGURATION MANAGEMENT PLAN
3. SUBTITLE
CMP
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80858C
5. CONTRACT REFERENCE
SOO Para, 2.7
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS ACCEPTABLE.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT AND FORMAT.
GOVERNMENT APPROVAL/DISAPPROVAL PROVIDED 30 DAYS AFTER
RECEIPT OF DOCUMENT.
BLK 10, 12, 13: SUBMITTAL DUE 30 DAYS AFTER JPF CONTRACT AWARD.
UPDATE CHANGES OCCUR.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A004
2. TITLE OF DATA ITEM
DATA ACCESSION LIST/INTERNAL DATA
3. SUBTITLE
DAL
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81453A
5. CONTRACT REFERENCE
SOO Para, 2.2; 2.2.2-7; 2.3-4; 2.6-8; 2.10.1;2.10.5;
2.10.8; 2.11.8; 3.3-4
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: THE DAL SHALL INCLUDE, BUT NOT BE LIMITED TO INTERNAL
DATA, PRODUCTION PROCESSES, WORK INSTRUCTIONS, PRODUCTION
SCHEDULES, WORK IN PROCESS, CONFIGURATION STATUS ACCOUNTING
INFORMATION, RAW MATERIAL INVENTORY, AND SCRAP RATES ETC.
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 DAYS AFTER CONTRACT
AWARD. SUBSEQUENT SUBMITTALS DUE NLT THE 15TH OF EVERY MONTH
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A005
2. TITLE OF DATA ITEM
CONFIGURATION STATUS ACCOUNTING INFORMATION
3. SUBTITLE
CSA
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81253C/T
5. CONTRACT REFERENCE
SOO Para, 2.7
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
AS REQ
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
AS REQ
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS ACCEPTABLE.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT AND FORMAT.
GOVERNMENT APPROVAL/DISAPPROVAL PROVIDED 30 DAYS AFTER
RECEIPT OF DOCUMENT.
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 DAYS AFTER CONTRACT
AWARD. SUBSEQUENT SUBMITTALS DUE NLT THE 15TH OF EVERY MONTH
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
05-17-17
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A006
2. TITLE OF DATA ITEM
SAFETY ASSESSMENT REPORT
3. SUBTITLE
SAR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80102C
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT ACCEPTABLE.
BLK 10, 12, 13: UPDATE AS CHANGES OCCUR.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
AFLCMC/EBHC- LT 1
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A007
2. TITLE OF DATA ITEM
SYSTEM SAFETY PROGRAM PROGRESS REPORT
3. SUBTITLE
SSPPR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80105C
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE 90 CALENDAR DAYS AFTER
CONTRACT AWARD. UPDATE AS REQUIRED DUE TO CHANGES.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A008
2. TITLE OF DATA ITEM
FAILURE MODE, EFFECTS, CRITICALITY ANALYSIS
3. SUBTITLE
FMECA
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81495A
5. CONTRACT REFERENCE
SOO Para, 2.3;2.10.4
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS OF THE DID ARE
MET. THE FMECA SHALL BE PERFORMED AT THE LOWEST LEVEL THAT WILL ALLOW
SATISFACTION OF THE FOLLOWING THREE OBJECTIVES:
• IDENTIFICATION OF A SINGLE POINT OF FAILURE (SPF). IF SPFS ARE IDENTIFIED
THE CONTRACTOR SHALL MAKE EVERY EFFORT TO ELIMINATE OR REDUCE THE
PROBABILITY OF RECURRENCE.
• MAINTENANCE TASK ANALYSIS. THE FMECA SHALL BE SUFFICIENTLY DETAILED
TO PERFORM THE LOGISTICS ANALYSIS REQUIRED.
• HEALTH MONITORING SYSTEM. THE FMECA SHALL BE CAPABLE OF SUPPORTING
THE MAINTAINABILITY/BIT PREDICTION AND TEST REQUIREMENTS.
EXISTING FMECA DATA MAY BE USED PROVIDING ALL ASSUMPTIONS EMPLOYED ARE
CONSISTENT WITH THIS PROGRAM.
BLK 8: GOVERNMENT WILL HAVE 30 DAYS FOR REVIEW AND COMMENT. THE CONTRACTOR
SHALL HAVE 15 DAYS TO INCORPORATE GOVERNMENT COMMENT AND RESUBMIT.
BLKS 10, 12 AND 13: PRELIMINARY SUBMISSION IS DUE 45 DP TO PRELIMINARY DESIGN
REVIEW (PDR). FINAL DUE 45 DP TO CRITICAL DESIGN REVIEW (CDR). UPDATES AS
REQUIRED.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN ELECTRONICALLY
TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR HAS GIVEN NOTICE OF DELIVERY
TO THE GOVERNMENT, AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A009
2. TITLE OF DATA ITEM
SYSTEM SAFEY PROGRAM PLAN
3. SUBTITLE
SSPP
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-81626
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 10, 12, 13: UPDATE AS REQUIRED DUE TO CHANGES. SUBMIT WHEN
UPDATED AND/OR AT GOVERNMENT REQUEST.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR
HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT, AND THE
GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF SUCCESSFUL
TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-MGMT-81398A.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A010
2. TITLE OF DATA ITEM
SYSTEM SAFETY HAZARD ANALYSIS REPORT
3. SUBTITLE
SSHAR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80101C
5. CONTRACT REFERENCE
SOO Para, 2.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
MTHLY
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT ACCEPTABLE.
BLK 9: APPLY AND USE DISTRIBUTION STATEMENTS IN ACCORDANCE WITH
ATTACHMENT 3 OF THE CONTRACT.
BLKS 10, 12, 13: UPDATE AS CHANGES OCCUR AND/OR AT GOVERNMENT
REQUEST.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR
HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT, AND THE
GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF SUCCESSFUL
TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-MGMT-81453A.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A011
2. TITLE OF DATA ITEM
EXPLOSIVE ORDNANCE DISPOSAL DATA
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80931B
5. CONTRACT REFERENCE
SOO Para, 2.3 and 2.11.8
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
AS REQ
14. DISTRIBUTION
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT.
RESUBMITTAL, IF REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS
AFTER RECEIPT OF GOVERNMENT COMMENTS.
BLK 9: APPLY AND USE DISTRIBUTION STATEMENTS IN ACCORDANCE
WITH ATTACHMENT 3 OF THE CONTRACT.
BLK 10: SUBMIT AS REQUIRED DUE TO CHANGES IN EXPLOSIVE
ORDNANCE DISPOSAL DATA AND/OR AT GOVERNMENT REQUEST.
BLK 13: UPDATES SHALL BE SUBMITTED IF CHANGES OCCUR.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
AFLCMC/EBHC- LT 1
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A012
2. TITLE OF DATA ITEM
EXPLOSIVE HAZARD CLASSIFICATION DATA REPORT
3. SUBTITLE
EHCDR
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-81299C
5. CONTRACT REFERENCE
SOO Para, 2.3; 2.11.8
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT.
RESUBMITTAL, IF REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS
AFTER RECEIPT OF GOVERNMENT COMMENTS.
BLKS 10, 12, 13: UPDATE AS REQUIRED DUE TO CHANGES AFTER
CONTRACT AWARD AND/OR AT GOVERNMENT REQUEST. RESUMITTAL, IF
REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A013
2. TITLE OF DATA ITEM
SYSTEMS ENGINEERING MANAGEMENT PLAN
3. SUBTITLE
SEMP
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81785A
5. CONTRACT REFERENCE
SOO Para, 2.2
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL DUE
NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT. RESUBMITTAL, IF
REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT OF
GOVERNMENT COMMENTS.
BLKS 10, 12, 13: INITIAL SUBMITTAL DUE NO LATER THAN 90 CALENDAR
DAYS AFTER CONTRACT AWARD. RESUBMITTAL, IF REQUIRED, IS DUE NO
LATER THAN 30 CALENDAR DAYS AFTER RECEIPT OF GOVERNMENT
COMMENTS. UPDATE ANNUALLY DUE TO CHANGES.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR
HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT, AND THE
GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF SUCCESSFUL
TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A014
2. TITLE OF DATA ITEM
SYSTEM/SUBSYSTEM PERFORMANCE SPECIFICATION
3. SUBTITLE
SPS
4. AUTHORITY (Data Acquisition Document No.)
DI-IPSC-81431A
5. CONTRACT REFERENCE
SOO Para, 2.2; 2.2.1; and 3.3
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK : CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET.
BLKS 8, 10 AND 13: DRAFT PLAN DUE TO GOVERNMENT FOR REVIEW AND
APPROVAL NO LATER THAN 30 CALENDAR DAYS AFTER CONTRACT
AWARD. THE CONTRACTOR HAS 21 CALENDAR DAYS TO INCORPORATE
COMMENTS INTO PLAN AND RESUBMIT TO GOVERNMENT FOR APPROVAL.
ANY CHANGES TO THE PERFORMANCE OF THE HARDWARE AND
SOFTWARE SHALL BE DOCUMENTED IN REVISIONS TO THE SYSTEMS
SPECIFICATION AND SUBMITTED TO THE GOVERNMENT FOR REVIEW AND
APPROVAL.
BLK 14: *DATA IETMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
AND THE GOVERNMENT HAS GIVEN NOTICE TO CONTRACTOR OF
SUCCESSFUL TRANSMITTAL OF SAID DATA.
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
A
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A015
2. TITLE OF DATA ITEM
PROGRAM PROTECTION IMPLENTATION PLAN
3. SUBTITLE
PPIP
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81306
5. CONTRACT REFERENCE
SOO Para, 2.10.2
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE
CONTENTS OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED TO ENSURE COMPLETE AND
CORRECT CONTENT. THE GOVERNMENT WILL HAVE 30 CALENDAR DAYS
FOR REVIEW AND COMMENT. THE CONTRACTOR SHALL HAVE 15
CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS AND
RESUBMIT FOR APPROVAL.
BLK 12: INTIAL SUBMITTAL DUE NO LATER THAN CRITICAL DESIGN
REVIEW (CDR).
BLK 13: ANY CHANGES SHALL BE DOCUMENTED IN REVISIONS AND
SUBMITTED TO THE GOVERNMENT FOR REVIEW AND CONCURRENCE.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A016
2. TITLE OF DATA ITEM
FAILURE SUMMARY AND ANALYSIS REPORT
3. SUBTITLE
FRACAS
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81315B
5. CONTRACT REFERENCE
SOO Para, 2.3; 2.5
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: GOVERNMENT APPROVED CONTRACTOR FORMAT ACCEPTABLE.
BLKS 10, 12, 13: A PRELIMINARY EMAIL NOTIFICATION (INDICATING C-HOBS LAT, LOT#,
DAY/DATE OF THE LAT, PASS/FAIL STATUS, QUANTITY, QUANTITY TESTED, AND FACILITY
LOCATION) SHALL BE SUBMITTED WITHIN TWENTY-FOUR (24) HOURS OF A LAT. IF A
FAILURE OCCURS DURING LAT OR RE-LAT, FINAL FRACAS REPORTS ARE DUE WITHIN 45
CALENDAR DAYS OF THE FAILURE. AFTER RECEIPT OF A FRACAS REPORT, THE
GOVERNMENT HAS NO LESS THAN 5 BUSINESS DAYS (NOT TO EXCEED 15 BUSINESS DAYS)
TO REVIEW AND RESPOND WITH AN APPROVAL/DISAPPROVAL OF THE FRACAS REPORT. IF
DISAPPROVED, THE FINAL FRACAS REPORT MUST BE RESUBMITTED WITHIN 15 CALENDAR
DAYS AFTER DISAPPROVAL NOTICE IS RECEIVED. THE TIMEFRAME FOR GOVERNMENT
REVIEW/RESPONSE TO THE RESUBMITTED REPORT REMAINS THE SAME AS PREVIOUSLY
STATED. IF THE INTENT IS TO RETURN TO LAT PRIOR TO FRACAS APPROVAL, A
DETERMINATION (TO INCLUDE RATIONALE AND RISK ASSESSMENT) MUST BE CONCURRED
UPON BY THE GOVERNMENT PRIOR TO LAT RESUMPTION. AFTER RECEIPT OF A LAT
CONTINUATION DETERMINATION, THE GOVERNMENT HAS NO LESS THAN 2 BUSINESS DAYS
(NOT TO EXCEED 4 BUSINESS DAYS) TO REVIEW AND RESPOND WITH CONCURRENCE/NON-
CONCURRENCE OF THE DETERMINATION.
NOTE: IF A LOT IS PRESENTED FOR LAT WITH USG REPRESENTATION, THEN THAT LOT WILL
BE COUNTED TOWARD RELIABLITY AND A FRACAS REPORT WILL BE REQUIRED IN THE
EVENT OF A FAILURE REGARDLESS OF FUTURE DISPOSITION INTENTIONS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN ELECTRONICALLY
TRANSMITTED TO GOVERNMENT SERVER, CONTRACTOR HAS GIVEN NOTICE OF DELIVERY
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A017
2. TITLE OF DATA ITEM
CONTRACTOR PRODUCTION TRANSITION PLAN
3. SUBTITLE
TP
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80790
5. CONTRACT REFERENCE
SOO Para, 2.11.9
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLKS 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE
CONTENTS OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED TO ENSURE COMPLETE AND
CORRECT CONTENT. THE GOVERNMENT WILL HAVE 30 CALENDAR DAYS
FOR REVIEW AND COMMENT. THE CONTRACTOR SHALL HAVE 15
CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS AND
RESUBMIT FOR APPROVAL.
BLK 12: INTIAL SUBMITTAL DUE NO LATER THAN CRITICAL DESIGN
REVIEW (CDR).
BLK 13: ANY CHANGES SHALL BE DOCUMENTED IN REVISIONS AND
SUBMITTED TO THE GOVERNMENT FOR REVIEW AND CONCURRENCE.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A018
2. TITLE OF DATA ITEM
QUALITY ASSURANCE PROGRAM PLAN
3. SUBTITLE
QAPP
4. AUTHORITY (Data Acquisition Document No.)
DI-QCIC-81794
5. CONTRACT REFERENCE
SOO Para, 2.11.5
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
BLKS 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE
CONTENTS OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 DAYS AFTER RECEIPT. RESUBMITTAL, IF
REQUIRED, IS DUE NO LATER THAN 30 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 10, 12, 13: INITIAL SUBMITTAL DUE NO LATER 30 CALENDAR DAYS
AFTER CONTRACT AWARD. SUSEQUENT SUBMITTALS TO BE PROVIDED
AS THE QUALITY ASSURANCE PLAN IS UPDATED.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A019
2. TITLE OF DATA ITEM
QUALITY ASSESSMENT REPORT
3. SUBTITLE
QAR
4. AUTHORITY (Data Acquisition Document No.)
DI-QCIC-81187
5. CONTRACT REFERENCE
SOO Para, 2.11.6
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
D
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET.
BLK 8: GOVERNMENT APPROVAL REQUIRED FOR CONTENT. APPROVAL
DUE NO LATER THAN 30 DAYS AFTER RECEIPT. RESUBMITTAL, IF
REQUIRED, IS DUE NO LATER THAN 15 CALENDAR DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
file://egacq1/org$/02.04_FUZES%20-%20RESTRICTED/JPF/08%20-%20Contracting/08-19%20%20Follow-On%20JPF%20Contract%20Planning/RFP/EXHIBITS/Exhibit%20A/DIDs%20List/DI-SAFT-80931B.PDF
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A020
2. TITLE OF DATA ITEM
DIMINISHING MANUFACTURING SOURCE AND
MATERIAL SHORTAGE IMPLEMENTATION PLAN
3. SUBTITLE
DMSMS
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81949
5. CONTRACT REFERENCE
SOO Para, 2.11.2
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
QTRLY
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET
BLK 8: APPROVAL REQUIRED FOR FINAL SUBMISSION ONLY.
GOVERNMENT WILL HAVE 30 CALENDAR DAYS FOR REVIEW AND
COMMENT. THE CONTRACTOR SHALL HAVE 15 CALENDAR DAYS TO
INCORPORATE GOVERNMENT COMMENT AND RESUBMIT
CONTRACT AWARD. SUBSEQUENT SUBMITTALS DUE QUARTERLY
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A021
2. TITLE OF DATA ITEM
MANUFACTURING PLAN
3. SUBTITLE
MP
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81889
5. CONTRACT REFERENCE
SOO Para, 2.11
6. REQUIRING OFFICE
AFLCMC/EBHC
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
N/A
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
BLK 4: CONTRACTOR FORMAT AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET.
BLK 8: GOVERNMENT WILL HAVE 30 CALENDAR DAYS FOR REVIEW AND
COMMENT. THE CONTRACTOR SHALL HAVE 15 CALENDAR DAYS TO
INCORPORATE GOVERNMENT COMMENT AND RESUBMIT.
BLK 10, 12, 13: INITIAL SUBMITTAL DUE 90 CALENDAR DAYS AFTER
CONTRACT AWARD. SUBSEQUENT SUBMITTALS DUE AS REQUESTED
THEREAFTER.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
C. CATEGORY
OTHER
D. SYSTEM/ITEM
C-HOBS
A022
2. TITLE OF DATA ITEM
CONFERENCE AGENDA/MINUTES
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81249B/T; DI-ADMIN-81250B
5. CONTRACT REFERENCE
SOO Para, 2.2, 2.6, 2.11.1, 2.11.7
6. REQUIRING OFFICE
7. DD250 REQ
LT
9. DIST
STATEMENT
REQUIRED
A
10. FREQUENCY
SEE BLK 16
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLK 16
a. ADDRESSEE Draft Final
Reg Repro
16. REMARKS
BLK 4: CONTRACTOR FORMAT IS AUTHORIZED PROVIDED THE CONTENTS
OF THE DID ARE MET
BLK 8: APPROVAL REQUIRED FOR FINAL SUBMISSION ONLY.
GOVERNMENT WILL HAVE 30 CALENDAR DAYS FOR REVIEW AND
COMMENT. THE CONTRACTOR SHALL HAVE 15 CALENDAR DAYS TO
INCORPORATE GOVERNMENT COMMENT AND RESUBMIT.
BLKS 10, 12, 13: DRAFT SUBMITTAL DUE NLT 15 BUSINESS DAYS AFTER
CLOSE OF SCHEDULED EVENT. MEETING MINUTES ARE REQUIRED FOR
ALL MEETINGS AS DEFINED IN THE CONTRACT. GOVERNMENT
COMMENTS DUE NO LATER THAN 5 BUSINESS DAYS AFTER RECEIPT.
FINAL SUBMITAL DUE NO LATER THAN 5 BUSINESS DAYS AFTER RECEIPT
OF GOVERNMENT COMMENTS.
BLK 14: *DATA ITEMS ARE DEEMED TO BE DELIVERED WHEN
ELECTRONICALLY TRANSMITTED TO GOVERNMENT SERVER,
CONTRACTOR HAS GIVEN NOTICE OF DELIVERY TO THE GOVERNMENT,
G. PREPARED BY
RONALD G SACCO II
H. DATE
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .