This document contains a federal contract opportunity notice and sample contract progress schedule. The federal contract opportunity notice is for a Multiple Award Construction Contract for Mountain Home Air Force Base in Idaho, with a contract ceiling of $90 million. Task orders under the contract may range from $2,000 to $15 million. The North American Industry Classification System code is 236220 and the annual size standard is $36.5 million. The contract will provide new construction, renovation, alteration, demolition, and repair work. The solicitation is expected to be issued on or around May 21, 2019. The sample contract progress schedule is a template for tracking project milestones and percentage of work completed on a monthly basis over the course of a project period.

Attachment 26

View the file

Other files for this federal contract opportunity

Other files attached to Mountain Home AFB MACC, newest first.
File Type Posted
Solicitation_Amendment_FA489719RA0040001_SF_30.pdf PDF
Attachment_25_Zones_and_Loads.pdf PDF
Q&A_Responses.docx DOCX document
Attachment_28_MHAFB-Dsize-PROJECT_coversheet.dwg DWG drawing
Attachment_27_MHAFB-Dsize-ASBUILT_titleblock.dwg DWG drawing
Attachment_29_Ductwork_Drawing.pdf PDF
MACC_SITE_VISIT_presentation.pdf PDF
MACC_SITE_VISIT_sign_in_sheet.pdf PDF
SFS_FORM_30_MACC.pdf PDF
Attachment_23_-_WD_Heavy_Ada.pdf PDF
MACC_SOW_Atch_5_-_Contractors_Monthly_Usage_Reporting_Form.pdf PDF
MACC_SOW_Atch_1_-_MHAFB_Temporary_Environmental_Controls_MHAFB_Env_Spec_20180628.pdf PDF
Attachment_4_-_AF_3052_Construction_Cost_Estimate_Breakdown.xls XLS spreadsheet
Attachment_14_-_Project_New_Addition_As-builts_Part1.pdf PDF
Attachment_3_-_Sample_Project_Statement_Of_Objectives_Bldg_927.pdf PDF
Attachment_1_-_Sections_L_and_M.pdf PDF
Attachment_24_-_WD_Highway_Ada.pdf PDF
MACC_SOW_Atch_3_-AF_Form_103_Work__BCE_Clearance_Request.pdf PDF
Attachment_18_-_WD_Residential_Elmore.pdf PDF
Attachment_21_-_WD_Residential_Ada.pdf PDF
Attachment_16_-_Bldg_927_Areas_of_Work.pdf PDF
Attachment_7_-_AF_Form_66_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment_10__-_Bonding_Information_Request.pdf PDF
Attachment_14_-_Project_New_Addition_As-builts_Part2.pdf PDF
Attachment_22_-_WD_Building_Ada.pdf PDF
Attachment_9_-_Past_Peformance_Information_Sheet.pdf PDF
Attachment_11_-_Financial_Information_Request.pdf PDF
Attachment_8_-_Past_Performance_Questionnaire.pdf PDF
Attachment_6_-_AF3064_Contract_Progress_Schedule.xlsx XLSX spreadsheet
Attachment_2_-_MACC_Statement_of_Work.pdf PDF
Attachment_13_-_TOPR.pdf PDF
Attachment_17__WD_Building-Sample_Project.pdf PDF
Solicitation_-_FA489719RA004.pdf PDF
Attachment_20_-_WD_Highway_Elmore.pdf PDF
MACC_SOW_Atch_4_-_Contractor_HAZMAT_Reporting_Form.pdf PDF
Attachment_12_-_Determination_of_Responsibility.pdf PDF
Attachment_19_-_WD_Heavy_Elmore.pdf PDF
Attachment_15_-Schedule_of_Submittals_(Form_66).pdf PDF
MACC_SOW_Atch_2_-_Base_Civil_Engineer_Work_Clearance_Request_20160401.pdf PDF
Attachment_5-_Bid_Schedule.pdf PDF
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

26-Oct-2018

Jun-19

26-Oct-2018

TBD

Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Total

1.50% 1.50%

0.50% 1.00% 1.50%

10.00% 10.00%

11.00% 11.00% 22.00%

22.00% 22.00%

9.00% 9.00%

6.00% 6.00%

9.00% 9.00% 18.00%

10.00% 10.00%

0.00%

100.00% 0.00% 2.00% 1.00% 0.00% 0.00% 22.00% 10.00% 29.00% 26.00% 10.00%

0.00% 2.00% 3.00% 3.00% 3.00% 25.00% 35.00% 64.0% 90.0% 100.0% 100.00%

Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Total

Form Approved

OMB NO. 0704-0188

DATE SIGNED

DATE SIGNED

11. APPROVED BY:

CONTRACT PROGRESS SCHEDULE

(See Contractor's Instructions on Reverse)

CONTRACTING OFFICER'S SIGNATURE

8. PROJECT TITLE

HVAC Replacement, A Typical Project

9. SUBMITTED BY:

APPROVAL RECOMMENDED BY:

Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters

Services, Directorate for Information, Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302, and to the Office of Management and Budget Paperwork Reduction Project 0704-0188, Washington DC 20503.

Please DO NOT RETURN your form/questionnaire to either of these addresses. Send your completed form/questionnaire to: SAF/AQCP, 1060 Air Force Pentagon Washington DC 20330-1060.

INSTALLATIONS ENGINEER'S SIGNATURE

1. CONTRACT NO.

FA4897-18-F-

2. NTP DATE

3. COMPLETION DATE

%C

DATE

SIGNED

19-Dec-2018

4. PURCHASE REQUEST NO.

LINE

NO

A

WORK ELEMENTS

5. PROJECT NO.

6. ACTUAL STARTING DATE

7. ACTUAL COMPLETION DATE

CONTRACTOR CONTRACTOR'S SIGNATURE

Time Line

5 Equipment

Chiller Installation incl piping6

7 DDC Controls

Bond

Submittals/Locates/layout

Demolition

Site Prep

Project Total

Cum Total

8 Electrical

9 Closeout 10.00%

9.00%

6.00%

18.00%

1.50%

1.50%

10.00%

22.00%

22.00%

LINE

NO

A

WORK ELEMENTS %C

Time Line

0.00% 2.00% 3.00% 3.00% 3.00%

25.00% 35.00%

64.00%

90.00% 100.00%

SEP-18 OCT-18 NOV-18 DEC-18 JAN-19 FEB-19 MAR-19 APR-19 MAY-19 JUN-19

AF IMT 3064, 20030901, V1 PREVIOUS VERSIONS ARE OBSOLETE