Record_of_Site_Visit_Bldg_418.pdf

PDF 52 KB Posted

Attached to
Bldg 418 - Paint Metal Roof
Solicitation number
FA6712-15-B-0001
Issued by

About this file

Record of Site Visit Bldg 418 10AM 12-11-14

View the file

Other files

File Type Posted
Corrugated_Metal_Dimensions.pdf PDF
Addendum_1_12_Dec_14.docx DOCX document
FA6712-15-B-0001-0001.pdf PDF
JLSS 14-0007_Sheet 03 of 04_A002_North and West Elevations.pdf PDF
01600 products.doc DOC document
01320 progress doc.doc DOC document
00001 cover 100 .doc DOC document
00110 table of contents.doc DOC document
01410 Env Spec Section —
01400 quality requirements.doc DOC document
01783 project record docs.doc DOC document
01500 temp facilities.doc DOC document
01340 submittal procedures.doc DOC document
Davis_Bacon_Wage_Determination_as_of_22_Aug_2014.pdf PDF
JLSS 14-0007_Sheet 02 of 04_A001_Roof Plan.pdf PDF
01010 summary 90 .docx DOCX document
JLSS 14-0007_Sheet 01 of 04_G001_Project Location.pdf PDF
02085 Disturbance of Lead Containing Surface Coatings.doc DOC document
FA6712-15-B-0001.pdf PDF
01770 close out.doc DOC document
01813a apendx.doc DOC document
J34786-1 UDS Level 2 Report Final Report.pdf PDF
09910 Painting 90 .doc DOC document
01340a report.doc DOC document
JLSS 14-0007_Sheet 04 of 04_A003_South and East Elevations.pdf PDF
00115 drawing index.doc DOC document
01813_green procur.doc DOC document
01100 work restrictions.doc DOC document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Painting Building 418 – Site Visit Minutes, Thursday, 11 December 2014:

Government Attendees:

Sue Gitto, Contract Specialist Brian Keenan, Project Manager Dave Martinelli, Contract Specialist Dave Geeza, Engineer Michael Tucker, Contract Specialist Daniel Ellingsen, Lead Contract Specialist

Company Attendees:

Bristol Perfect Pro Painters

Spectrum Constatine Painting Spartan Global Urban Enterprises Green World Contracting

Meeting started promptly at 10 AM, opened by Sue Gitto, then Brian Keenan briefly reviewed the specifications. Following the recap, the attendees went to Building 418. The site vist involved viewing the hangar roof from a vantage point, and ended at approximately 10:20. No site photography was permitted and no one was permitted on the roof.

The following clarifications were made today:

• Work is on the main building only, the roofs on both sides were recently completed

• Remove old, damaged paint only, approximately 75% of the roof, as per the specs

• Encapsulate the current paint that is not being removed

• Apply primer and 2 top coats

• Awardee must provide Lead Abatement Certification

• Due to high winds – Awardee will need to provide plan to ensure capturing all of the abated lead paint

• Awardee is responsible for removal of the lead paint chips from the gutters and downspouts that are created from this job only.

• Evacuation from roof is not required when planes land. However, due to high winds typical of the area, additional winds when planes land, plus the angle and height of the roof, contractors need to give extra consideration to ensure the safety of their employees

• Anything dropped (i.e. paint brush, screw, washer, pen, etc.) will need to be retrieved immediately for the safety of Government property (e.g. aircraft)

• Metal Roof Corrugation Dimensions – Brian is researching…

• Section 02085 – Disturbance of Lead Containing Surface Coatings, 3.8 E clarification:

contractor is required to achieve to the baseline level

NOTE: Submit any additional questions via email to: Sue.Gitto@us.af.mil no later than Noon on Monday, 15 Dec 2014. Answers will be posted on FBO no later than Friday, 19 Dec 2014.