DB_SOW_JBSF170263_Replace_Chiller_Pumps_and_Piping_B4196_Rev_1_20180816.pdf
PDF 332 KB Posted
- Attached to
- Replace Chiller Pumps & Piping Bldg 4196
- Solicitation number
- FA301618R0068
About this file
DB SOW JBSF170263 Replace Chiller Pumps and Piping B4196 Rev 1 20180816
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FACILITY SUSTAINMENT, REPAIR, AND MODERNIZATION (FSRM)
DESIGN BUILD STATEMENT OF WORK (DBSOW)
Replace Chiller, Pumps and Piping, B4196
JBSA-FSH, Fort Sam Houston
JBSF170263 / 63637
24 May16 August 2018
Revision: 1
502d CES/CENME
Point of Contact:
Ryan P. Kemble
(210) 221-5300 ryan.p.kemble.civ@mail.mil
PROJECT TITLE: Replace Chiller, Pumps, and Piping, B4196
Project Number: JBSF170263 Work Order NO.: 63637 Page 2 of 25
1. INTRODUCTION
2. PROJECT DESCRIPTION
2.1. General Description
2.1.1. Current Situation
2.1.2. Narrative
3. DESIGN REQUIREMENTS, CODES AND STANDARDS
3.1. Applicable Criteria
3.2. Applicable Codes and Standards
3.3. Technical Specifications
3.4. Design Standards
3.5. Drawings
3.6. Field Information
3.7. Design Details and Standards
3.8. Design Quality
3.9. Design Freedom
3.10. Energy Standard Compliance
3.11. Accessibility Requirements
3.12. Anti-Terrorism Force Protection (ATFP)
3.13. Permits
4. DETAILED WORK REQUIREMENTS
4.1. Work Plan/Design Requirement(s):
4.2. Civil/Site
4.3. Architectural
4.4. Structural
4.5. Mechanical
4.6. Electrical
4.7. Plumbing
4.8. Environmental
5. PERIOD OF PERFORMANCE
6. PHASING REQUIREMENTS
7. GOVERNMENT FURNISHED ITEMS
Project Number: JBSF170263 Work Order NO.: 63637 Page 3 of 25
8. NOTED DB CONTRACTOR REQUIREMENTS
8.1. Required Site survey:
8.2. Schedule of Deliverables and Milestones
8.3. Coordination of Work
8.4. Quality Control Plan
8.5. Toilet Facilities
9. NOTED DB CONTRACTOR SHALL PROVIDE
9.1. Submittals
9.2. Acceptance Phase
10. LIST OF APPENDICES
Project Number: JBSF170263 Work Order NO.: 63637 Page 4 of 25
DESIGN BUILD STATEMENT OF WORK (DBSOW)
(Design Requirements)
1. INTRODUCTION
This document provides the Facility Sustainment, Repair, and Modernization (FSRM) Design Build Statement of Work (DBSOW) for the replacement of the existing Water Cooled chiller and pumps with an appropriately sized air cooled chiller and pumps at JBSA-FSH Building 4196.
The DBSOW development was accomplished by 502d CES/CENME design with input from 502d OPS/Engr and 502d CES/CEPDI .
The project scope is described below and supporting specifications or other documentation are in the Appendices.
The following is a summary of the basic project information:
Project Number: JBSF170263 Project address: Joint Base San Antonio-Fort Sam Houston (JBSA-FSH), 2250 Engineer St., Bldg. 4196 , Fort Sam Houston, TX
2. PROJECT DESCRIPTION
2.1. General Description
The objective of this Statement of Work is to provide for the design, procurement and construction for the removal and replacement of existing Water cooled chiller and cooling tower, and associated pumps and equipment with an air cooled chiller sized to cool the portions building 4196 presently served by the existing water cooled chiller.
See FIGURE 1: VICINITY MAP, for location of the project site. See FIGURE 2: PROJECT SITE MAP, which illustrates the project site location and surrounding area.
Project Number: JBSF170263 Work Order NO.: 63637 Page 5 of 25
FIGURE 1: VICINITY MAP
FIGURE 2: PROJECT SITE MAP
Project Number: JBSF170263 Work Order NO.: 63637 Page 6 of 25
2.1.1. Current Situation
The existing, 250 Ton water cooled chiller, was originally designed and installed to provide cooling for users in B4196 AND B4197. Over the years, the area served by this chiller was reduced to two (2) approximately 40,000 ft2 bays of B4196 containing primarily office spaces.
The piping to other areas has been abandoned and separate chillers provided to the other areas, rendering the chiller oversized. The current chiller failed in 2013 and a temporary 170 Ton chiller was connected and is currently providing cooling for the affected portions of B4196.
2.1.2. Narrative
Design and construction shall comply with the requirements contained within Appendix A of the Design Build Statement of Work (DBSOW). The design and technical criteria contained and cited in this DBSOW along with the technical specifications to be developed from the Unified Facilities Guide Specifications (UFGS) establish minimum standards for design and construction quality. The Designers of Record shall use the Unified Facilities Guide Specifications (UFGS) and the requirements contained in this DBSOW to fully develop the technical specifications and construction drawings. The objective of this solicitation is to remove the existing water-cooled chiller, cooling tower, pumps and piping and obtain a new air-cooled chiller, properly sized to meet the needs of existing cooling loads and tenants served by the cooling loop.
The building and site drawings included in this DBSOW illustrate the conceptual design of the project. Conceptual drawings shall be a guide to the DB Contractor to meet Tenants basic functional requirements.
3. DESIGN REQUIREMENTS, CODES AND STANDARDS
3.1. Applicable Criteria
Applicable design and construction criteria is specifically indicated, but not limited to that mentioned in this Section. Criteria shall be taken from the most current references as of the date of issue of the DBSOW to the contractor for proposal, unless noted otherwise. Referenced codes and standards are minimum acceptable criteria. Administrative, contractual, and procedural features of the contract shall be as described in other sections of the DBSOW. The design requirements located within the DBSOW represent the minimum quality and quantity acceptable for the proposals and project submittals. The standards, documents, and criteria referenced within this DBSOW, although not all attached, are modified to the extent indicated within this section, and shall be the most current version. Each DB Contractor shall be responsible for obtaining any documents not attached as part of this DBSOW but referenced as criteria for the project. Referenced government/military criteria can be obtained from the following website:
http://www.wbdg.org. Requirements of this section may delete, revise, add to or substitute for criteria contained in the referenced documents and this section shall be deemed the controlling authority of any changes to the other referenced documents and criteria. In the event of conflict between referenced standards that are not addressed in the contract, the most stringent requirements apply.
http://www.wbdg.org/
Project Number: JBSF170263 Work Order NO.: 63637 Page 7 of 25
3.2. Applicable Codes and Standards
The design, materials, equipment, and installation shall be in accordance with the current requirements of all building codes, UFCs, standards, AFIs, ETLs, Technical specifications and design manuals, within the requirements of this section, and within the listed specifications for design and renovation of the facility. In addition, JBSA FSH Design Guide as listed in the Appendix B shall be applied to the specific features of design and construction on this project.
40 CFR 82 Protection of Stratospheric Ozone AFI 32-1023 Design and Construction Military Construction Projects AFI 32-1065 Grounding Systems AFMAN 32-7089 Refrigerant Management Program Air Force AFJMAN 32-1080 Electrical Power Supply and Distribution American National Standard Safety Code (ANSI) American Society of Heating, Refrigeration, and Air Conditioning Engineers
(ASHRAE)
American Society of Mechanical Engineers (ASME) American Water Works Association (AWWA) ANSI/ASHRAE/IES Standard 90.1 ASHRAE Standard 90.2 ETL 04-3 (Change 1), Design Criteria for Prevention of Mold in Air Force Facilities Executive Order (EO) 13693 Planning for Federal Sustainability in the Next Decade Fort Sam Houston Installation Design Guide Fort Sam Houston Maintenance and Repair Plan IEEE C2 National Electrical Safety Code IEEE141- Electrical Power Distribution for Industrial Plant Illuminating Engineering Society of North America (IESNA) Institute of Electrical and Electronics Engineers (IEEE) Insulated Cable Engineers Association (ICEA) International Building Code (IBC) 2015 International Mechanical Code (IMC) 2018 International Plumbing Code (IPC) 2015 JBSA Soil Management Plan JBSA-FSH Historical Bldg Maintenance and Repair Plan National Environmental Balancing Bureau (NEBB) Standards National Fire Protection Agency (NFPA) 101- Life Safety Code NFPA 101 – Life safety Code NFPA 70- National Electrical Code NFPA Codes – several others that pertain to this DBSOW.as pertain to this DBSOW Occupational Safety and Health Administration (OSHA) Telecommunications Systems Cabling Standards Title 10 CFR 435, Federal Energy Management Planning and Programs UFC 1-200-02 High Performance and Sustainable Building Requirements UFC 3-201-01 Civil Engineering UFC 3-230-01 Water Storage, Distribution, and Transmission UFC 3-240-01 Wastewater Collection https://www.wbdg.org/ccb/DOD/UFC/ufc_1_200_02.pdf
Project Number: JBSF170263 Work Order NO.: 63637 Page 8 of 25
UFC 3-301-01 Structural Engineering UFC 3-400-02 Design: Engineering Weather Data UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems UFC 3-410-02 Direct Digital Control for HVAC and Other Local Building Systems UFC 3-420-01 Plumbing Systems UFC 3-450-01 Design: Noise and Vibration Control UFC 3-501-01 Electrical Engineering UFC 3-520-01 Interior Electrical Systems UFC 3-530-01 Interior and Exterior Lighting Systems and Controls UFC 3-550-01 Exterior Electrical Power Distribution UFC 3-560-01 Electrical Safety; O&M UFC 3-580-01 Telecom Building Cabling Systems Planning and Design UFC 3-600-01 Fire Protection Engineering for Facilities UFC 4-021-01 Design and O&M: Mass Notification Systems Unified Facilities Guide Specifications (UFGS)
3.3. Technical Specifications
The DB Contractor shall generate a Specification package as part of the Construction Documents that uses the Unified Facilities Guide Specifications (UFGS) appropriately edited for each aspect of the project. The UFGS can be retrieved at: http://www.wbdg.org. Unless noted otherwise, material specifications, equipment efficiencies, equipment listing (i.e., UL, ANSI, NEMA, etc.), testing requirements, execution, and similar requirements shall not be changed unless dictated by more stringent requirements referenced in this DBSOW. The technical specifications shall be developed by the Designers of Record (DOR). Specifications provided in Appendix A shall be included and take precedence over UFGS located in the WBDG, unless otherwise indicated.
Div 01 Specifications provided in Appendix A:
01 14 00 Work Restrictions 01 30 00 Administrative Requirements 01 31 19.00 44 Project Meetings 01 32 16.00 20 Project Schedule 01 33.00 Submittal Procedures 01 33 16.00 10 Design After Award 01 33 29 Sustainability Reporting 01 35 13.10 00 Special Procedures-Surveying 01 35 13.20 00 Special Project Procedures – CAD rev6 01 35 13.30 00 Special Project Procedures – GIS_rev6-tracked 01 35 29 Occupational Safety and Health 01 35 35 Environmental Protection 01 42 00 Sources For Reference Publication 01 45 00.10 20 Contractor Quality Control 01 50 00 Temporary Construction Facilities and Controls 01 54 23.00 Scaffolding Tubular Steel 01 56 00.00 44 Dust Control https://www.wbdg.org/ccb/DOD/UFC/ufc_3_301_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_400_02.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_410_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_420_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_450_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_501_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_520_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_530_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_550_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_560_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_580_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_3_600_01.pdf https://www.wbdg.org/ccb/DOD/UFC/ufc_4_021_01.pdf
Project Number: JBSF170263 Work Order NO.: 63637 Page 9 of 25
01 62 35 Recycled/ Recovered/ Biobased Materials 01 71 23.16 Cutting and Patching 01 72 00.00 44 Alterations to Existing Facilities 01 74 19.00 Construction Waste Management 01 77 00.00 20 Contract Closeout 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data 01 78 36.00 Warranty of Construction 01 86 12.07 40 Reliability Centered Acceptance for Mechanical Systems 01 86 26.07 40 Reliability Centered Acceptance for Electrical Systems 01 91 00.15 Total Building Commissioning
3.4. Design Standards
Equipment, hardware, and materials shall be standard manufactured items unless otherwise specified. Replacement parts shall be standard and readily available through commercial means.
Discontinued products will not be accepted unless approved by the Contracting Officer and 502 CES PM. The design of the civil, architectural, structural, mechanical, electrical and other engineering features of the work shall be accomplished, reviewed and approved by architects, interior designers and engineers who are licensed professionals to practice in their respective professional field in Texas or possession of the United States. The DB Contractor is responsible and liable for the complete design and shall not assume that the provided design criteria and drawings in this solicitation will relieve him from performing any additional design as required to produce a complete set of construction documents for a full and functional system. To ensure proper design quality control, the DB Contractor shall adhere to the requirements outlined under Division 01 specifications 01 33 16.00 10, Design after Award. The Designer of Record (DOR) shall provide the Government a copy of the completed specifications, design calculations, and drawings in accordance with that standard. In addition the DB Contractor shall coordinate and organize a design charette within 7 calendar days of 65% Design NTP ..
3.5. Drawings
Attached concept drawings are included for general information on the design and construction of a building and the development of the site. These drawings may be used as a reference in the design of the system. The design illustrated in the drawings is not intended to be a final or a recommended solution. Drawings are available in electronic format (PDF). See “Appendix C – Project Conceptual Drawings”.
3.6. Field Information
The DB Contractor is responsible for obtaining all information necessary to properly design and install all work. Gathering information during design shall be coordinated through the Contracting Officer. The DB Contractor is responsible for field verifying all information contained on any As-Built drawings provided or acquired. The DB Contractor is responsible for coordination of project work activities with the Contracting Officer that would interrupt or limit the on-going daily activities and/or functions of the facility.
Project Number: JBSF170263 Work Order NO.: 63637 Page 10 of 25
3.6.1. Hazardous Materials Report
An asbestos/hazardous materials report is provided in Appendix F. Abatement is not anticipated to be a part of this scope of work based on the current report.
3.6.2. Geo-Technical Report
A survey and geotechnical report shall be the responsibility of the DB Contractor. Survey will include grading, utility locations, manhole inverts, verification of existing features, etc., and shall tie into the project datum. Approximate boundaries are given in the sketch “Geotechnical Survey Boundaries.pdf” in Appendix C
Temporary Chillers
Existing Temporary chiller will remain in place and connected to system to maintain cooling to the building until the new chiller is ready to be brought into service. It should be outside the boundary of the contractors work site to allow for access by Government Personnel at all times.
Contractor shall coordinate at least 14 calendar days in advance for any relocation of the temporary chiller that is required.. Contractor shall take adequate measures to protect the cooling hoses and power lines extending within the work area and shall notify the COR immediately if any damage occurs or is observed.
Switchover from temporary chiller to new chiller shall be scheduled at least 14 days in advance and will require participation by government operations personnel to operate the temporary chiller.
3.7. Design Details and Standards
The DB Contractor shall be responsible for developing and shall provide a design and construction package which uses and further develops the conceptual drawings within this DBSOW in accordance with current A/E/C CAD standard release 6.0 and in compliance with the JBSA Special Project Procedures, specification sections for CAD, GIS and Surveying standards under 01 35 13.10, 01 35 13.20 and 01 35 13.30, respectively as listed in Division 01 Specifications provided in Appendix A. Additional details shall be created by the DB Contractor as required but shall conform to the requirements of this DBSOW and are subject to approval by 502 Civil Engineer Squadron Engineers and Project Manager.
3.8. Design Quality
The main objectives of this solicitation are to design and construct/erect a turnkey, engineered cooling system, and develop the site as shown on conceptual drawings and to maximize design, and materials quality. Design and materials quality is achieved through the integration of utility systems within the building and on the site, selection of building systems for low-cost maintenance and operation, and an overall balance of aesthetics and functionality within the parameters provided herein.
3.9. Design Freedom
http://www.wbdg.org/ffc/army-coe/technical-reports-tr/erdcitl-tr12-6-r6
Project Number: JBSF170263 Work Order NO.: 63637 Page 11 of 25
Conceptual site plan is included in the DBSOW to illustrate the feasibility of providing the project requirements within given site constraints. Conceptual floor plans are included to illustrate one solution to accommodating the building requirements within the allowable scope as well as establishing spatial relationships. Requirements stated and illustrated in this DBSOW are minimums. Innovative, creative, or cost-saving proposals which meet or exceed these requirements are encouraged and shall be considered during the development of the design / design submittal reviews. The drawings provided establish project floor area requirements and spatial relationships that have been reviewed for user function and preliminary code compliance.
Floor and site plans may change with government approval to enhance design, comply with codes, incorporate alternates, include betterments, or support constructability.
3.10. Energy Standard Compliance
The building shall comply with the provisions of UFC 1-200-02 Change 3 and ASHRAE Standard 90.1 - Energy Standard for Buildings. As a separate part or section of the Design Analysis, demonstrate compliance with ASHRAE 90.1 and UFC 3-400-01 using calculations, vendor literature, equipment catalog sheets, compliance forms, worksheets, and narrative descriptions of the building envelope, HVAC systems, service water heating, electrical power, lighting, and other equipment and systems which contribute to the heat load of the areas served by the existing system. All appliances provided shall be Energy Star rated.
3.11. Accessibility Requirements
The design and construction of Site shall be fully accessible to physically disabled persons and shall conform to the ADA and ABA Accessibility Guidelines for Buildings and Facilities.
3.12. Anti-Terrorism Force Protection (ATFP)
This building is classified as a primary gathering facility for the purpose of force protection requirements (ATFP). Construction therefore shall comply with UFC 4-010-01, Unified Facilities Criteria (UFC), DOD Minimum Anti-terrorism Standards for Building shall be provided for the building and the site. Building must comply with all ATFP standards.
Significant ATFP requirements are listed below.
- Any object within 33 feet of building which has an accessible opening 6 inches or larger in size must be enclosed.
- Provide a cut-off switch inside building to shut down the HVAC system. Note: All existing Air Handlers served by this system have existing cut-off switches inside the building. No modifications to air handlers is required.
3.13. Permits
The DB Contractor shall be responsible for preparing, filing, and paying for any fees required to obtain all necessary permits for the construction of this project.
4. DETAILED WORK REQUIREMENTS
Project Number: JBSF170263 Work Order NO.: 63637 Page 12 of 25
4.1. Work Plan/Design Requirement(s):
4.1.1. The word “remove” or “removed” as used in statement of work, shall be understood to mean DB Contractor shall disconnect and/or demolish item indicated, from its supportive element base and or its mechanical or electrical connection, and dispose of the item off the installation, according to UFGS 01-35-35 Environmental Protection, federal, state, and local requirements. DB Contractor shall protect supportive elements to remain, and provide a replacement to match existing if damaged, at no expense to the government.
4.1.2. The word “provide” or “provided” as used in statement of work, shall be understood to mean, DB Contractor shall supply item indicated and/or install according to manufactures printed instructions, code and specification requirements, and standard industry practices, to be complete and fully functional for its intended purpose, with no ancillary construction or other work required to be performed by the government.
4.1.3. DB Contractor and workers will refer to Appendix F, Hazmat Survey Report, and be familiar with its findings, prior to beginning any work on the facility.
4.1.4. Provide Hydronic pressure tests on all installed/modified portions of water lines to leak test. This includes, but is not limited to, Chilled Water Supply/Return, Water Main, Wastewater lines, and Storm Sewer Lines.
4.1.5. All Materials are required to be approved by 502nd CES Engineering Flight via material submittal, whether stated in “new work” listed item or not.
4.2. Civil/Site
4.2.1. Demolition:
4.2.1.1. Provide equipment, materials and labor to remove existing cooling tower structure and foundation.
4.2.1.2. Provide equipment, materials and labor to remove existing equipment pad in location where new air-cooled Chiller is to be installed.
4.2.1.3. Remove existing sidewalk and asphalt paving in way of trenching for re-routed water and sewer lines mentioned in para 4.7.2.
4.2.1.4. Provide trenching to uncover existing and pathway for new water, sewer and storm water lines as well as other underground utility interference.
4.2.2. New Work:
Project Number: JBSF170263 Work Order NO.: 63637 Page 13 of 25
4.2.2.1. Perform survey of the project site. Site survey shall include topographical survey in one-foot contour intervals and spot elevations; surface features including parking lots, driveways, walks, curb and gutter, pads, walls, signs, hydrants, valves, manholes, cleanouts, inlets, utility poles, guy wires, transformers, sprinklers, backflow devices, landscaping, etc.; and underground utilities. Utility locations shall be determined from base mapping, surface features found in the field, and pot-hole operations. The survey shall encompass all areas associated with the design and construction of all features included within the scope of the project. Topographic map data shall be gathered by field methods, using Global Positioning System (GPS), total station methods, or a combination thereof. The survey shall be generated by a registered professional land surveyor, licensed in the State of Texas and comply with EM 1110-1- 1005, Engineering and Design - Control and Topographic Surveying. Any on-site investigations or field work including topographic survey, must be coordinated with the COR. A digging permit is required for intrusive operations.
4.2.2.2. Perform Geotechnical Investigation. The Geotechnical design requirements for this project include, but are not limited to, construction specifications, all pertinent subsurface investigation, and foundation design drawings including plans, sections, and details. Any on-site investigations or field work including geotechnical investigations, must be coordinated with the COR. A digging permit is required for intrusive operations.
4.2.2.3. Provide new foundation for air cooled chiller and piping support structures.
New foundation shall be dimensioned to provide adequate space for installation and manufacture’s required clearance for maintenance access to all equipment.
Sizing and design shall include space to accommodate Concrete Masonry Unit (CMU) described in para 4.3.2.1 below. New foundation shall be designed to protect existing underground utilities. A foundation design analysis is required for this project. The design of any foundation system shall include, but not be limited to, presentation of allowable bearing capacity, soil parameters, settlement or consolidation, other applicable soil properties (i.e., permeability, shear strength, etc.) and all associated calculations.
4.2.2.4. Provide excavation and grading of area around demolished cooling tower, relocated pipework and new concrete foundation and surrounding earthwork to positively drain away from the building and prevent ponding. The grading shall maintain existing topography were possible, while recognizing standard gradients.
The principles of positive drainage shall be applied to control the conditions that remove rainfall away from facility and functions.
Project Number: JBSF170263 Work Order NO.: 63637 Page 14 of 25
4.2.2.5. Provide sodding in way of existing cooling tower after demolition and grading is complete in accordance with UFGS 32 92 23, Sodding.
4.2.2.6. Contractor will backfill all trenched areas with base material.
4.2.2.7. Provide concrete, asphalt, and soil to match existing material removed.
Finished surface shall match and be flush with adjacent surface.
4.2.2.5.4.2.2.8.Contractor will adhere to the requirements of the JBSA Soil Management
Plan for all soils added or removed from the construction site. A copy is provided in Appendix A
4.3. Architectural
4.3.1. Demolition:
4.3.1.1. Make new penetrations into Mechanical room to accommodate piping to new chillers. If contractor is not re-using existing penetrations for electrical cabling, contractor shall furnish new cable penetrations as well.
4.3.2. New Work:
4.3.2.1. Provide new CMU screen wall enclosure of new air-cooled chillers. CMU Brick should be design set both upright and sideways to allow for adequate airflow and for aesthetic purposes, design should match existing CMU on North end of the building. A sketch “Chiller B4196 Model (1).pdf” and keyed notes to be followed are provided in Appendix C. CMU enclosure shall be painted to match surrounding buildings. Height of screen wall should be not less than 8 feet. Side of enclosure facing the sidewalk shall be comprised of a series of lockable gates to facilitate service access to chiller. Gates should be of similar style to those on existing CMU on North side of building. Open mesh netting of similar style to netting on existing CMU on north side of building shall be put over top of enclosure.
4.3.2.2. Note all surrounding buildings are listed on the state historic registrar by
State Historical Preservation Office (SHPO). Elevation drawings and paint for new enclosure shall be approved by Base Cultural Resource Program Lead prior to construction.
4.3.2.3. Provide lockable m e t a l access gates into new enclosure. Gate shall b e o f s i m i l a r s t y l e t o g a t e s o n e x i s t i n g C M U o n N o r t h s i d e o f b u i l d i n g a n d s h a l l restrict access into enclosure allowing only CE
Project Number: JBSF170263 Work Order NO.: 63637 Page 15 of 25 personnel entry. Gate width shall be not less than 6 feet and height shall be at least 8 feet. Gate shall open towards the street and shall provide at least approximately 180 degrees of swing. Contractor shall coordinate with COR to obtain mechanical room key core or padlock. Provide new penetrations through exterior wall for chiller hookup valves. Seal and refinish unused penetrations from old equipment/utilities in exterior wall.
4.3.2.4. Contractor shall repair and refinish all surfaces and finishes damaged by contractor.
4.4. Structural
Note the requirements of para 4.2.1.1, 4.2.2.3, 4.3.1.1, and 4.3.2.1.
4.5. Mechanical
1) The design and installation shall include, but may not be limited to:
a. Perform detailed cooling load analysis for the two sections of building 4196 served from existing chiller. Determine total cooling load based on peak load of the areas served.
b. HVAC Load Calculations shall be performed using a sophisticated computer software program, such as Trace 700 Load Design Program or equivalent industry standard. Calculations shall include 100 percent of the personnel, ventilation, lighting and equipment loads. Equipment shall be selected based on satisfying the peak sensible, latent and total calculated cooling loads.
Design submissions of the building load calculation computer simulation analysis shall include the complete input data, design parameters, and the following cooling output data (as a minimum):
Systems summary totals and per each section of building served (Airflow
& Capacity Quantities) System Cooling Peak Load Summary Internal Load Building Envelope Composition (U-values, Areas, and ASHRAE 90.1
Analysis) Peak Airflow Loads.
4.5.1. Demolition:
4.5.1.1. Remove and capture all refrigerants in accordance with Section 02 41 00 Demolition and Deconstruction. The Contractor shall comply with all environmental and safety regulations for refrigerant disposal.
Note existing chiller contains refrigerant R-123
Project Number: JBSF170263 Work Order NO.: 63637 Page 16 of 25
a) Notify the Contracting Officer a minimum of 14 calendar days in advance to ensure the appropriate documentation is submitted and approved and the correct refrigerant recovery equipment is utilized. Contractor is to provide required containers that meet the requirements of AFMAN 32-7089 and 40 CFR Part 82.
4.5.1.2. Remove and haul away existing equipment, including one (1) water- cooled chiller, one (1) cooling tower, two (2) circulating chilled water pumps, two (2) condenser water pumps, one (1) air separator, one (1) expansion tank, and all other additional ancillary equipment and piping up to isolation valve shown on concept drawing.
4.5.1.3. Prepare equipment pads to receive new circulating chilled water pumps.
Remove existing mounting studs and install new studs. Ensure a clean and level mounting surface.
4.5.1.4. Patch mechanical floor with suitable concrete material in way of removed equipment foundations and make level with existing floor.
4.5.2. New Work:
4.5.2.1. PProvide one (1) new, air cooled, chiller with a total capacity equal to the determined cooling load. 300 Tons shall be assumed the appropriate size for bidding purposes and confirmed during the design phase. Chiller shall have at least two circuits and/or screw compressor so that unit can match the cooling load.
4.5.2.2. Provide two (2) new circulating chilled water pumps (Primary and secondary), each sized to provide required flow and head pressure to existing loops.
4.5.2.3. Provide piping and valves to connect chiller and pumps to existing loops, retaining temporary connection valves and piping. Provide new air separator, buffer tank of at least 500 gal, and expansion tank sized for existing chilled water loops.
4.5.2.4. A chemical shot feeder, sized for system design, shall be installed and located in the mechanical room.
4.5.2.3.4.5.2.5.Provide new air/dirt eliminator sized for system.
4.5.2.4.4.5.2.6.All installed/modified Penetrations for cables, cable trays, conduits, pipes, tubes, wires, and similar items to accommodate electrical, mechanical, plumbing, and communications systems that pass through a wall, floor, or floor/ceiling
Project Number: JBSF170263 Work Order NO.: 63637 Page 17 of 25 assembly constructed as a fire barrier shall be protected by a firestop system or device.
4.5.2.5.4.5.2.7.System Equipment Testing/Balancing Plan: The Contractor shall submit a
System Equipment Testing and Balancing Plan for the chilled water distribution system with the new chiller to include the Design Review Report, Pre-Field TAB Engineering Report, checklist, and equipment and performance data. The plan shall include all required technical support personnel as specified in Section 23 05 93 Testing, Adjusting and Balancing fFor HVAC. System commissioning shall be in accordance with Section 23 08 00.00 10 Commissioning of HVAC Systems
4.6. Electrical
4.6.1. Demolition:
4.6.1.1. Remove existing electrical wiring to removed equipment back to closest circuit breaker.
4.6.1.2. Remove breakers which will not be re-used.
4.6.1.3. Remove existing Direct Digital Controls (DDC) that cannot be re-used in new installation. Disconnect and retain Direct Digital Controls (DDC) which can be re-used in new installation.
4.6.1.4. Contractor shall remove all control cabling back to control cabinet in mechanical room. Contractor is to coordinate with COR prior to disconnecting control cables from control cabinet.
4.6.1.5. Prepare Electrical panels for new wiring and new circuit breakers for new equipment. Cover any unused openings to panel.
4.6.1.6. Perform survey of existing available electrical service and power study.
a) Electrical analysis shall include existing primary power source characteristics (such as voltage designation, phase, number of conductors, available fault current and grounding classifications); Estimated total connected load (kVA) and the resulting demand load (kVA), breakdown by category (lighting, convenience outlet, mechanical equipment, special operating equipment, user equipment, and miscellaneous load categories); estimated voltage selection, conductors, standards of design, and selected equipment. Design submission of Electrical design analysis shall be in accordance with UFC 3-501-01 Electrical Engineering.
4.6.1.7. Contractor shall remove disconnect switch on exterior of building in way of new CMU wall. Disconnect switch and conduit shall be removed back to nearest junction box and made electrically safe. Repair building exterior finishes and paint to match surrounding.
Project Number: JBSF170263 Work Order NO.: 63637 Page 18 of 25
4.6.2. New Work:
4.6.2.1. Provide new electrical wiring and circuit breakers for new equipment.
4.6.2.2. Reinstall Direct Digital Control (DDC) components retained for re-use in para
4.6.1.3 above.
4.6.2.3. Provide new Direct Digital Controls (DDC) for new chiller plant equipment and chillers to provide control capabilities per section 23 09 23 BACnet spec for JBSA FSH. DDC Controllers shall be fully compatible and communicate with JCI Metasys ADX Server Front End Energy Management Control System, located at B4197.
4.6.2.4. Provide new cabling for all new and re-installed DDC components. Contractor shall coordinate with COR before terminating new control cabling in existing control cabinet in Mechanical room.
4.7. Plumbing
4.7.1. Demolition: Not Applicable
4.7.2. New Work:
4.7.2.1. Relocate/re-route underground piping in way of new equipment pad. To include installation of new piping and thrust blocks from the point where piping first deviates from existing route to the point where it returns to the existing route.
4.7.2.1.1. To include existing water main, existing sewer line and existing storm water drain line shown in sketch “Utilities Systems_B4196” in Appendix C
4.7.2.1.2. Water Main and Sewer Piping to be re-routed around new chiller pad to the street then back to reconnect to existing line. See sketch “Utilities Re-Route.pdf”
4.7.2.4.7.3. Any downspouts falling within the boundary of the new equipment pad shall be routed above grade to a point off the skid pad and re-connected to the existing storm water line. Storm water line connecting downspouts NORTH of skid pad shall be re-routed to existing 30” storm water line as shown in sketch “Utilities Re-Route.pdf”Not Applicable
4.8. Environmental
4.8.1. DB Contractor is responsible and liable to abide by all of JBSA-FSH Environmental Protection Section 01 35 35. This solicitation is not inclusive in listing all requirement or instructions therefore DB Contractor shall refer to all government and JBSA-FSH specifications whether stated within the SOW or not.
Project Number: JBSF170263 Work Order NO.: 63637 Page 19 of 25
4.8.2. All waste chemicals and waste materials must be properly characterized, transported, and disposed of at a permitted facility. Contact the JBSA-Lackland, Hazardous Waste Program Manager at (210) 671-5382 or (210) 671-4844.
4.8.3. Removal of birds or nests needs to be coordinated through 502 CES/CEIEA office, Mr. Tabor 210-295-8339, rustin.t.tabor.civ@mail.mil. Any bats can be removed by CE Pest Management
4.8.4. DB Contractor will make every practical effort to maximize non-hazardous solid waste and Construction Debris (C&D) diversion from landfills or incinerators through reuse, donation, recycling, Qualified Recycling Programs (QRP), composting and mulching, or other waste diversion activities to optimize reduction in both the volume of solid waste disposed and overall cost of non-hazardous solid waste management. A minimum of 54% of debris should be diverted through recycling and/or reuse.
4.8.5. Any compostable materials generated should be composted, scrap materials eligible for recycling must be recycled, and any waste sent for disposal at the landfill must be reported to 502 CES/CEIE.
4.8.6. Any removed concrete should be recycled and diversion/landfill rate must be reported to 502 CES/CEIE.
4.8.7. DB Contractor must record disposal and recycling quantities and will provide report to 502 CES/CEIE Base Environmental.
4.8.8. Ensure Paint, wash water and/or any material/debris generated during this activity is not dumped onto ground or allowed to enter storm drain or pollute storm water runoff.
a. Provide a plan for removal and manifesting C&D, tracking and recycling of scrap metal/concrete. DB Contractor will provide a manifest and fund the disposal of any and all waste. Any questions email Hazardous Waste Program Manager. See para 4.8.8 g below.
b. Any Painting or staining operations must be done with LOW VOC coating materials per requirements of section 01 33 29 Sustainability Reporting
c. HVAC unit being replaced, unit purchased must use a non-Class I/II refrigerant.
d. DB Contractor will minimize nuisance dust emissions.
e. DB Contractor will reclaim refrigerants prior to removing and/or capping off old HVAC equipment or parts. Air Quality Program Manager (PH: 210-295-0936) needs all safety mailto:rustin.t.tabor.civ@mail.mil
Project Number: JBSF170263 Work Order NO.: 63637 Page 20 of 25
Data Sheets including quantities on all new equipment to be installed as part of HVAC prior to project completion.
f. If during excavation or other construction activities any previously unidentified or unanticipated resources are discovered or found, the Contractor shall immediately stop work and notify the Contracting Officer and 502 CES/CEIE per requirements of Section 01 35 35 Environmental Protection.
g. Prior to any work being performed, DB Contractor must submit a list and the associated Safety Data Sheets of the proposed hazardous materials to be used to the JBSA- Lackland Hazardous Materials Office; email Hazardous Material Program Manager, Edward Vogel, 210-652-4668 edward.vogel@us.af.mil.
h. All waste chemicals and materials must be managed in accordance with the JBSA Hazardous Waste Management Plan. Contact Hazardous Waste Program Manager at the Environmental Hotline: (210)671-4844
5. PERIOD OF PERFORMANCE
The period of performance for the Building 4196 Replace Chiller, Pumps, and Piping Project is 281 calendar days. All work must be scheduled to complete within this timeframe. Any modifications or extensions will be requested through 502d Contracting office and coordinated with 502 Civil Engineer Squadron COR, and contractor for review and discussion.
6. PHASING REQUIREMENTS
6.1. Special Coordination for Work Area Access and Hours of Operation (Daily Work Hours) The Contractor shall coordinate with COR to develop a sequencing plan to minimize down time and coordinate weekend work if required. A sequence of events including partial demolition, such as individual chiller demolition, and partial construction, may be required to complete work with minimum down time. Contractor shall prepare and submit for approval a schedule for all phases.
7. GOVERNMENT FURNISHED ITEMS
7.1. As-built drawings of the existing facility.
7.2. Existing Conditions Photographs, these photos do not represent the entire scope of work.
The inclusion of these photos in no way alleviates the DB Contractor from the responsibility to conduct his/her own site visit to verify field conditions.
Project Number: JBSF170263 Work Order NO.: 63637 Page 21 of 25
8. NOTED DB CONTRACTOR REQUIREMENTS
8.1. Required Site survey:
Attend a Pre-Bid site visit to verify measurements, quantities and investigation of existing site conditions.
8.2. Schedule of Deliverables and Milestones
8.2.1. Initial Milestones
KEY SERVICE OR
DELIVERABLE
DUE DATE
Period of Performance Begins Contract Design NTP Note on Schedule
Submit Visitors Clearance Request Provided to CONS 10 calendar days after NTP
Preliminary Project Schedule 14 days after Design NTP Project Design Phase (65% Design Submission)
42 – days after Design NTP
Design Team Review of 65% Phase 14 – days after 65% Submission Project Design Phase (95% Design Submission)
21 – days after 65% Phase Approval
Design Team Review of 95% Phase 14 – days after 95% Submission Submit Environmental Plan according to Spec 01 35 35
Within 50 days of Award
Final Design Review/Charrette (100% Construction Sets)-Issue For Construction (IFC) NTP
7 – days after 95% Phase Completion
Quality Control Plan 7 – days after 95% Phase Completion
Design Team Review of 100% Phase 14 – days after 100% Submission
Construction Begins On receipt of Construction NTP
Construction Phase Complete 120 - Days after Construction
NTP
Acceptance Period 14 – days after Construction Phase Complete
Training for Shop Personnel Complete Prior to end of Acceptance Period
Contractor provides filled out 1354 Prior to end of Acceptance Period
Project Close-Out 30 Days After Acceptance
Project Number: JBSF170263 Work Order NO.: 63637 Page 22 of 25
KEY SERVICE OR
DELIVERABLE
DUE DATE
Contractor provides itemized serial numbers, MFG, Materials list for 502 CEO Inventory
Prior to the start of Completion Inspection.
The DB Contractor shall submit a preliminary schedule showing the design and the construction phases of the project as per this DBSOW and the deliverable schedule.
The days listed above are calendar days, including Saturdays, Sundays, and Federal holidays.
The Government must receive the deliverable by the start of the next business day. If the due date falls on a Saturday, Sunday, or Federal holiday, the Government expects receipt by the start of the next business day. The DB Contractor should assume 14-days for receipt of Government comments for review of major submittals. On-site review conferences or conference calls can be scheduled no sooner than 14-days following receipt of the submittal.
The Government may accept submittals prior to the due date provided they are complete and the DB Contractor has completed a quality control check on all documents. The Government will not accept partially complete submittals early or otherwise.
8.3. Coordination of Work
The Contractor shall coordinate all work and outage times with the CO. All work shall be performed during normal work days and hours, Monday thru Friday 0700 – 1700, excluding Federal holidays and, Headquarters (HQ) Air Education and Training Command (AETC) Family Days. Projected HQ AETC Family Days and Federal holidays are identified under Legal Holidays shown below. All family days are subject to change based on mission requirements.
The following legal holidays are observed by JBSA:
New Year's Day January 1st Martin Luther King, Jr.'s Birthday 3rd Monday in January President’s Day 3rd Monday in February Memorial Day Last Monday in May Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
NOTE: Any of the above holidays falling on a Saturday will be observed on the preceding Friday; holidays falling on a Sunday will be observed on the following Monday.
The following are the projected AETC Family Days for 2018:
Project Number: JBSF170263 Work Order NO.: 63637 Page 23 of 25
- 23 Nov 2018
- 24 Dec 2018
- 31 Dec 2018
8.4. Quality Control Plan
Contractor Quality Control Plan shall be submitted within 7 Calendar Days of 95% design effort.
8.5. Toilet Facilities
Toilet facilities are not available for the DB contractors’ use. DB Contractor shall provide portable toilets.
9. NOTED DB CONTRACTOR SHALL PROVIDE
9.1. Submittals
Submittals shall be submitted and distributed as indicated in DIV 01 Specifications section 01 33 00 and 01 78 00 and as indicated below. Design submittals are identified based on major milestones and is not exclusive of all other submittals as necessary per Contract. The schedule of delivery of design documents to the Contracting Officer is in calendar days. Calendar days for each requirement extends from the date of the Notice to Proceed (NTP) or approval of the previous milestone, except as otherwise noted. All submittals must be submitted to the Contracting Officer for approval.
The Government reserves the right to disapprove design document submittals if the submittals do not meet normal standards for the stage of design being submitted or if review comments are too numerous or of great a significance. In this event, the A/E will be required to resubmit the design documents in the following number of copies at no additional charge to the Government:
a. Reports & Design Analysis – Two(2) electronic (CD) copies and 3 Hard copies
b. Construction Drawings - Two(2) electronic (CD) copies and 3 Hard copies
c. Project Schedules - Two(2) electronic (CD) copies and 3 copies
9.2. Acceptance Phase
After construction completion and prior to final payment, the DB Contractor shall provide, at a minimum, the following.
a. Operation and Maintenance Manuals (Manuals to be provided prior to any equipment testing per Section 01 86 12.07 40)
b. Training
c. List of Standard Equipment and Service Organization of products installed
Project Number: JBSF170263 Work Order NO.: 63637 Page 24 of 25
d. System Equipment Testing/Balancing Report: Submit test results within 14 days of testing. At minimum, test results shall be submitted 5 days before final inspection.
e. As Built CADD documents: Submit four (4) copies of as-built drawings in BOTH digital (minimum AutoCAD 2010) and Adobe (pdf) formant. 4 sets of hard copies shall be submitted on 36” x 48” for review. Submit NLT 14 days after final/inspection.
The list above is not all inclusive. The Schedule of Material Submittals and Appendix A – Division 01 Specifications identifies the required submittals. It is the Contractor’s responsibility to review the references provided and submit the submittals as identified in the specifications.
The PM of 502 CES, will maintain a small team of advisors on behalf of the CO in order to ensure the completeness of each stage of the project and that the scope of work has been met.
Once a project phase is completed and the DB Contractor provides their report for review and approval, the CO will either sign off on the approval for the next phase to begin, or reply to the vendor, in writing, advising what tasks must still be accomplished.
Once all project tasks have been completed, the project will enter the handoff/closure stage.
During this stage of the project, the DB Contractor will provide completed DD-1354 and project task checklist to Contracting Officer and 502 CES PM. The PM of 502 CES will work with 502 CES Real Property. (Don Morgan, and Eduardo Constancio) to complete the approval process.
Once the DD-1354 is approved by 502 CES Real Property, the 502 CES PM will acknowledge acceptance of all project deliverables and that the DB Contractor has met all assigned tasks.
Any discrepancies involving completion of project tasks or disagreement between 502 CES PM and the chosen DB Contractor will be referred to both organizations’ contracting offices for review and discussion.
10. LIST OF APPENDICES
Appendix A – JBSA-Volume II Technical Specifications Appendix B – JBSA-Design Guide Appendix C – Project Conceptual Drawings Appendix D – As-Built Drawings Appendix E – Project Photos Appendix F – HazMat Survey Report Appendix G – 502CES ACM LBP Spec Requirements Appendix H – Request to use Radioactive Materials Appendix I – Application for Installation Access Credential (AIAC) Appendix J – CAD Requirements
Project Number: JBSF170263 Work Order NO.: 63637 Page 25 of 25
Appendix K - Architectural and Engineering Instructions Manual (AEIM) Appendix L - GC HazMat Usage Report (SDS)
| 1. INTRODUCTION |
| 2. PROJECT DESCRIPTION |
| 2.1. General Description |
| 2.1.1. Current Situation |
| 2.1.2. Narrative |
| 3. DESIGN REQUIREMENTS, CODES AND STANDARDS |
| 3.1. Applicable Criteria |
| 3.2. Applicable Codes and Standards |
| 3.3. Technical Specifications |
| 3.4. Design Standards |
| 3.5. Drawings |
| 3.6. Field Information |
| 3.6.1. Hazardous Materials Report |
| 3.6.2. Geo-Technical Report |
| 3.7. Design Details and Standards |
| 3.8. Design Quality |
| 3.9. Design Freedom |
| 3.10. Energy Standard Compliance |
| 3.11. Accessibility Requirements |
| 3.12. Anti-Terrorism Force Protection (ATFP) |
| 3.13. Permits |
| 4. DETAILED WORK REQUIREMENTS |
| 4.1. Work Plan/Design Requirement(s): |
| 4.1.1. The word “remove” or “removed” as used in statement of work, shall be understood to mean DB Contractor shall disconnect and/or demolish item indicated, from its supportive element base and or its mechanical or electrical connection, and dispose... |
| 4.1.2. The word “provide” or “provided” as used in statement of work, shall be understood to mean, DB Contractor shall supply item indicated and/or install according to manufactures printed instructions, code and specification requirements, and standa... |