Attachment_6_-_AF3064_Contract_Progress_Schedule.xlsx

XLSX spreadsheet 77 KB Posted

Attached to
Mountain Home AFB MACC Federal contract opportunity
Solicitation number
FA4897-19-R-A004
Issued by
Department of the Air Force Air Combat Command

About this file

This document provides a contract progress schedule for a federal construction contract. The schedule outlines 24 work elements making up 100% of the project value. It includes bonds, general requirements, site work, concrete, masonry, metals, wood and plastics, thermal and moisture protection, doors and windows, finishes, specialties, equipment, furnishings, special constructions, mechanical, electrical, and design efforts. The schedule assigns a percentage of the total job and planned completion percentages to each reporting period, with reports due on the 15th of each month and a completion date of 25 December 2011. It requires the contractor's signature certifying completion percentages and allows for an inspector and contracting officer to recommend approval or disapproval.

The federal contract opportunity is a presolicitation notice for a multiple award construction contract with a ceiling of $90 million to be awarded by the 366th Contracting Squadron at Mountain Home Air Force Base in Idaho. Work will involve new construction, renovation, alteration, demolition and repair of facilities at Mountain Home AFB and various ranges and sites. Requirements will include design-build, design-bid-build, and individual task orders ranging from $2,000 to $15 million. The solicitation is expected to post on 21 May 2019 with proposals due by the date specified. The notice seeks up to six contractors to receive IDIQ contracts for a five-year ordering period under lowest price technically acceptable procedures.

Attachment 6

View the file

Other files for this federal contract opportunity

Other files attached to Mountain Home AFB MACC, newest first.
File Type Posted
Attachment_28_MHAFB-Dsize-PROJECT_coversheet.dwg DWG drawing
Solicitation_Amendment_FA489719RA0040001_SF_30.pdf PDF
Attachment_25_Zones_and_Loads.pdf PDF
Q&A_Responses.docx DOCX document
Attachment_27_MHAFB-Dsize-ASBUILT_titleblock.dwg DWG drawing
Attachment_29_Ductwork_Drawing.pdf PDF
Attachment_26_Sample_Contract_Progress_Schedule.pdf PDF
MACC_SITE_VISIT_presentation.pdf PDF
MACC_SITE_VISIT_sign_in_sheet.pdf PDF
SFS_FORM_30_MACC.pdf PDF
Attachment_8_-_Past_Performance_Questionnaire.pdf PDF
Attachment_2_-_MACC_Statement_of_Work.pdf PDF
Attachment_13_-_TOPR.pdf PDF
Attachment_17__WD_Building-Sample_Project.pdf PDF
Solicitation_-_FA489719RA004.pdf PDF
Attachment_23_-_WD_Heavy_Ada.pdf PDF
MACC_SOW_Atch_5_-_Contractors_Monthly_Usage_Reporting_Form.pdf PDF
MACC_SOW_Atch_1_-_MHAFB_Temporary_Environmental_Controls_MHAFB_Env_Spec_20180628.pdf PDF
Attachment_4_-_AF_3052_Construction_Cost_Estimate_Breakdown.xls XLS spreadsheet
Attachment_14_-_Project_New_Addition_As-builts_Part1.pdf PDF
Attachment_3_-_Sample_Project_Statement_Of_Objectives_Bldg_927.pdf PDF
Attachment_1_-_Sections_L_and_M.pdf PDF
Attachment_24_-_WD_Highway_Ada.pdf PDF
MACC_SOW_Atch_3_-AF_Form_103_Work__BCE_Clearance_Request.pdf PDF
Attachment_18_-_WD_Residential_Elmore.pdf PDF
Attachment_21_-_WD_Residential_Ada.pdf PDF
Attachment_16_-_Bldg_927_Areas_of_Work.pdf PDF
Attachment_7_-_AF_Form_66_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment_10__-_Bonding_Information_Request.pdf PDF
Attachment_14_-_Project_New_Addition_As-builts_Part2.pdf PDF
Attachment_22_-_WD_Building_Ada.pdf PDF
Attachment_9_-_Past_Peformance_Information_Sheet.pdf PDF
Attachment_11_-_Financial_Information_Request.pdf PDF
Attachment_20_-_WD_Highway_Elmore.pdf PDF
MACC_SOW_Atch_4_-_Contractor_HAZMAT_Reporting_Form.pdf PDF
Attachment_12_-_Determination_of_Responsibility.pdf PDF
Attachment_19_-_WD_Heavy_Elmore.pdf PDF
Attachment_15_-Schedule_of_Submittals_(Form_66).pdf PDF
MACC_SOW_Atch_2_-_Base_Civil_Engineer_Work_Clearance_Request_20160401.pdf PDF
Attachment_5-_Bid_Schedule.pdf PDF
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Progress Schedule

Contract:LINEWork Elements%Report 1Report 2Report 3Report 4Report 5Report 6Report 7Report 8Report 9Report 10Report 11Report 12Report 13Report 14Report 15Report 16Report 17Report 18Report 19Report 20Report 21Report 22Report 23Report 24Check & Balance0.00%
Project Title:NO15-Jan-111-Feb-1115-Feb-111-Mar-1115-Mar-111-Apr-1115-Apr-111-May-1115-May-111-Jun-1115-Jun-111-Jul-1115-Jul-111-Aug-1115-Aug-111-Sep-1115-Sep-111-Oct-1115-Oct-111-Nov-1115-Nov-111-Dec-1115-Dec-1125-Dec-11
Project Number:1Bonds0.75%0.75%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.75%0.000%
Installation:(00000)0.75%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Notice to Proceed:2General Requirements11.00%2.50%1.00%1.00%0.50%0.50%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%1.00%0.25%11.00%0.000%
Calendar Days(01000)2.50%1.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Start Date (NLT):3Site Work8.50%0.00%1.00%1.00%0.70%0.50%0.50%0.50%0.50%0.50%0.50%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%0.20%8.50%0.000%
Completion Date:(02000)0.00%1.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Closeout Date:4Concrete11.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%2.25%2.00%1.50%0.00%1.50%0.00%0.75%0.50%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.50%11.00%0.000%
ABC Construction Company(03000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
SUBMITTED BY5Masonry1.50%0.00%0.00%0.00%0.00%0.00%0.25%0.25%0.25%0.15%0.15%0.00%0.00%0.00%0.00%0.00%0.15%0.10%0.15%0.00%0.00%0.00%0.00%0.00%0.05%1.50%0.000%
(04000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
6Metals3.00%0.00%0.00%0.00%0.00%0.00%0.50%0.50%0.50%0.50%0.25%0.25%0.25%0.25%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%3.00%0.000%
(05000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
7Wood & Plastics4.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%1.00%0.25%0.25%0.25%0.25%0.25%0.25%0.25%0.25%4.00%0.000%
XXXXXX, Senior Project Manager(06000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Date Signed:15-Dec-108Thermal & Moisture4.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%0.50%0.50%0.50%0.50%0.50%0.50%0.00%0.00%0.00%0.00%4.00%0.000%
366 CES/CEN (Recommendation)(07000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
APPROVED DISAPPROVED9Doors & Windows2.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%1.00%0.00%0.00%0.00%0.00%0.00%2.00%0.000%
(08000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
10Finishes13.50%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%2.50%2.50%1.00%1.25%1.25%1.25%1.25%1.25%1.25%13.50%0.000%
(09000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
11Specialties3.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%1.00%0.50%0.25%0.25%3.00%0.000%
XXXXX, Inspector(10000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Date Signed:12Equipment1.50%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.50%0.25%0.25%0.25%0.25%1.50%0.000%
366 CES/CEN(Concurrence)(11000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
CONCUR NON-CONCUR13Furnishings0.00%0.00%0.000%
(12000)0.00%
14Special Constructions2.25%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%0.50%0.50%0.25%2.25%0.000%
(13000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
15Conveying System0.00%0.00%0.000%
(14000)0.00%
MARK STOUGH, Project Manager16Mechanical17.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%3.00%3.50%3.50%3.00%2.00%1.00%0.50%0.25%0.25%17.00%0.000%
Date Signed:17-Dec-10(15000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
366 FAS/PKB (Approval)17Electrical10.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%1.00%1.00%1.00%1.00%0.50%0.50%0.50%0.50%0.50%0.50%0.50%0.50%0.50%0.50%10.00%0.000%
APPROVED DISAPPROVED(16000)0.00%0.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
18Design Efforts7.00%1.00%2.00%1.00%2.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%1.00%7.00%0.000%
(17000)1.00%2.00%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!100.00%
19Scheduled100.00%4.25%4.00%3.00%3.20%1.00%1.50%2.50%3.75%3.40%3.65%1.70%3.20%1.70%3.20%2.95%8.10%7.80%7.35%6.95%6.45%5.70%4.20%4.45%6.00%100.00%0.000%
Scheduled - Cumulative4.25%8.25%11.25%14.45%15.45%16.95%19.45%23.20%26.60%30.25%31.95%35.15%36.85%40.05%43.00%51.10%58.90%66.25%73.20%79.65%85.35%89.55%94.00%100.00%ERROR:#REF!
XXXXXXXXXXXX, Contracting Officer20Actual7.10%1.65%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Date Signed:Actual - Cumulative7.10%8.75%ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!

Environmental Chemical Corporation (ECC) Revision 1 (18 Feb 08) Contract Progress Schedule

AFCEE/ACA-B Form 3064 (25 Jan 08) &"Times New Roman,Regular"&8Page &P of &N FA8903-06-D-8511-0029

Progress Report 1

CONTRACT PROGRESS REPORT PROJECT TITLE:

CONTRACTOR: ADDRESS:

REPORT NO:PERIOD COVEREDPROJECT NO:TASK ORDER:COMPLETION DATE:
1FROM:TO:

LINE NO. WORK ELEMENT % OF TOTAL JOB % COMPLETED THIS PERIOD % COMPLETED CUMULATIVE

1Bonds0.750%0.753%0.753%
(00000)
2General Requirements11.000%3.544%3.544%
(01000)
3Site Work8.500%0.000%0.000%
(02000)
4Concrete11.000%0.000%0.000%
(03000)
5Masonry1.500%0.000%0.000%
(04000)
6Metals3.000%0.000%0.000%
(05000)
7Wood & Plastics4.000%0.000%0.000%
(06000)
8Thermal & Moisture4.000%0.000%0.000%
(07000)
9Doors & Windows2.000%0.000%0.000%
(08000)
10Finishes13.500%0.000%0.000%
(09000)
11Specialties3.000%0.000%0.000%
(10000)
12Equipment1.500%0.000%0.000%
(11000)
13Furnishings0.000%0.000%0.000%
(12000)
14Special Constructions2.250%0.000%0.000%
(13000)
15Conveying System0.000%0.000%0.000%
(14000)
16Mechanical17.000%0.000%0.000%
(15000)
17Electrical10.000%0.000%0.000%
(16000)
18Design Efforts7.000%2.804%2.804%
(17000)
TOTAL100.000%7.102%7.102%
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the Contractor has satisfactorily completed the indicated percentage of the contract per contract specs.
SUBMITTED BY OR FOR
NAME AND TITLESIGNATUREDATE
NAME
Title
RECOMMEND APPROVAL DISAPPROVAL BY INSPECTOR
NAME AND TITLESIGNATUREDATE
INSPECTOR's NAME
Inspector
APPROVED DISAPPROVED BY CONTRACTING OFFICER
NAME AND TITLESIGNATUREDATE

Contracting Officer

Progress Report 2

CONTRACT PROGRESS REPORT PROJECT TITLE:

CONTRACTOR:ADDRESS:
ABC Constuction Company
REPORT NO:PERIOD COVEREDPROJECT NO:TASK ORDER:COMPLETION DATE:
2FROM:TO:

LINE NO. WORK ELEMENT % OF TOTAL JOB % COMPLETED THIS PERIOD % COMPLETED CUMULATIVE

1Bonds0.750%0.000%0.753%
(00000)
2General Requirements11.000%0.709%4.253%
(01000)
3Site Work8.500%0.214%0.214%
(02000)
4Concrete11.000%0.000%0.000%
(03000)
5Masonry1.500%0.000%0.000%
(04000)
6Metals3.000%0.000%0.000%
(05000)
7Wood & Plastics4.000%0.000%0.000%
(06000)
8Thermal & Moisture4.000%0.000%0.000%
(07000)
9Doors & Windows2.000%0.000%0.000%
(08000)
10Finishes13.500%0.000%0.000%
(09000)
11Specialties3.000%0.000%0.000%
(10000)
12Equipment1.500%0.000%0.000%
(11000)
13Furnishings0.000%0.000%0.000%
(12000)
14Special Constructions2.250%0.000%0.000%
(13000)
15Conveying System0.000%0.000%0.000%
(14000)
16Mechanical17.000%0.000%0.000%
(15000)
17Electrical10.000%0.097%0.097%
(16000)
18Design Efforts7.000%0.633%3.437%
(17000)
TOTAL100.000%1.653%8.754%
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the Contractor has satisfactorily completed the indicated percentage of the contract per contract specs.
SUBMITTED BY OR FOR
NAME AND TITLESIGNATUREDATE
Senior Project Manager,
RECOMMEND APPROVAL DISAPPROVAL BY INSPECTOR
NAME AND TITLESIGNATUREDATE
APPROVED DISAPPROVED BY CONTRACTING OFFICER
NAME AND TITLESIGNATUREDATE

Contracting Officer, image4.emf image5.emf image6.emf image1.emf image2.emf image3.emf image10.emf image7.emf image8.emf image9.emf image14.emf image11.emf image12.emf image13.emf

File details come from the government source that posted it. Updated .