CONFORMED SOLICITATION DOCUMENT (AMENDMENT 02)
View the file
Other files for this federal contract opportunity
Show all 50
Air Force Multiple-Award Construction IDIQ, Germany has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section B - Supplies or Services and Prices
BID SCHEDULE
Performance Period: 01 OCTOBER 2009 or date of award (whichever is later), through “60 Months after effective date of award”.
CLIN
DESCRIPTION
PRICE
INFO CLIN
UNIT PRICE BOOK (UPB).
Contractor shall furnish all plant, labor, materials, equipment, etc., as necessary to perform work detailed in the attached General Statement of Need (SON) for the unit price specified in the Unit Price Book (UPB) for Standard/Non-Standard Work Hours for task orders as applicable. This CLIN applies to all sub-trades.
0001AA
UPB FOR STANDARD HOURS.
Contractor shall perform work during standard hours as specified in Section F. Standard hour is defined as: Monday through Friday (0600 to 1800), excluding German Holidays. The Government estimates that standard hours will be used 90% of the time. Contractor is not entitled to an equitable adjustment if actual work reflects a different value.
MAXIMUM
COEFFICIENT
0001AB
UPB FOR NON-STANDARD HOURS.
Contractor shall perform work during non-standard hours as specified in Section F. Non-Standard hour is defined as: Monday through Friday (1800 to 0600) AND German Holidays and weekends. The Government estimates that non-standard hours will be used 10% of the time. Contractor is not entitled to an equitable adjustment if actual work reflects a different value.
MAXIMUM
COEFFICIENT
| 0002 |
| LUMP SUM ORDERING PROCEDURE (LSOP). |
Contractor shall furnish all plant, labor, materials, equipment, etc., as identified at the task order site visit to perform work as detailed in the attached General Statement of Need (SON)
***LUMP SUM PRICE PER TASK ORDER
*** ONLY OFFERS RECEIVED IN € (EURO) WILL BE ACCEPTED
End of bid schedule
PRICE/COST INFORMATION
SECTION B: PRICE/COST INFORMATION
COST LIMITATIONS: Task orders may be subject to Statutory Cost Limitations. If so, the limitation will be cited in the applicable task order.
XXX
B-1. NOTES REGARDING MAXIMUM COEFFICIENTS:
In order to be considered for award, each offeror must submit maximum coefficients for sub CLINS 0001AA and 0001AB as identified above. The maximum coefficient is the price multiplier that the contractor offers. The Government uses this multiplier to determine the price of work for each task on individual task orders. The Government established unit prices listed in the UPB (material, equipment, and labor without any markups for material, equipment, labor, subcontractor, overhead, or profit), are multiplied times the maximum coefficient to arrive at the actual price for a unit of work. An example of a decrease from the prices in the UPB would be “0.98.” An example of an increase above the prices in the UPB would be “1.06.”
NOTE: Maximum Coefficients are only a not-to-exceed (NTE) value and the Contractor may propose lower coefficients when competing for individual task orders.
The offeror’s price percentage factor (maximum coefficient) must be sufficient to cover all costs including (but not limited to) all general & administrative expenses; computer expense; overhead; profit; project direct costs; licenses; certifications; protection or moving of Government property; mobilization and demobilization expense; engineering/technical design support services; daily and final cleanup; gross receipts tax; general conditions (superintendent salaries, builder’s risk insurance); site and home office overhead; wage determination differential; special clothing or equipment for workers; equipment rental (offeror is expected to hire subcontractors which have their own equipment common to the trade); all insurance for all employees; portable toilets; traffic barricades; flag persons; safety equipment; additional supervision; material waste; swell and compaction; paperwork associated with the contract; consultant fees; on and off site storage separated according to reusable and unusable materials; all costs for breakage-, cutting-, gritting loss; the provisioning of machines; scaffolding with a working platform up to 2m height; freight and other transportation costs to the location of use within the real property; unloading and costs of haulage materials; dumping fees, and all contingencies, as well as costs associated with compliance of environmental, labor, and tax laws and all other contract requirements, as no allowance will be made after contract award.
Section C - Descriptions and Specifications
GENERAL INFORMATION
SECTION C: DESCRIPTION/SPECIFICATIONS
The contract is for a broad range of sustainment, maintenance, repair, alteration, and minor construction projects to include residential and commercial work for the Kaiserslautern Military Community (KMC) and Spangdahlem Air Base areas. The primary bases/geographically-separated units (GSU) are Ramstein Air Base, Spangdahlem Air Base, Sembach Air Base, Einsiedlerhof Air Station, Kapaun Air Station, Landstuhl and Vogelweh Military Family Housing, Bitburg Annex, Oberweis and Buechel. The maximum radius for this contract will be the borders of Germany. The work is required in support of the 435th Civil Engineer Group and 52 Civil Engineer Squadron.
C-1. GENERAL INFORMATION
The following documents are to be used in the execution of work under this contract:
a. General Statement of Need (including annexes); Section J, attachment 1.
(1) Work is to be performed in accordance with the publication “Deutsche Industrie Normen (DIN)” , “Verdingungsordnung fuer Bauleistungen, Part C (VOB, part C)”, ”Landesbauordnung Rheinlandpfalz (LbauO)” and the scope of work specified in individual Task orders issued against this contract
(2) The intent of the Statement of Need (SON) is to furnish concise industrial and commercial standards for a broad range of construction within Government properties.
b. Unit Price Book (UPB)
(1) The UPB contains pricing information and shall serve as the basis for establishing the value of the work to be performed on a unit price basis. All UPB unit prices are comprised of items such as material, labor, and equipment delivered and installed at the job site. No additional cost shall be incurred by the Government for the unit prices without the approval of the Contracting Officer.
(2) The UPB consists of the sections as listed in section H-5 of the solicitation.
C-2. GENERAL STATEMENT OF WORK (SOW)
SEE ATTACHMENT 1, SECTION J
Section D - Packaging and Marking
SECTION D-PACKING AND MARKING
SECTION D. PACKING AND MARKING
ANY SPECIAL PACKING OR MARKING WILL BE IDENTIFIED AT THE TASK ORDER LEVEL.
Section E - Inspection and Acceptance
SECTION E. INSPECTION AND ACCEPTANCE TERMS
1) Authorized representatives from 435 CEG and 52 CES Engineer Sections, as applicable, will be responsible for inspection and/or acceptance. The inspectors will be identified by name at the task order site visit. The Contracting Officer is responsible for final acceptance of the work.
2) Notice of Completion of Task Order/Prefinal and Final Inspection
a) The contractor shall submit a request for final inspection, in writing, to the Contracting Officer. The final inspection will be requested at least five (5) business days before the desired date or otherwise negotiated with the Contracting Officer.
b) The Government inspector, along with the contractor, shall conduct a pre-final inspection at least three (3) business days prior to the final inspection. The contractor shall correct any discrepancies noted prior to the final inspection.
The Government inspector will conduct the final inspection in the presence of the Contract Administrator and contractor. The contractor will correct any discrepancies noted within the time specified by the Contracting Officer. Upon request, final payment will be made after correction of all discrepancies.
CLAUSES INCORPORATED BY REFERENCE
| 52.246-12 |
| Inspection of Construction |
| AUG 1996 |
| 52.246-13 |
| Inspection--Dismantling, Demolition, or Removal of Improvements |
| AUG 1996 |
Section F - Deliveries or Performance
NEW SECTION F PER AMENDMENT 2
CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC
PER TASK ORDER
to be determined
PER TASK ORDER
PER TASK ORDER
to be determined
PER TASK ORDER
F-1. HOLIDAY PERFORMANCE AND HOURS OF WORK:
Normal access to the job site shall be between the hours of 0600 to 1800 hrs, Monday through Friday. Work performed after standard hours or on German holidays shall be coordinated by the Contractor and negotiated with the C. O. on the task order level. Some work areas may not be accessible on so-called “Goal days” or “Family days”.
Training Holidays, Goal days or Family days: These are unique to military forces stationed in Europe. Most accompany Federal holidays and dates are determined each year. A current listing may be obtained from the Contracting Officer.
List of US Holidays:
(1) 1 January*
New Year's Day
(2) 3rd Monday in January Martin Luther King's Day
(3) 3rd Monday in February Presidents Day
(4) Last Monday in May Memorial Day
(5) 4 July*
Independence Day
(6) 1st Monday in September Labor Day
(7) 2nd Monday in October Columbus Day
(8) 11 November*
Veteran's Day
(9) 4th Thursday in November Thanksgiving Day
(10) 25 December*
Christmas Day
*When the holiday is on a Saturday, the preceding Friday will be the U.S. holiday. When the holiday is on a Sunday, the following Monday will be the U.S. holiday.
List of Host Country Holidays in Germany are:
(1) 01 Jan
New Years Neujahrtag
(2) **
3 Kings Day Heilige 3 Koenige
(3) **
Good Friday Karfreitag
(4) **
Easter Monday Ostermontag
(5) 01 May Labor Day Tag der Arbeit
(6) **
Ascension Day Himmelfahrt
(7) **
Whit Monday Pfingstmontag
(8) **
Corpus Christi Fronleichnam
(9) 03
Oct Union Day Tag der Deutschen Einheit
(10) 01 Nov All Saints Day Allerheiligen
(11) 25 Dec Christmas Weihnachten
(12) 26 Dec Christmas Weihnachten **Indicates dates change each year. May be applicable on a state by state basis where work is performed under the contract.
F-2. LIQUIDATED DAMAGES (LDs)
LDs will be incorporated in all task orders totaling $550,000.00 or greater. The C. O. reserves the right to incorporate LDs for task orders less than this amount if he/she determines that LDs are warranted due to mission failure, loss of assets, etc. If LDs are used, they will be announced at the task order site visit.
If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount specified in the task order for each calendar day of delay until the work is completed or accepted. Please reference clause 52.211-12 for additional information.
F-3. CLAUSES INCORPORATED BY FULL TEXT [ IAW FAR 11.401 ]
PERIOD OF PERFORMANCE: Performance under this contract shall be for a maximum of 5 years from the effective date of contract award. Performance periods for each task order shall be negotiated prior to award of task order.
PLACE OF PERFORMANCE: Work under this contract shall be at Air Force installations within the borders of Germany to include geographically separated units (GSU). Spandahlem Air Base and Ramstein Air Base contracting offices will administer the basic contract and task orders.
PERIOD OF CONTRACT: The basic period of this contract shall be in effect from the effective date of the contract award plus 60 months.
CLAUSES INCORPORATED BY REFERENCE
| 52.247-34 |
| F.O.B. Destination |
| NOV 1991 |
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within (SEE INDIVIDUAL TASK ORDERS) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than (SEE INDIVIDUAL TASK ORDERS). The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of (determined per task orders) for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.247-55 F.O.B. POINT FOR DELIVERY OF GOVERNMENT-FURNISHED PROPERTY (JUN 2003)
(a) Unless otherwise specified in this solicitation, the Government will deliver any Government-furnished property for use within the contiguous United States or Canada to a point specified by the Contractor in the offer. If the Government makes delivery by railroad, the f.o.b. point will be private siding, Contractor's plant. If the Contractor's plant is not served by rail, the f.o.b. point will be railroad cars in the same or nearest city having rail service. The Government may choose the mode of transportation and the carriers and will bear the cost of all line-haul transportation to the specified destination.
(b) If the destination of the Government-furnished property is a Contractor's plant located outside the contiguous United States or Canada, the f.o.b. point for Government delivery of Government-furnished property will be a Contractor-specified location in the contiguous United States. If the Contractor fails to name a point, the Government will select as the f.o.b. point the port city in the contiguous United States nearest to the Government-furnished property that has regular commercial water transportation services to the offshore port nearest the Contractor's plant.
(c) Unless otherwise directed by the Contracting Officer or provided in the contract, the Contractor shall return all Government-furnished equipment, supplies, and property, including all property not returned in the form of acceptable end items, to the point at which the Government property was originally furnished to the Contractor under the contract. Notwithstanding the fact that the Government may have furnished the property at the Contractor's plant, the Contracting Officer may direct the Contractor to deliver the Government property being returned to, and load, block, and brace it in, railway cars in the city in which the Contractor's plant is located, or, if the Contractor's city is not served by rail service, in the nearest city having rail service. Unless otherwise specified in the contract, all property shall be packed in containers conforming with the rules of common carrier published tariffs so as to be free of penalty charges by the carrier designated for shipment by the Government.
(End of clause)
Section G - Contract Administration Data
GENERAL INFORMATION
SECTION G. CONTRACT ADMINISTRATION
(a) The resulting contract shall be administered by the following Contract Activity(s):
FOR KMC & Ramstein AB:
700th CONTRACTING SQUADRON
LGCC-SABER
Am Opelkreisel, ROB, GEB 164
D-67663 Kaiserslautern FOR Spangdahlem AB
52th CONTRACTING SQUADRON/LGCC
Civil Engineering Flight
Arnold Blvd, Bldg 128
D-54529 Spangdahlem
(b) All correspondence and data submitted by the contractor under this contract shall reference the contract number, delivery order number, project number, project title (if applicable) and must be written in English.
NOTE:
No changes, deviations, or waivers shall be effective without a modification of the contract executed by the Contracting Officer authorizing such changes, deviations or waivers.
ACCOUNTING AND APPROPRIATION DATA:
The appropriate Accounting and Appropriate Data will be cited on Individual Task Orders.
INVOICES:
The contractor will be paid no more than once a month on the submission of proper invoices through Wide Area Work Flow (WAWF) for the services performed during the preceding month.
https://wawf.eb.mil/ A separate invoice shall be submitted for each Task Order. A properly prepared invoice shall be submitted identifing the type of funds requested by Contract Line Item Number (CLIN) and its corresponding two-digit Account Contract Reference Number (ACRN).
Section H - Special Contract Requirements
SPECIAL CONTRACT REQUIREMENTS
SECTION H. SPECIAL CONTRACT REQUIREMENTS
H-1. GENERAL TERMS:
(a) This is a Firm Fixed Price, Indefinite Delivery, Indefinite Quantity, type contract and will include a wide variety of individual specific elements of construction work identified in the UPB. Construction work not covered by the UPB will be presented by the Contractor as a Lump Sum Ordering Procedure (LSOP). During the contract period, 435 CEG or 52 CES will identify construction tasks required to complete specific projects and the Contracting Officer will negotiate and issue individual task orders to the contractor to perform the projects. The contractor shall furnish all materials, equipment and personnel necessary to design, manage, and accomplish each task order. The Government will issue a Notice to Proceed for each task order placed against the basic contract.
(b) Guaranteed Minimum: $50,000.00 per awardee
(c) The "maximum", as referred to in the contract clause FAR 52.216-22, "Indefinite Quantity", is the contract total estimated cost. The Government anticipates that there will be a maximum estimated cost of $275,000,000.00 for the 5-year ordering period. This estimated "maximum" amount may only be exceeded through a bi-lateral agreement between the Government and contractor. The Contractor must be prepared to perform up to the contract maximum estimated cost of $275,000,000.00. If the Government's requirements for services set forth in the solicitation do not result in orders in the amount described as "maximum", the event shall not constitute the basis for an equitable adjustment under this contract.
H-2. CONSTRUCTION START-UP PERIOD:
The Contractor must have the organization and capability to start performance on the next day after the award of the basic contract.
H-3. Performance Evaluation Meetings:
The contract manager shall be required to meet monthly, or more often than monthly depending on the workload of the Contractor, with the 435th CES/CEPM Chief and the Contracting Officer (CO) to discuss progress and quality of work being performed. The contract manager for the Spangdahlem area shall be required to meet monthly or more often than monthly depending on the workload of the Contractor, with the 52 CES/CEPM OIC/NCOIC and the CO to discuss progress and quality of work being performed.
H-4. PROGRAM STATUS REVIEWS (PSR):
The Contractor shall conduct Program Status Reviews at least annually (or more often as needed). As part of the Program Status Reviews, the Contractor shall provide a Program Status Briefing. The briefing, including presentation materials, will include the following as a minimum: a) overall CES/CECM Program report (number of projects to date, total active projects, total Dollars/Euro awarded, percentage of UPB/Lump-Sum awarded, quality assurance problems, performance difficulties, etc.); b) Brief overview of current projects/task orders, highlighting any “high interest” tasks; c) Identification of key personnel working and major subcontractors; d) Any other item determined necessary by the Contracting Officer. The contractor shall be responsible for coordinating with the Contracting Officer for scheduling the briefings, facility and attendance arrangements. As a minimum, the following personnel shall be invited to attend: Contracting Squadron Construction Flight Chief (700 CONS & 52 CONS), Engineering & Construction Flight Chief (435th CES/CEC & 52th CES/CEC), and CES/SABER Chief and the Contracting Officer.
H-5. NOTES REGARDING THE UNIT PRICE BOOK (UPB):
The following table lists the UPB version (STLB Bau Z) that shall be applied to the proposed contract:
| Book # |
| Title |
| Date of release |
| 600 |
| Erdarbeiten |
| Sep 08 |
| 606 |
| Abwasserkanalarbeiten |
| Sep 08 |
| 607 |
| Druckrohrleitungsarbeiten im Erdreich |
| Sep 08 |
| 608 |
| Drän- und Versickerungsarbeiten |
| Sep 08 |
| 615 |
| Verkehrswegebauarbeiten |
| Sep 08 |
| 620 |
| Landschaftsbauarbeiten |
| Sep 08 |
| 621 |
| Dämmung an technischen Anlagen |
| Sep 08 |
| 630 |
| Mauerarbeiten |
| Sep 00 |
| 631 |
| Beton- und Stahlbetonarbeiten |
| Sep 08 |
| 634 |
| Zimmer- und Holzbauarbeiten |
| Sep 08 |
| 638 |
| Dackdeckungs- und Dachabdichtungsarbeiten |
| Sep 08 |
| 639 |
| Klempnerarbeiten |
| Sep 08 |
| 650 |
| Putz- und Stuckarbeiten |
| Sep 00 |
| 651 |
| Gerüstarbeiten |
| Sep 08 |
| 652 |
| Fliesen- und Plattenarbeiten |
| Sep 00 |
| 653 |
| Estricharbeiten |
| Sep 08 |
| 655 |
| Tischlerarbeiten |
Sep 00
| 656 |
| Parkettarbeiten |
Sep 08
| 657 |
| Beschlagarbeiten |
| Sep 00 |
| 660 |
| Metallbau- und Stahlbauarbeiten |
| Sep 08 |
| 661 |
| Verglasungsarbeiten |
| Sep 08 |
| 663 |
| Beschichtungs- und Tapezierarbeiten |
| Sep 00 |
| 665 |
| Bodenbelagsarbeiten |
| Sep 00 |
| 679 |
| Raumlufttechnische Anlagen |
| Sep 08 |
| 680 |
| Heizanlagen und zentrale Wassererwärmungsanlagen |
| Sep 08 |
| 681 |
| "Gas-, Wasser- und Abwasserinstallationsarbeiten" |
| Sep 08 |
| 682 |
| Elektrische Kabel- und Leitungsanlagen in Gebäuden |
| Sep 08 |
| 684 |
| Blitzschutzarbeiten |
| Mar 04 |
Additional Line Item Listing (Section J, Attachment 05) In addition Section J, Attachment #5 contains an additional items list for items not covered by the listed UPB. Those items address customer established item standards and need to be considered and incorporated into the contractor provided software program. These items shall be considered by the offerors when calculating their max. coefficients.
The test project will require the use of the UPB and additional line items as described above. The contractor shall provide their Test Project Proposal in Excel/PDF format.
This UPB (and the additional line item listing shown in Section J, attachment 05) shall be used for the entire 5-year ordering period without any changes.
All offerors need to have a copy of the UPB on hand in order to calculate their basic contract maximum coefficients. The UPB and additional items list shall also be applied by the offerors when calculating the test project proposal and be applied by the awardees when calculating price at the task order level.
The hardcopy version of the this UPB is available from the following source:
Beuth Verlag GmbH
Burggrafenstraße 6 10787 Berlin
Required Submittals for all Contract Awardees after contract award:
All Offerors who receive a basic contract award shall provide UPB hardcopy books and software UPB program. ARRIBA 12.3 or any suitable substitute that is GAEB compatible/PDF format will be acceptable to the Government, provided it meets the below criteria and has been approved through the Contracting Officer prior to submittal. Most current software versions shall be provided.
Possible source for the software is:
RIB Software AG
Vaihinger Straße 151 70567 Stuttgart
Submittal package after contract award shall consist of the following:
· 2 complete sets of hardcopy books of the UPB described above.
· 2 full user licenses for Software Program described above. This shall include annual updates and initial incorporation of the additional line items described below provided by the C. O. for a five year period. Translation of the electronic UPB into English.
· Adding all the additional line items (Section J, Attachment 05) to the software program (and translate into English).
· Provide initial and annual user training for the provided software to an average 8 Government users.
· The software must have an index in the front to facilitate easy access to all data.
· The software must have the capability to add additional UPB line items.
H-6. TASK ORDER SAMPLE CALCULATION
The following sample calculation illustrates the use of the UPB (standard and non-standard hours) and Lump-Sum Ordering Procedures (LSOP). This content shall be applied in providing the test project proposal as well as on any future task order proposals. The contractor has submitted a maximum coefficient for standard and non-standard hours as shown below. One item was not contained in the UPB so therefore the Contractor submitted a Lump Sum Proposal for that item. All figures are fictitious and may or may not exist in the UPB used for this contract.
SAMPLE DESCRIPTION OF WORK: Replace sidewalk and improve storm drainage. For this example; the following coefficients are used:
Standard hours -- .50 Non-standard hours -- .60
Note: table below was updated per Amendment #2. More columns made be used for the proposal as long as all information is below as shown below.
| TYPE OF WORK |
| DESCRIPTION/QTY. |
| PRICE FROM UPB |
Earth Work (standard hours)
| Item 00.02.010.00 |
| Top soil 10-20 cm 500 m3 x 40.00 |
| € 20,000.00 |
| Item 00.02.011.00 |
| Top soil seeding, 1000 m2 x 4.00 |
| € 4,000.00 |
| Subtotal 1 |
| € 24,000.00 |
Drainage Work (standard hours)
| Item 06.02.03.01 |
| Top soil remove, 150 m2 x 7.5 |
| € 1,125.00 |
| Item 06.03.01.02 |
| Excavate construction pit, 400 m3 @ 23.00 |
| € 9,200.00 |
| Item 06.03.01.02 |
| Excavate pipe trench, 150 m3 x 40.00 |
| € 6,000.00 |
| Item 06.03.16.00 |
| Pipe cover by sand, 20 m3 x 80.00 |
| € 1,600.00 |
| Item 06.09.01.03 |
| PVC Pipe, 40 m @ 36.00 |
| € 1,440.00 |
| Item 05.11.02.00 |
| Chanel, 6 ea @ 375.00 |
| € 2,250.00 |
| Subtotal 2 |
| € 21,615.00 |
| Subtotal 1 & 2 (standard hour work) |
| € 45,615.00 |
| Standard hour maximum coefficient |
| x 0.50 |
| Adjusted standard hour subtotal |
| € 22,807.50 |
Road Work (non-standard hours)
| Item 15.04.12.01 |
| Curbstones 18x30 cm, 60 m @ 113.00 |
| € 6,780.00 |
| Subtotal |
| € 6,780.00 |
| Maximum Coefficient |
| x 0.60 |
| Adjusted non-standard hour subtotal |
| € 4,068.00 |
Non-UPB Item (LSOP)
| NA |
| Specialized Equipment |
| € 5,080.00 |
| TOTALS |
| UPB costs (standard hours) |
| € 22,807.50 |
| UPB costs (non-standard hours) |
| € 4,068.00 |
| LSOP (Specialized Equipment) |
| € 5,080.00 |
| Total task order proposal including UPB & LSOP |
| € 31,955.50 |
H-7. TASK ORDER; ORDERING UNDER THE UNIT PRICE BOOK (UPB):
All task orders placed under this contract will be competed among the multiple IDIQ awardees, regardless of value. Based on the requirements of the task order and the initial site visit, the Contractor is responsible to determine the required trades to be performed under the task order. The proposed maximum coefficients in the contract will be applied to the corresponding trades to determine the price. The Contractor shall use the UPB as described in H-5 above and consider the additional line item list in Attachment #5.
PROCEDURES:
(a) As the need exists for performance under the terms of this contract, the CO or his/her representative will notify the Contractor of an existing requirement. The following are procedures for ordering from the contract CLINS (at the task order level).
(1) Upon receipt of the task order solicitation, the Contractor shall respond to the needs of the Government within 2 working days (or a shorter time period during emergency requirements) by visiting the proposed work site in the company of the CO (or authorized representative), US Air Force Engineers and a representative of the using agency (if necessary) to conduct a scope validation site visit and conference during which the following will be discussed (but not limited to):
-Site investigation
-Methods and alternatives for accomplishing work
-Definition and refinement of requirements
-Statement of need
-Requirements for plans, sketches, shop/design drawings, submittals, etc
-Preliminary quantities (NOTE: The Contractor establishes his own detailed quantity estimates for use in developing his proposal.)
(2) Upon establishment of the scope of the individual requirement, the Contractor shall then prepare his technical and cost proposal for submission to the CO (in hard copy and electronic format).
(3) The technical proposal includes (but not limited to) identifying tasks, refining quantities, preparing working drawings detailed engineering plans/drawings (as the requirement exists), developing performance times, and including a detailed statement of proposed work.
(4) The cost proposal shall include UPB line item numbers in numerical order, quantities, and unit cost for each pre-priced work item. The Lump-Sum Ordering Procedure (LSOP) may be used if a better price can be obtained than the UPB. If used, LSOP will clearly identify the scope of that portion of work to be executed by the LSOP method. In some cases, a separation of UPB line items into separate groups will be required. (i.e. New Work, Repair, different funding sources).
(5) Measurements shall be in accordance with units specified in the UPB.
(6) From the date of the site visit, the time allowed for submittal of the Contractor's technical and cost proposal for individual requirements will be as follows, unless otherwise directed by the CO. Classification of projects as Routine, Urgent or Emergency will be determined by the Government.
Routine: UPB proposals shall be delivered to the CO no later than ten workdays after the site visit. Projects will be classified as “routine” approximately 75% of the time.
Urgent: UPB proposals shall be submitted within three workdays after the site visit unless mission dictates a shorter time period. Projects will be classified as “urgent” approximately 18% of the time.
Emergency: UPB proposals shall be submitted within 8 hours after the site visit. Projects will be classified as “Emergency” approximately 7% of the time.
(7) Upon receipt of the Contractor's technical and cost proposal, the Government will review the technical proposal for completeness and reasonableness. The Government will return the technical proposals with comments as required.
(8) If the CO directs a work schedule that is during non-standard hours, then the non-standard working hours coefficient indicated on the Bid Schedule shall be applied for those specific items of work that will be performed during non-standard hours. The standard coefficient (multiplier) price for the remaining items of work to be installed will be applied for standard working hours.
(c) If a project is cancelled prior to acceptance of technical proposals, the Government reserves the right to cancel the requirement without any reimbursement.
H-8. LUMP-SUM ORDERING PROCEDURE (LSOP) ITEMS:
Pricing for each task order will be IAW the Unit Price Book unless more favorable pricing is offered via the LSOP. CLIN 0002 may be used for special items that are not covered by UPB, but are generally within the general intent of the contract. Award will be made to the Contractor providing an acceptable proposal and the best overall price (includes UPB and LSOP).
Support Documents Required for LSOP: The Contractor is required to submit a full LSOP package to include detailed statement of work. The SOW shall address all the items shown in the Standardized Technical Proposal (STP) format. Items to be included (but not limited to) will be construction schedule, phasing plan, subcontracting list, etc.
H-9. TASK ORDER INFORMATION:
(a) Task orders will be issued for CLINS 0001AA, 0001AB, and 0002 by the CO using a Standard Form 1155. Each task order will include the following information:
· Date of the task order.
· Contract number, task order number and project number.
· Scope of work, location (building number) and task order lump sum price, inclusive of UPB and LSOP items.
· Delivery or performance data.
· Accounting and appropriation data.
· Any other pertinent data.
(b) The Contractor's proposal on every task order must be supported by necessary documentation as required, to indicate that adequate engineering and planning to accomplish the requirement have been done so as to minimize any delays in the construction process. Examples of documentation required for submittals that might reasonably be expected include sketches, drawings, calculations, catalog cuts, specifications, architectural renderings, detailed scope of work etc. All such design submittals must be approved by the CO prior to start of any actual construction or demolition work.
H-10. TIME EXTENSIONS (Weather):
In case of unusually severe weather, a time extension may be granted. The listing below defines the monthly-anticipated adverse weather delay days for the contract period:
| JAN – 8 days |
| FEB – 8 days |
| MAR – 6 days |
| APR – 5 days |
| MAY – 3 days |
| JUN – 1 day |
| JUL – 0 days |
| AUG – 0 days |
| SEP – 3 days |
| OCT – 5 days |
| NOV – 6 days |
| DEC – 7 days |
The above schedule of monthly-anticipated adverse weather will constitute the base line for monthly (or portion thereof) weather time evaluations. Upon acknowledgment of the Notice to Proceed and continuing throughout the contract on a monthly basis, actual adverse weather days will be recorded by the Contractor on a calendar day basis (include weekends and holidays) and compared to the monthly-anticipated adverse weather days above. The Contractor shall prove to the CO all severe weather delays with a full justification (to include official daily weather report print-outs, concrete curing temperature specifications, etc). The CO reserves the right to deny weather delay claims that are not fully justified.
The number of actual adverse weather days shall be calculated chronologically from the first to the last day in each month. Once the total number of actual adverse weather days anticipated above has occurred, the CO will examine any subsequently occurring adverse weather days to determine whether a Contractor is entitled to time extension. These subsequently occurring adverse weather days must prevent work for 50 percent or more of the Contractor's workday and delay work critical to the timely completion of the project. The CO will convert any delays meeting the above requirements to calendar days and issue a modification.
The Contractor's task order progress schedule must reflect the above anticipated adverse weather delays on all weather dependent activities.
H-11. Warranty Service Requirements:
In addition to FAR clause 252.246-7002, the following applies:
(a) The Contractor shall furnish, as a minimum, 1 primary and alternate name and telephone number of his/her management staff, available 24 hours per day, 7 days per week, for the life of this contract to respond to warranty situations.
(b) Following notification by the CO (or authorized representative), the Contractor shall respond to a warranty service requirement identified by the CO (or authorized representative), in accordance with the “Warranty Service Priority List” of this program. This list prioritizes warranty work into the following categories:
Emergency -- Perform on site inspection to evaluate situation, determine course of action, initiate work within 2 hours and work continuously to completion.
Urgent -- Perform on site inspection to evaluate situation, determine course of action, initiate work within 24 hours and work continuously to completion.
Routine -- All other work to be initiated within 48 hours and work continuously to completion.
Definitions:
Emergency -- Emergency deemed by 435 CES/CEPM or 52 CES/CEPM such as a life-threatening situation caused by a utility outage deemed hazardous to the safety of personnel.
Urgent -- All utilities, including HVAC, plumbing and electrical. Also, intrusion alarm systems, all roof leaks, kitchen equipment, and fire detection/protection and sprinkler systems.
Routine -- All other areas.
(c) Should parts be required to complete the work and these parts are not immediately available, the Contractor shall have a maximum of 12 hours after arrival at the job site to provide the CO with firm, written proposals for emergency alternatives and temporary repairs for Government participation with the Contractor to provide emergency relief until the required parts are available on site for the Contractor to perform permanent warranty repair. The Contractor’s proposals shall include a firm date and time that the required parts shall be available on site to complete the permanent warranty repair. The CO will evaluate the proposed alternatives and select the alternative considered to be in the best interest of the Government to reduce the impact of the emergency condition. Alternatives considered by the CO will include the alternative for the Contractor to “do nothing” while waiting until the required parts are available to perform permanent warranty repair. Negotiating a proposal, which will require Government participation and the expenditure of Government funds, shall constitute a separate procurement action by the Government.
H-12. NOTES REGARDING WORK HOURS:
Standard Working Hours. The Contractor shall perform tasks during the standard working period of 0600 to 1800, Monday through Friday, excluding German Holidays. Standard work hours also apply to work on an American Holiday when the work is pre-approved by the Contracting Officer. The Government estimates that work will be performed during standard hours 90% of the time. This figure is only an estimate. The contractor is not entitled to an equitable adjustment if actual work performed reflects a different value.
Non-Standard Working Hours. Non-standard working hours are defined as the period from 1800 to 0600, Monday through Friday, as well as weekends and German Holidays. The Government estimates that work will be performed during non-standard hours 10% of the time. This figure is only an estimate. The contractor is not entitled to an equitable adjustment if actual work performed reflects a different value.
Items of work to be accomplished during non-standard hours shall be clearly identified in contractor technical/cost proposals, including justification for the request. The Contractor may elect to work during non-standard hours (1800 to 0600); however, a request must be: a) submitted in writing to the 435 CEG or 52 CES Chief of Engineering at least 48 hours in advance, and b) approved by the Contracting Officer if non-standard pricing coefficients are to be applied. Hours worked without prior notification and the approval of the Contracting Officer will be calculated at the pricing coefficients applied for standard hours. The only exception is for task orders subject to an accelerated construction schedule. Accelerated task orders will have the non-standard working hour coefficient applied to the associated task order line items.
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
| 52.202-1 |
| Definitions |
| JUL 2004 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| APR 1984 |
| 52.203-6 |
| Restrictions On Subcontractor Sales To The Government |
| SEP 2006 |
| 52.203-7 |
| Anti-Kickback Procedures |
| JUL 1995 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| JAN 1997 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| JAN 1997 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| SEP 2007 |
| 52.203-13 |
| Contractor Code of Business Ethics and Conduct |
| DEC 2007 |
| 52.204-4 |
| Printed or Copied Double-Sided on Recycled Paper |
| AUG 2000 |
| 52.204-7 |
| Central Contractor Registration |
| JUL 2006 |
| 52.204-9 |
| Personal Identity Verification of Contractor Personnel |
| SEP 2007 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| SEP 2006 |
| 52.211-13 |
| Time Extensions |
| SEP 2000 |
| 52.215-2 |
| Audit and Records--Negotiation |
| MAR 2009 |
| 52.215-8 |
| Order of Precedence--Uniform Contract Format |
| OCT 1997 |
| 52.215-11 |
| Price Reduction for Defective Cost or Pricing Data--Modifications |
| OCT 1997 |
| 52.215-13 |
| Subcontractor Cost or Pricing Data--Modifications |
| OCT 1997 |
| 52.215-17 |
| Waiver of Facilities Capital Cost of Money |
| OCT 1997 |
| 52.215-21 |
| Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing Data--Modifications |
| OCT 1997 |
| 52.222-50 |
| Combating Trafficking in Persons |
| AUG 2007 |
| 52.223-2 |
| Affirmative Procurement of Biobased Products Under Service and Construction Contracts |
| DEC 2007 |
| 52.223-3 |
| Hazardous Material Identification And Material Safety Data |
| JAN 1997 |
| 52.223-5 |
| Pollution Prevention and Right-to-Know Information |
| AUG 2003 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-10 |
| Waste Reduction Program |
| AUG 2000 |
| 52.223-11 |
| Ozone-Depleting Substances |
| MAY 2001 |
| 52.223-14 |
| Toxic Chemical Release Reporting |
| AUG 2003 |
| 52.223-15 |
| Energy Efficicency in Energy-Consuming Products |
| DEC 2007 |
| 52.223-16 |
| IEEE 1680 Standard for the Environmental Assessment of Personal Computer Products |
| DEC 2007 |
| 52.223-17 |
| Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts |
| MAY 2008 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| JUN 2008 |
| 52.225-14 |
| Inconsistency Between English Version And Translation Of Contract |
| FEB 2000 |
| 52.228-3 |
| Worker's Compensation Insurance (Defense Base Act) |
| APR 1984 |
| 52.228-4 |
| Workers' Compensation and War-Hazard Insurance Overseas |
| APR 1984 |
| 52.228-5 |
| Insurance - Work On A Government Installation |
| JAN 1997 |
| 52.229-6 |
| Taxes--Foreign Fixed-Price Contracts |
| JUN 2003 |
| 52.232-5 |
| Payments under Fixed-Price Construction Contracts |
| SEP 2002 |
| 52.232-17 |
| Interest |
| JUN 1996 |
| 52.232-18 |
| Availability Of Funds |
| APR 1984 |
| 52.232-23 |
| Assignment Of Claims |
| JAN 1986 |
| 52.232-27 |
| Prompt Payment for Construction Contracts |
| OCT 2008 |
| 52.232-33 |
| Payment by Electronic Funds Transfer--Central Contractor Registration |
| OCT 2003 |
| 52.233-1 |
| Disputes |
| JUL 2002 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| 52.236-6 |
| Superintendence by the Contractor |
| APR 1984 |
| 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| 52.236-8 |
| Other Contracts |
| APR 1984 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-13 |
| Accident Prevention |
| NOV 1991 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.236-21 Alt I |
| Specifications and Drawings for Construction (Feb 1997) - Alternate I |
| APR 1984 |
| 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| 52.242-13 |
| Bankruptcy |
| JUL 1995 |
| 52.242-14 |
| Suspension of Work |
| APR 1984 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.243-6 |
| Change Order Accounting |
| APR 1984 |
| 52.244-5 |
| Competition In Subcontracting |
| DEC 1996 |
| 52.244-6 |
| Subcontracts for Commercial Items |
| MAR 2007 |
| 52.245-1 |
| Government Property |
| JUN 2007 |
| 52.245-9 |
| Use And Charges |
| JUN 2007 |
| 52.248-3 |
| Value Engineering-Construction |
| SEP 2006 |
| 52.249-2 Alt I |
| Termination for Convenience of the Government (Fixed-Price) (May 2004) - Alternate I |
| SEP 1996 |
| 52.249-3 |
| Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements) |
| MAY 2004 |
| 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| 52.249-10 Alt I |
| Default (Fixed-Price Construction) (Apr 1984) Alternate I |
| APR 1984 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.201-7000 |
| Contracting Officer's Representative |
| DEC 1991 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2008 |
| 252.204-7000 |
| Disclosure Of Information |
| DEC 1991 |
| 252.204-7001 |
| Commercial And Government Entity (CAGE) Code Reporting |
| AUG 1999 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.204-7006 |
| Billing Instructions |
| OCT 2005 |
| 252.205-7000 |
| Provision Of Information To Cooperative Agreement Holders |
| DEC 1991 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country |
| DEC 2006 |
| 252.215-7000 |
| Pricing Adjustments |
| DEC 1991 |
| 252.222-7002 |
| Compliance With Local Labor Laws (Overseas) |
| JUN 1997 |
| 252.223-7004 |
| Drug Free Work Force |
| SEP 1988 |
| 252.223-7006 |
| Prohibition On Storage And Disposal Of Toxic And Hazardous Materials |
| APR 1993 |
| 252.225-7002 |
| Qualifying Country Sources As Subcontractors |
| APR 2003 |
| 252.225-7012 |
| Preference For Certain Domestic Commodities |
| DEC 2008 |
| 252.225-7031 |
| Secondary Arab Boycott Of Israel |
| JUN 2005 |
| 252.225-7041 |
| Correspondence in English |
| JUN 1997 |
| 252.227-7033 |
| Rights in Shop Drawings |
| APR 1966 |
| 252.229-7000 |
| Invoices Exclusive of Taxes or Duties |
| JUN 1997 |
| 252.229-7002 |
| Customs Exemptions (Germany) |
| JUN 1997 |
| 252.231-7000 |
| Supplemental Cost Principles |
| DEC 1991 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| MAR 2008 |
| 252.232-7008 |
| Assignment of Claims (Overseas) |
| JUN 1997 |
| 252.233-7001 |
| Choice of Law (Overseas) |
| JUN 1997 |
| 252.236-7000 |
| Modification Proposals-Price Breakdown |
| DEC 1991 |
| 252.236-7005 |
| Airfield Safety Precautions |
| DEC 1991 |
| 252.236-7006 |
| Cost Limitation |
| JAN 1997 |
| 252.236-7007 |
| Additive or Deductive Items |
| DEC 1991 |
| 252.236-7013 |
| Requirement for Competition Opportunity for American Stell Producers, Fabricators, and Manufacturers |
| JAN 2009 |
| 252.239-7001 |
| Information Assurance Contractor Training and Certification |
| JAN 2008 |
| 252.242-7004 |
| Material Management And Accounting System |
| NOV 2005 |
| 252.243-7001 |
| Pricing Of Contract Modifications |
| DEC 1991 |
| 252.243-7002 |
| Requests for Equitable Adjustment |
| MAR 1998 |
| 252.244-7000 |
| Subcontracts for Commercial Items and Commercial Components (DoD Contracts) |
| JAN 2009 |
| 252.245-7000 |
| Government-Furnished Mapping, Charting, and Geodesy Property |
| DEC 1991 |
| 252.246-7002 |
| Warranty of Construction (Germany) |
| JUN 1997 |
| 252.247-7012 |
| Ordering Limitation |
| DEC 1991 |
| 252.247-7023 |
| Transportation of Supplies by Sea |
| MAY 2002 |
| 252.247-7024 |
| Notification Of Transportation Of Supplies By Sea |
| MAR 2000 |
| 5352.223-9001 |
| Health and Safety on Government Installations |
| JUN 1997 |
52.215-19 NOTIFICATION OF OWNERSHIP CHANGES (OCT 1997)
(a) The Contractor shall make the following notifications in writing:
(1) When the Contractor becomes aware that a change in its ownership has occurred, or is certain to occur, that could result in changes in the valuation of its capitalized assets in the accounting records, the Contractor shall notify the Administrative Contracting Officer (ACO) within 30 days.
(2) The Contractor shall also notify the ACO within 30 days whenever changes to asset valuations or any other cost changes have occurred or are certain to occur as a result of a change in ownership.
(b) The Contractor shall--
(1) Maintain current, accurate, and complete inventory records of assets and their costs;
(2) Provide the ACO or designated representative ready access to the records upon request;
(3) Ensure that all individual and grouped assets, their capitalized values, accumulated depreciation or amortization, and remaining useful lives are identified accurately before and after each of the Contractor's ownership changes; and
(4) Retain and continue to maintain depreciation and amortization schedules based on the asset records maintained before each Contractor ownership change.
The Contractor shall include the substance of this clause in all subcontracts under this contract that meet the applicability requirement of FAR 15.408(k).
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.216-18 Ordering. (OCT 1995)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from DATE OF AWARD THROUGH 60 MONTHS AFTER EFFECTIVE DATE OF AWARD.
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) If mailed, a delivery order or task order is considered "issued" when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.216-19 Order Limitations. (OCT 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $2,500.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor:
(1) Any order for a single item in excess of $5,000,000.00;
(2) Any order for a combination of items in excess of $275,000,000.00; or
(3) A series of orders from the same ordering office within 5 WORKDAYS that together call for quantities exceeding the limitation in subparagraph (1) or (2) above.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) above.
(d) Notwithstanding paragraphs (b) and (c) above, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 3 WORKDAYS days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
(End of clause)
52.216-22 Indefinite Quantity. (OCT 1995)
(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the "maximum". The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum".
(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after COMPLETION OF ALL TASK ORDERS ISSUED DURING THE CONTRACT PERIOD.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
The Government may require continued performance of any services within the limits and at the rates specified in the contract.