SOMS_Building_2379_Storm_Damage

28 KB Posted

Attached to
Repair Storm Damage Building 2379 Federal contract opportunity
Solicitation number
FA4855-16-B-0018
Issued by
Department of the Air Force Special Operations Command

About this file

SOMS

Text of this file

Sheet1

AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALSPROJECT #PROJECT TITLESOLICITATION/CONTRACT NO.
CZQZ16-0015Repair Storm Damage B2379
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM, DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIF OF COMPLIANCESHOP DRAWINGSSAMPLES / COLOR SELECTTEST RESULTSMANF'R RECOMMENDATIONSMANF'R. WARRANTYLICENSED APPLICATORMANUF'S TECHNICAL DATAELECTRONIC FILES (CD)OTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATEFOLLOW-UPCONTRACTOR NOTIFIED: Approval DateCONTRACTOR NOTIFIED: DisApproval DateCONTRACTOR RE-SUBMITTALFINAL APPROVALREMARKS
1Statement of Work §5 Meetings: Preconstruction Meeting Minutes135 working days after meeting is held
2Statement of Work §5 Meetings: Post Survey Briefing135 working days after meeting is held
3Statement of Work (SOW) §21.1 Constrution Schedule AF Form 3064125 working days after meeting is held
4SECTION 01 01 00 Work §1.3 C. Clearance Request AF 1031310 working days prior to start of Construction
5SECTION 01 11 00 §1.4 Salvage Plan1310 working days prior to start of Construction
6SECTION 01 30 00 §1.3 View Location Map1310 working days prior to start of Construction
7SECTION 01 30 00 §1.4 Progress and Completion Pictures13Weekly, Throughout the Duration of the Project
8SECTION 01 30 00 §1.7.2 Superintendent Qualifications1310 working days after Notice to proceed (NTP)
9SECTION 01 35 26 §1.7 Accident Prevention Plan (APP)1315 working days prior to the date of Pre-Construction Meeting
10SECTION 01 35 26 §1.12.2 Accident Reports13NLT 5 working days after accident/near misses
11SECTION 01 35 40.00 20 §1.8 Environmental Protection Plan (EPP)1310 working days after Notice to proceed (NTP)
12SECTION 01 35 40.00 20 §3.3 Field Quality Control Reports1310 working days prior to start of Construction
13SECTION 01 35 40.00 20 §1.7 Material Safety Data Sheets (MSDS)1310 working days prior to bring material on base
14SECTION 01 43 00 §1.1 Traffic Control for Airfield Safety1315 working days after Notice to proceed (NTP)
15SECTION 01 45 00.00 10 §3.2 Contractor Quality Control Plan15 working days after Notice to proceed (NTP)
16SECTION 01 74 19 §1.6 Waste Management Plan1310 working days after Notice to proceed (NTP)
17SECTION 01 78 00 §3.1 As-built Drawings1320 working days after the completion of construction
18SECTION 02 41 00 §1.2.1 Demolition Plan1315 working days prior to start of Construction
19SECTION 02 41 00 §1.10 Existing Conditions1315 working days prior to start of Construction
20SECTION 02 41 00 §1.6 Demolition Notification135 working days prior to start of Construction
21SECTION 07 60 00 §1.3 Flashing Shop drawing and manufacture information (gutters, downspouts, base flashing, flashing at penetrations, drip edge eave flashing331310 working days prior to use of material
22SECTION 07 92 00 §2.1 Sealants3331310 working days prior to use of material
23SECTION 08 11 13 §2.1 Metal Door and Frame33331310 working days prior to use of material
24SECTION 08 91 00 §2.2- 2.3 Wall and Door Louvers31310 working days prior to use of material
25SECTION 09 30 13 §2.1 Tile333310 working days prior to use of material
26SECTION 09 30 13 §2.2- 2.3 Setting-BedTile333310 working days prior to use of material
27SECTION 09 30 13 §2.2- 2.3 Mortar, Grout and Adhesive333310 working days prior to use of material
28SECTION 09 51 00 §1.3 Shop Drawing31310 working days prior to use of material
29SECTION 09 51 00 §2.1 Acoustical Ceiling System and Ceiling Tiles333310 working days prior to use of material
30SECTION 09 65 00 §2.1 VCT TILES333110 working days prior to use of material
31SECTION 09 90 00 §1.3 Coating and Color1310 working days prior to use of material
32SECTION 22 00 00 §3.2 Water Heaters and Hot Water Storage333310 working days prior to use of material
33SECTION 23 00 00 §1.3 Air Handling Unit333310 working days prior to use of material
34SECTION 23 00 00 §1.3 Room Fan-Coil Units333310 working days prior to use of material
35SECTION 23 00 00 §1.3 Metal Ducts333310 working days prior to use of material
36SECTION 23 00 00 §1.3 Supply Diffusers and Returns333310 working days prior to use of material
37SECTION 23 07 00 §1.3 Duct and Pipe Insulation System333310 working days prior to use of material
38SECTION 23 11 25 §1.3 Gas Pipe and Fittings333310 working days prior to use of material
39SECTION 23 11 25 §1.3 Welders Qualifications1310 working days prior to use of material
40SECTION 23 23 00 §2.2 Refrigerant piping material333310 working days prior to use of material
41SECTION 23 23 00 §3.4 Refrigerant piping testing3135 working days after intallation
42SECTION 26 00 00.00 20 §3.4 Electrical Shop Drawings31310 working days after completion of work
43SECTION 26 05 19.00 10 §2 Insulated Conductor wire33310 working days prior to use of material
44SECTION 26 08 00 §1.4.3 Accepatance testing and inspection31310 working days after completion of work
45SECTION 26 20 00 §2.2 Conduit Fittings333310 working days prior to use of material
46SECTION 26 20 00 §2.11 Circuit breakers333310 working days prior to use of material
47SECTION 26 20 00 §2.9 Switches333310 working days prior to use of material
48SECTION 26 56 00 §1.3 Photometric plan31310 working days prior to use of material
49SECTION 26 56 00 §2.1.3 Induction Luminaires333310 working days prior to use of material
50SECTION 26 56 00 §2.1.3 Luminaire ballasts333310 working days prior to use of material
51SECTION 26 56 00 §2.2.1 Photo Cell333310 working days prior to use of material
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71

Sheet2

Sheet3

Other files for this federal contract opportunity

Other files attached to Repair Storm Damage Building 2379, newest first.
File Type Posted
FA4855-16-B-0018-0002.docx DOCX document
FA4855-16-B-0014-0002.docx DOCX document
CZQZ160015-10-E101-Proposed_Elec.pdf PDF
CZQZ160015-03-A101-Floor_Plan.pdf PDF
Additional_Spec.pdf PDF
CZQZ160015-04-A102-Roof_Plan.pdf PDF
CZQZ160015-05-A201-Elevation_Plan.pdf PDF
SOW-_CZQZ16-0015_Repair_Storm_Damage_B2379.docx DOCX document
Pre-Bid_Response.doc DOC document
Attachment_6_CAFB_Hardware_Specifications_Guideline-_2011.pdf PDF
FA4855-16-B-0018-0001.pdf PDF
Attachment_5_CAFB_Architectural_Compatibility_Guide-2012.pdf PDF
Attachment_7_CAFBI32_201_Fire_Protection_Operations_N_Fire_Prevention_Program.pdf PDF
Attachment_9_CAFB_Electrical_Standards-2016.pdf PDF
Attachment_8_CAFB_Labeling_Standards__2009_Rev1.pptx PPTX presentation
FA4855-16-B-0018_Solicitation.pdf PDF
Attachment_4_SOMS.pdf PDF
Attachment_3_Drawings.pdf PDF
Attachment_2_Specs.pdf PDF
Attachment_1_SOW.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .