01100 work restrictions.doc

DOC document 33 KB Posted

Attached to
Bldg 418 - Paint Metal Roof
Solicitation number
FA6712-15-B-0001
Issued by

About this file

Specifications

View the file

Other files

File Type Posted
Corrugated_Metal_Dimensions.pdf PDF
Addendum_1_12_Dec_14.docx DOCX document
FA6712-15-B-0001-0001.pdf PDF
Record_of_Site_Visit_Bldg_418.pdf PDF
JLSS 14-0007_Sheet 03 of 04_A002_North and West Elevations.pdf PDF
01600 products.doc DOC document
01320 progress doc.doc DOC document
00001 cover 100 .doc DOC document
00110 table of contents.doc DOC document
01410 Env Spec Section —
01400 quality requirements.doc DOC document
01783 project record docs.doc DOC document
01500 temp facilities.doc DOC document
01340 submittal procedures.doc DOC document
Davis_Bacon_Wage_Determination_as_of_22_Aug_2014.pdf PDF
JLSS 14-0007_Sheet 02 of 04_A001_Roof Plan.pdf PDF
01010 summary 90 .docx DOCX document
JLSS 14-0007_Sheet 01 of 04_G001_Project Location.pdf PDF
02085 Disturbance of Lead Containing Surface Coatings.doc DOC document
FA6712-15-B-0001.pdf PDF
01770 close out.doc DOC document
01813a apendx.doc DOC document
J34786-1 UDS Level 2 Report Final Report.pdf PDF
09910 Painting 90 .doc DOC document
01340a report.doc DOC document
JLSS 14-0007_Sheet 04 of 04_A003_South and East Elevations.pdf PDF
00115 drawing index.doc DOC document
01813_green procur.doc DOC document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Copyright 2002 and 2005 by The American Institute of Architects (AIA)

Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA

SECTION 01100 - WORK RESTRICTIONS

This Section uses the term "Architect." Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.

Much of this Section consists of Project-specific data. Examples given in the model text in the Evaluations illustrate possible Section content; use the model text to develop text for specific Project requirements. See Evaluations.

Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.

PART 1 - GENERAL

1.1 CONTRACTOR ACCESS TO AIR FORCE INSTALLATION

A. Access to Air Force installations in general and access to specific secured areas are subject to Air Force Regulations and procedures and shall be adhered to at all times.

B. Personnel Identification: Provide ID badges for all Contractor and Subcontractor personnel who make frequent visits to or perform work on the base.

1. Badges shall be hard paper stock (approx. 2 x 3 inches) and shall be enclosed by a plastic laminated cover.

2. The badge shall include a photo, employee’s name, employee’s signature, and Contractor’s company name.

3. The badge shall be worn by each employee such that it is visible at all times.

1.2 USE OF PREMISES

Retain one of two paragraphs below. Retain first paragraph if Project is on a vacant site or in an unoccupied building being renovated and there are no Owner-occupancy requirements. Retain second if Owner will occupy portions of an existing site or building. Revise to suit Project.

A. General: Contractor shall have use of premises indicated by Contracting Officer for construction operations, including use of Project site, during construction period.

1. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time. Work schedule shall be as follows:

a. Normal work hours shall be between 7:30 and 4:00 PM with no work on federal holidays.

b. Any deviation from the normal working hours shall be approved three (3) working days in advance by the Contracting Officer.

2. Work is prohibited on UTA Training Weekends which will occur two weekends per month, typically the first and third weekends of the month.

3. Comfort stations are not provided by 911th Air Wing.

4. Any type of advertising, including signs for advertising are not permitted on base.

5. Taking of photographs is prohibited except by the written permission coordinated through the Contracting Officer.

6. Firearms are not permitted on the base.

7. Contractor is to expect that the facility will be occupied during the entire project.

The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.Retain paragraph and subparagraphs below if Project site will be accessible to other parties or if parts of a building being renovated will be occupied during construction; revise to suit Project. See Evaluations for model text.

B. Use of Site: Limit use of premises to work in areas indicated by Contracting Officer. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to immediate areas of construction.

Retain first subparagraph below if reduced site disturbance is required for LEED Credit SS 5.1. Credit applies only to greenfield sites. See Evaluations.

2. Owner Occupancy: Allow for Government occupancy of Project sites.

Subparagraph and associated subparagraphs below are examples of a special requirement appropriate to many projects; revise to suit Project or delete.

3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

Insert other paragraphs, as appropriate, describing additional limitations on use of site by construction personnel. See Evaluations for model text.

Retain paragraph below if the Work involves existing occupied building; otherwise, delete.

C. Use of Existing Buildings: Maintain existing buildings in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect buildings and their occupants during construction period.

1. Avoid use of Base Facilities, including toilet facilities, unless approved in writing by Contracting Officer.

D. Contractor shall assume full responsibility for protection and safekeeping of products under this Contract.

E. Contractor shall be responsible for protecting all remaining permanent equipment.

F. Contractor shall obtain and pay for the use of additional storage or work areas needed for operation under this Contract.

Insert additional paragraphs specifying specific limitations on use of existing building. See Evaluations for model text.

END OF SECTION 01100

911th AIRLIFT WING

WORK RESTRICTIONS

911TH CIVIL ENGINEERING

PAINT METAL ROOF, BLDG 418

01100 - 1

1100 HERMAN AVE

JLSS 14-0007

CORAOPOLIS, PA 15108