Text version
CLIN SUB
CLIN Noun / CLIN Title FY16-17
Basic
FY17-18
Option Yr 1
FY18-19
Option Yr 2
FY19-20
Option Yr 3
FY20-21
Option Yr 4
X001 FFP - Tear Down & Inspect
AA FFP - 1250 Hour Inspection - LEVEL 1
AB FFP - 1250 Hour Inspection - LEVEL 2
AC FFP - 1250 Hour Inspection - LEVEL 3
AA FFP - 2500 Hour Inspection - LEVEL 1
AB FFP - 2500 Hour Inspection - LEVEL 2
AC FFP - 2500 Hour Inspection - LEVEL 3
X004 FFP - 5000 Hour Inspection - LEVEL 1
X005 FFP Labor Wrap Rate - Unscheduled Engine Removal (UER)
X006 FFP Labor Wrap Rate - O&A - Other
X007 FFP - MISTR Rotary Pump (Scavenge Pump) Repair
X008 FFP - Test Cell Run
X009 NSP - CDRLS - Data Reporting
X010 FFP for each event Travel
Basic Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4
T53 APPENDIX H - PRICING MATRIX
X002
X003
10-Jun-15
NSP = Not Separately Priced -- Data priced as part of FFP CLIN efforts FFP = Firm Fixed Price
FFP Labor Wrap Rate = A FFP hourly rate that covers all skills required to complete the task
BASIC AND OPTION YEAR TOTALS
No Price to be submitted for Pricing Matrix
No Price to submitted for Pricing Matrix Travel will be a FFP effort at time of event IAW Joint Travel Regulations
CLIN
SUB
CLIN Noun / CLIN Title
FY16-17 1 YR
BASIC Annual BEQ / or Yearly Hours Estimate
FY17-18 Option Yr 1 Annual
BEQ / or Yearly Hours Estimate
FY18-19 Option Yr 2 Annual
BEQ / or Yearly Hours Estimate
FY19-20 Option Yr 3 Annual
BEQ / or Yearly Hours Estimate
FY20-21 Option Yr 4 Annual
BEQ / or Yearly Hours Estimate
X001 Tear Down & Inspect 13 14 10 13 13
FY16-17 1250
Yearly Forecast =
FY17-18 1250
Yearly Forecast =
FY18-19 1250
Yearly Forecast =
FY19-20 1250
Yearly Forecast =
FY20-21 1250
Yearly Forecast =
X002 AA 1250 Hour Inspection - LEVEL 1 1 1 1 1 1 AB 1250 Hour Inspection - LEVEL 2 1 0 1 0 0 AC 1250 Hour Inspection - LEVEL 3 0 1 0 1 1
FY16-17 2500
Yearly Forecast =
FY17-19 2500
Yearly Forecast =
FY18-19 2500
Yearly Forecast =
FY19-20 2500
Yearly Forecast =
FY20-21 2500
Yearly Forecast =
X003 AA 2500 Hour Inspection - LEVEL 1 2 2 3 3 3 AB 2500 Hour Inspection - LEVEL 2 3 2 2 3 3 AC 2500 Hour Inspection - LEVEL 3 3 4 0 0 1
X004 5000 Hour Inspection - Overhaul 0 0 0 0 0
X005 Unscheduled Engine Removal (UER) 3 4 3 5 4
X006 O&A - Other 5000 (hours) 5000 (hours) 5000 (hours) 5000 (hours) 5000 (hours)
X007 MISTR Rotary Pump (Scavenge Pump) 0 (hours) 600 (hours) 120 (hours) 120 (hours) 120 (hours)
X008 Test Cell Run 5 6 5 6 5
X009 CDRLS - Data Reporting
X010 Travel
FY17-18 Option Yr 1 - CLINs
100X
FY18-19 Option Yr 2 - CLINs
200X
FY19-20 Option Yr 3- CLINs
300X
FY20-21 Option Yr 4- CLINs
400X
T53 CLINs with Best Estimated Quantities (BEQs)
CLIN ITEM DETAILS
FY16-17 1-Yr Basic Period CLINs 000X
T53 Appendix J Pricing Matrix
File details come from the government source that posted it. Updated .