About this file

This document provides details for a Multiple Award Construction Contract opportunity at Mountain Home Air Force Base. The solicitation will be for construction, repair, and renovation services across multiple locations in Idaho, with an anticipated contract ceiling of $90 million over a five year period. Individual task orders will range from $2,000 to $15 million. Eligible firms must have the capability to perform design-build and design-bid-build construction projects. The pre-proposal conference included a review of evaluation criteria and a site visit of the sample project involving repairs and upgrades to Building 927. Questions are due by June 23rd and proposals are due July 12th, with award intented for up to five contracts.

PowerPoint presentation

View the file

Other files for this federal contract opportunity

Other files attached to Mountain Home AFB MACC, newest first.
File Type Posted
Solicitation_Amendment_FA489719RA0040001_SF_30.pdf PDF
Attachment_25_Zones_and_Loads.pdf PDF
Attachment_28_MHAFB-Dsize-PROJECT_coversheet.dwg DWG drawing
Q&A_Responses.docx DOCX document
Attachment_27_MHAFB-Dsize-ASBUILT_titleblock.dwg DWG drawing
Attachment_29_Ductwork_Drawing.pdf PDF
Attachment_26_Sample_Contract_Progress_Schedule.pdf PDF
MACC_SITE_VISIT_sign_in_sheet.pdf PDF
SFS_FORM_30_MACC.pdf PDF
Attachment_23_-_WD_Heavy_Ada.pdf PDF
MACC_SOW_Atch_5_-_Contractors_Monthly_Usage_Reporting_Form.pdf PDF
MACC_SOW_Atch_1_-_MHAFB_Temporary_Environmental_Controls_MHAFB_Env_Spec_20180628.pdf PDF
Attachment_4_-_AF_3052_Construction_Cost_Estimate_Breakdown.xls XLS spreadsheet
Attachment_14_-_Project_New_Addition_As-builts_Part1.pdf PDF
Attachment_3_-_Sample_Project_Statement_Of_Objectives_Bldg_927.pdf PDF
Attachment_8_-_Past_Performance_Questionnaire.pdf PDF
Attachment_6_-_AF3064_Contract_Progress_Schedule.xlsx XLSX spreadsheet
Attachment_2_-_MACC_Statement_of_Work.pdf PDF
Attachment_13_-_TOPR.pdf PDF
Attachment_17__WD_Building-Sample_Project.pdf PDF
Solicitation_-_FA489719RA004.pdf PDF
Attachment_1_-_Sections_L_and_M.pdf PDF
Attachment_24_-_WD_Highway_Ada.pdf PDF
MACC_SOW_Atch_3_-AF_Form_103_Work__BCE_Clearance_Request.pdf PDF
Attachment_18_-_WD_Residential_Elmore.pdf PDF
Attachment_21_-_WD_Residential_Ada.pdf PDF
Attachment_16_-_Bldg_927_Areas_of_Work.pdf PDF
Attachment_7_-_AF_Form_66_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment_10__-_Bonding_Information_Request.pdf PDF
Attachment_14_-_Project_New_Addition_As-builts_Part2.pdf PDF
Attachment_22_-_WD_Building_Ada.pdf PDF
Attachment_9_-_Past_Peformance_Information_Sheet.pdf PDF
Attachment_11_-_Financial_Information_Request.pdf PDF
Attachment_20_-_WD_Highway_Elmore.pdf PDF
MACC_SOW_Atch_4_-_Contractor_HAZMAT_Reporting_Form.pdf PDF
Attachment_12_-_Determination_of_Responsibility.pdf PDF
Attachment_19_-_WD_Heavy_Elmore.pdf PDF
Attachment_15_-Schedule_of_Submittals_(Form_66).pdf PDF
MACC_SOW_Atch_2_-_Base_Civil_Engineer_Work_Clearance_Request_20160401.pdf PDF
Attachment_5-_Bid_Schedule.pdf PDF
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Proposal Conference/ Sample Project Site Visit

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

MOUNTAIN HOME AFB, ID

18 June 2019

Welcome to Mountain Home AFB, ID

Agenda

• Introductions

• Submitting Questions

• Purpose and Scope

• Estimated Dollar Threshold

• Offeror Capabilities

• Delivery and Performance Period Requirements

• Section L

• Section M

• Sample Project

Introductions 366th Financial Acquisition Squadron (FAS)

Commander – Maj Brian Williams 366th Financial Acquisition Squadron (FAS)

Director of Contracting/Contracting Officer – Andrea Porter 366th Financial Acquisition Squadron (FAS)

Contracting Chief of Construction – Kevin Kirkendall 366th Civil Engineer Squadron (CES)

Project Manager – Buck Adams 366th Financial Acquisition Squadron (FAS)

Contracting Specialist/Presenter – Emily Morrison

Submitting Questions

ALL QUESTIONS MUST BE SUBMITTED IN VIA

EMAIL TO: kevin.kirkendall.3@us.af.mil And emily.morrison.1@us.af.mil

Due by 23 June 19 No questions will be answered during this

Briefing nor at the Site Visit

RESPONSES TO ALL QUESTIONS RECEIVED WILL

BE POSTED TO FedBizOps

Purpose and Scope

• This is a requirement for a Multiple Award Construction Contract (MACC)

• Provide a vehicle for executing a broad range of maintenance, repair and new construction of buildings, facilities, or base infrastructure, performed under a design/build or bid/build process.

• Work will be performed at MHAFB, off-base Small Arms Ranges, Grasmere Range Complex, Saylor Creek Range Complex, Juniper Butte Range Complex, associated Emitter Sites, Rattle Snake Radar Site, and other MHAFB off-base facilities, as well as Gowen Field, Boise, ID.

• The work is required in support of the Base Civil Engineer Squadron (CES) activities

• The individual requirements will vary in size and complexity at the TO level

• Shortened response time may be required

Estimated Dollar Threshold

The total estimated dollar threshold of this acquisition is $90M for a five (5) year ordering period. This contract will have the following minimum/maximum parameters based on new contract vehicles and historical data from prior mission requirements.

• Maximum contract value: $90,000,000.00

• Minimum contract value: $2,000.00

• Minimum task order amount: $2,000.00

• Maximum task order amount: $15,000,000.00

Offeror Capabilities The successful offeror must posses the following capabilities:

• Sufficient resources to provide a broad range of maintenance, repair, construction and design;

• Ability to manage a design/construction multi-discipline, multi-task program;

• Ability to provide adequate construction staff, technical support staff, and key management;

• Ability to provide 10%, 35%, 65%, 95% and 100% design with stamps on certain elements of construction;

• Adequate bonding capacity for single and multiple task order workload

Delivery or Performance Period Requirements

• The Ordering Period for this contract is one (1) - five (5) year ordering period;

• Each TO awarded under the MACC defines the individual requirement POP.

• The POP for each task order is driven by the nature and complexity of the project, construction season, and lead time for particular construction materials and statutory limitations for new construction

Section L- Instructions, Conditions, and Notices to Offerors

• Offerors must follow the instructions contained in Section L.

• Noncompliance may result in ineligibility.

• Proposals must be received by at the address specified in Section L no later than 1:00 PM MST on 12 July 2019.

• Offers received after the exact time set for receipt of offers will be considered late and therefore ineligible for award.

• Communications: Exchanges of source selection information after submission of proposals will be controlled by the Contracting Officer. Email may be used to transmit such information.

• Proposals shall be submitted to the Government in three separate sections as set forth below:

SECTION PAGE LIMIT NUMBER OF COPIES DESCRIPTION

I No page limitation 2 Electronic Executed Solicitation Documents & Price Proposal

II No page limitation 2 Electronic Technical Proposal

III 15 Pages (3 pages up to 5 relevant contracts)

2 Electronic Past Performance Information Sheets

• Proposal information: Sections I, II, and III shall be submitted electronically on CD-Rs or DVDRs.

• Proposals shall be in the English language and all monies shall be proposed in United States dollars.

• Each page containing proprietary information should be so marked.

• Proposal Submission: Submission of the initial proposal packages via electronic mail will not be accepted.

• Please be aware of base pass procedures and possible gate delays.

• Please follow the specific instructions as provided in Section I, II, III.

• Section I- Contract documentation and price proposal

• Section II- Technical Proposal

• Section III- Past Performance

• Past Performance Questionnaires due:

4:00 PM MST 8 Jul 2019

Section M- Evaluation Process

• Step 1: The Government organizes all proposals in order of price proposed for the sample project from lowest to highest.

• Step 2: Review proposals to ensure compliance with Section L, Instruction to Offerors.

• Step 3: Determine whether clarification is required.

• Step 4: Beginning with the lowest priced proposal and continuing in order of price, the Government evaluates proposals for both Technical Acceptability and Past Performance. NOTE: This evaluation process continues until eight (8) proposals have been found Acceptable for Technical and Past Performance.

• Step 5: [deleted]

• Step 6: The eight (8) proposals found to have an Acceptable rating for Technical and Past Performance have their Price proposal evaluated, using one or more of the techniques defined in FAR 15.404-1, in order to determine if they are reasonable and realistic. NOTE: For a price to be determined reasonable and realistic, the offeror’s sample project total evaluated price (TEP) will not deviate more than 20% (+/-) from the average price of all proposals found Acceptable for Technical and Past Performance.

• Step 7: Of the eight (8) proposals that are determined to be Technically and Past Performance Acceptable, and Price Reasonable and Realistic, the five (5) proposals with the lowest price are chosen for contract award. NOTE: The remaining three (3) of the eight (8) evaluated will be reserved for on-ramping.

Number of Contracts to be Awarded

• The Government intends to award to a target of five (5) contracts.

NOTE: The Government reserves the right to award more than or fewer than the target number of five (5) contracts as a result of this solicitation.

• The Government reserves the right to award the sample project to the awarded firm providing the lowest price for the sample project, subject to the availability of funds.

• The Government requires a minimum acceptance period of 120 calendar days available to the Government for awarding the sample project. NOTE: At the time of award, the Government will issue a task order for the minimum guarantee amount to all of the contractors awarded a contract under the MACC.

On/Off Ramp Procedures

• Purpose: To ensure an adequate number of contractors are available to achieve effective competition;

• All Contract holders are expected to participate;

• Contractors unable to participate shall provide written notice to the Contracting Officer;

• Anniversary of contract award: Government will evaluate each contractor’s participation rate.

On/Off Ramp Procedures

• Failure to participate or marginal/unsatisfactory participation may result in off-ramping;

• Government reserves the right to on-ramp contractor(s) to maintain a pool of up to five contractors;

• Three previously evaluated contractors to submit proposals on the next task order. The lowest-priced technically acceptable of the three previously evaluated contractors is on-ramped.

Sample Project

Performance criteria: Design and install repairs to the existing electrical service, HVAC, and lighting for the administrative portion of Building 927 (PMEL). Project shall include providing a Design Analysis and providing and installing material as a construction project.

Interior photographs will be allowed of existing conditions at Bldg 927 for use in design of work.

Sample Project

Please meet at the bus outside.

Individuals will be taken in groups due to the size of the site.

Reminder

Submit Questions to:

Kevin Kirkendall kevin.kirkendall.3@us.af.mil And

Emily Morrison emily.morrison.1@us.af.mil

Due by 23 June 19

Important TIPS

• Read and understand everything in solicitation before submitting an offer; after contract award it is too late.

• Federal Gov’t cannot award to vendor not registered in SAM.