341 OPLAN 32-7041.pdf

PDF 942 KB Posted

Attached to
Helicopter Maintenance and Support Services Federal contract opportunity
Solicitation number
FA2517-08-R-8001
Issued by
Department of the Air Force Space Command

About this file

Malmstrom AFB MT 341 SW OPLAN 32-7041 Storm Water Pollution Prevention September 2006

View the file

Other files for this federal contract opportunity

Other files attached to Helicopter Maintenance and Support Services, newest first.
File Type Posted
Amendment 0004 to RFP FA2517-08-R-8001.pdf PDF
Amendment 0004 to RFP FA2517-08-R-8001.pdf PDF
Amendment 03 to RFP FA2517-08-R-8001.pdf PDF
Atch 2 - 19 Aug 09 Helo Mx PWS - Amendment 3.pdf PDF
Hand Tools Rev. 1 —
090811 Section A-M —
Questions from Interested Parties 2- Posted 11 Aug 2009.docx DOCX document
Amendment 02 to RFP FA2517-08-R-8001.pdf PDF
090811 Section A-M —
Atch 2 - 3 Aug 09 Helo Mx PWS.pdf PDF
Questions from Interested Parties 1 31 Jul 2009.docx DOCX document
Atch 1 - DD254.pdf PDF
Atch 13 L-4 PP Client Authorization Letter —
Atch 15 L-6 Staffing Matrix.docx DOCX document
Atch 5 - CBA 2006-293 Malmstrom.pdf PDF
Atch 3 - AFE PWS 17 Jun 09.pdf PDF
Atch 9 - Minot - Wage Determination.pdf PDF
Pre-Proposal Conference 090713.ppt PPT presentation
Atch 3 - AFE PWS 17 Jun 09.doc DOC document
341SWI31-214.pdf PDF
090707 WORKLOAD DATA.pdf PDF
090707 Helicopter Maintenance Hand Tools.pdf PDF
090707 DOL-CBA 2008-2354 Minot.pdf PDF
090707 DOL - CBA 2006-293 Malmstrom.pdf PDF
FEW NDI.pdf PDF
Order log.pdf PDF
91 MXG Support Agrmnt.pdf PDF
090706 Access to Technical Libarary.pdf PDF
090504 Industry Day Notification.pdf PDF
DRAFT PWS.docx DOCX document
081103 Bidder's Library Criteria for Access.pdf PDF
RedactedModificationsP00006-010.pdf PDF
1_RedactedModificationsP00001-005.pdf PDF
RedactedModificationsP00047-50.pdf PDF
RedactedModificationsP00019-020.pdf PDF
RedactedModificationsP00018.pdf PDF
RedactedModificationsP00061-63.pdf PDF
1_RedactedModificationsP00035-40.pdf PDF
RedactedModificationsP00021-27.pdf PDF
RedactedModificationsP00055.pdf PDF
RedactedModificationP00076-77.pdf PDF
RedactedModificationsP00028-30.pdf PDF
RedactedModificationsP00064-65.pdf PDF
RedactedModificationsP00068-70.pdf PDF
RedactedModificationsP00078-80.pdf PDF
RedactedModificationsP00041-44.pdf PDF
RedactedModificationsP00081-83.pdf PDF
RedactedModificationsP00084-86.pdf PDF
RedactedReleasableCopyoftheContractSOWApril2006(2)(2).PDF PDF
1_RedactedModificationsP00031-34.pdf PDF
Show all 50

Helicopter Maintenance and Support Services has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

341ST SPACE WING

Malmstrom Air Force Base, Montana

341 SW OPLAN 32-7041

Storm Water Pollution Prevention

September 2006

MEMORANDUM FOR SEE DISTRIBUTION (ANNEX Z)

FROM: 341 CES/CEVC

39 78th St. North Malmstrom AFB MT 59402-7536

SUBJECT: 341 SW Storm Water Pollution Prevention Plan

1. Attached is 341 SW Storm Water Pollution Prevention Plan, September 2006.

2. This plan implements AFI 32-7041 and Montana Pollutant Discharge Elimination System (MPDES) permit MTR000197. This plan is effective upon receipt for developing and managing Malmstrom AFB storm water systems.

3. Unit environmental coordinators and facility managers are responsible for maintaining a working knowledge of the contents of this guide.

4. The OPR for this plan is 341 CES/CEVC, Environmental Flight.

Attachment:

MAFB Storm Water Pollution Prevention Plan

SECURITY INSTRUCTIONS

1. The long title of this guide is 341st Space Wing Storm Water Pollution Prevention Plan. The short title is 341 SW OPLAN 32-7041.

2. This document is unclassified. Any portion may be extracted or reproduced for planning.

3. The OPR for this plan is 341 CES/CEVC. Address any recommended changes in content or distribution requirements to 341CES/CEVC.

RECORD OF CHANGES/RECORD OF REVIEW

RECORD OF CHANGES

CHANGE NUMBER DATE DATE ENTERED POSTED BY

___Replacement____________Sept 06________Sept 06___________KJClavin_

RECORD OF REVIEW

REVIEWED BY DATE REVIEWED REMARKS

UNCLASSIFIED

Storm Water Pollution Prevention Plan iv

SUMMARY

1. PURPOSE: This plan is designed to provide Malmstrom AFB personnel with the following information:

a) Potential sources of pollutants in runoff from industrial and construction activity.

b) Best management practices to eliminate/reduce pollutants.

c) Organizations and individuals tasked in maintaining pollution control equipment or implementing best management practices.

2. CONDITIONS FOR IMPLEMENTATION: This plan is effective upon receipt and will be used in day-to-day operations.

3. OPERATIONS TO BE CONDUCTED: This plan identifies potential sources of runoff pollutants from industrial and construction activities that affect the quality of discharge, identifies best management practices to eliminate/reduce pollutants and tasks those organizations responsible for implementing those practices. In accordance with Part IV C of the General Permit, Discharges to Water Quality Impaired Waterways, MAFB has identified the MT41Q331_013, water class B-3, Missouri River from Rainbow Dam to Morony Dam as receiving surface water that is listed as impaired on the state’s 303(d) list. MAFB has actively sampled and reviewed for any potential impacts to the water body. This review has determined that other than sediment no pollutants of concern are discharged from MAFB to the impaired water body. The best management practices under permit authorization MTR000197 and MTR40008 (Small Municipal Storm Sewer General Permit) collectively control sediment and other pollutants of concerns in MT41Q001_01.

4. COMMAND RELATIONSHIP: All activities that affect the quality and operation of storm water pollution control practices or equipment.

5. OPSEC: Operations security considerations were used in preparing this plan.

6. This is an updated publication and supersedes all previous versions.

Storm Water Pollution Prevention Plan September 2006 v

TABLE OF CONTENTS

Page

Letter of Transmittal i

Security Instructions ii

Record of Changes/Record of Review iii

Plan Summary iv

Table of Contents v

Basic Plan BP-1

Annex A-Description of Potential Pollutant Sources A-1

Annex P-Storm Water Management Controls P-1

Annex R-Site Information and Outfall Descriptions R-1

Appendix 1 – MAFB Storm System Map R-1-1

Appendix 2 – USGS Map R-2-1

Annex U-Comprehensive Site Inspections U-1

Annex W-Storm Water Sampling and Monitoring Program W-1

Appendix 1 – Storm Water Discharge Sampling Matrix W-1-1 Appendix 2 – MAFB Industrial Storm Water Pollution Sources W-1-2

Annex Z – Distribution List Z-1

Storm Water Pollution Prevention Plan

September 2006

341 SW OPLAN 32-7041

BASIC PLAN

REFERENCES:

AFI 32-7041, Water Quality Compliance AFPD 32-70, Environmental Quality EPA 832-R-92-006, Storm Water Management Activities for Industrial Activities—Developing Pollution Prevention Plan & Best Management Practices EPA 832-R-92-005, Storm Water Management for Construction Activities Developing Pollution Prevention Plans and Management Practices

1. PURPOSE: This plan provides guidance, procedures, and actions taken by personnel or organizations that maintain pollution control equipment to reduce or eliminate pollutants entering the storm water system. This plan also implements the requirements of Permit MTR 000197, Authorization to Discharge, under the Montana Pollutant Discharge Elimination System, Section IV.

2. TASKED ORGANIZATIONS: All personnel assigned to organizations that have activities with a potential to discharge pollutants or undesirable substances to the storm water system are tasked to implement the best management practices (BMP) outlined in this plan. These activities include outdoor storage, loading and unloading of dry bulk material or liquids, and outdoor process activities. Specific organizational tasking identified in the list of activities that have the potential to discharge to the storm water system are in Annex A, Description of Potential Pollutant Sources. Compliance with this plan is mandatory.

3. SITUATION: 341st Civil Engineer Squadron Environmental Flight (341 CES/CEV) personnel prepared this storm water pollution prevention plan (SWP3) in accordance with AFI 32-7041, Water Quality Compliance, and state and federal storm water regulations under the Montana Pollutant Discharge Elimination System (MPDES) Phase I and permit MTR 000197. These regulations require identification of all potential sources of pollutants in runoff, inclusion of best management practices, site maps, and other detailed information specified in the MTR 000197 permit and regulation.

4. MISSION: The mission is to eliminate the effects of pollutants on the waters of Montana and to maintain compliance with the Clean Water Act and permit MTR 000197.

In accordance with Part IV C of the General Permit, Discharges to Water Quality Impaired Waterways, MAFB has identified the MT41Q331_013, water class B-3, Missouri River from Rainbow Dam to Morony Dam as a receiving surface water that is listed as impaired on the state’s 303(d) list . MAFB has actively sampled and reviewed for any potential impacts to the water body. This review has determined that the best management practices

BP-1

September 2006 under permit authorization MTR000197 and MTR40008 collectively control any pollutants of concern in MT41Q001_01.

5. EXECUTION:

5.1. Concept of Operations:

5.1.1. A comprehensive and standardized source of information and methods must be available to assist in accomplishing the plan’s mission because many activities at Malmstrom AFB that can affect storm water quality cross organization lines.

5.1.2. The primary source for guidance and reporting of storm water activities at Malmstrom AFB is 341 CES/CEV.

5.1.3. Each organization must be accountable for their activities because there are many activities performed outside of 341 CES that affect the storm water discharges.

5.1.4. Not all organizations or management practices may be implemented or affected by this plan.

5.1.5. This plan will be implemented for all activities identified in this plan.

5.2. Tasked Organizations:

5.2.1. The 341st Space Wing commander has responsibility for Malmstrom AFB storm water discharges, but delegates the authority to carry out the storm water management program to other individuals and organizations; i.e., the Environmental, Safety, and Occupational Health Council, which is chaired by the vice commander.

5.2.2. 341 CES/CEV is responsible for storm water issues. They are the focal point for all the technical aspects of the storm water program including the implementation, maintenance, and revision of the SWP3. It is also responsible for assessing storm water management practices and selecting those that are reasonable and appropriate for the installation. In addition, they must determine which BMPs to implement to reduce storm water contamination.

5.2.3. All squadrons are identified in Annex A.

BP-2

September 2006

6. ADMINISTRATION AND IMPLEMENTATION:

6.1. Administration: 341 CES/CEV will maintain this plan. Squadron flight chiefs and team chiefs will ensure all personnel under their supervision and control are familiar with their duties and responsibilities under this plan.

6.2. Implementation: The elements of implementation of this plan are found in the attached annexes.

7. COMMAND AND SIGNAL: Not applicable.

8. SIGNATORY AND CERTIFICATION REQUIREMENT: “I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the persons who manage the system, or those directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.”

//SIGNED//

SANDRA E FINAN, Colonel, USAF Commander

BP-3

Storm Water Pollution Prevention Plan September 2006

ANNEX A TO 341 SW OPLAN 32-7041

DESCRIPTION OF POTENTIAL POLLUTANT SOURCES

PURPOSE: This annex identifies the organizations with activities that are potential sources of pollution. These activities can be expected to affect the quality of storm water discharges from Malmstrom AFB.

1. STANDARD INDUSTRIAL CLASSIFICATION CODE (SIC) FACILTIES: The primary mission at Malmstrom AFB is national security. To accomplish this mission several activities occur that require an authorization to discharge stormwater associated with industrial activity from the Montana Department of Environmental Quality (MDEQ). These activities are outlined in Table A-1.

TABLE A-1

ACTIVITIES REQUIRING MPDES PERMIT COVERAGE

SIC Description Office

Symbol Affected

Bldgs Activity

4119 Local Passenger, Transportation

341 LRS 850 & 870 Vehicle maintenance

4214 Local Trucking with Storage

341 LRS 1448 Truck maintenance

4522 Helicopter Carrier, Nonscheduled

MXG/MXH

1440, Bay 5 Helicopter maintenance

5171 Petroleum Bulk Storage

LRS/LGRF

41120 & 41121 (Active) 41100, 41102 & 41101 (Inactive)

Storage and distribution of petroleum fuels

2439 Woodworking, not otherwise classified

CES/CEOHV

371 Maintenance and repair work

3449 Misc metal structure

CES/CEOHV

371 Maintenance and repair work

2. LOADING AND UNLOADING OF MATERIALS: Loading and unloading activities occur outdoors on loading docks and at storage and accumulation areas. Spills or leaks during loading and unloading operations could potentially reach the storm drains. For additional information regarding spill control and prevention see MAFB OPlan 32-4.

Specific outdoor activities are listed below.

A-1

Storm Water Pollution Prevention Plan September 2006

TABLE A-2

MISCELLANEOUS ACTIVITIES THAT MAY AFFECT

THE STORM WATER SYSTEM

BLDG # USER / OCCUPANT MATERIAL ACTIVITY / ESTIMATED AMOUNT

1248 POV Car Wash Soap AAFES Car Wash/6-40 gallon barrels 1448 LRS Vehicle

Operations Soap Military Vehicle Wash Rack/1-40 gallon barrel 1480 Aircraft Fuel/De-fuel

Pump house JP-8 Pumping station/ Varies

1535 Hazardous Waste Storage Area

Various Hazardous Materials & Wastes

All materials stored inside TSDF/ Varies

WSA Weapons Storage Area Water Fire Suppressant System (Deluge)

Munitions and POL storage/200,000 gals of water

TABLE A-3

ABOVEGROUND STORAGE TANKS

BLDG # USER/OCCUPANT VOLUME

[Gallons]

CONTENT CONTAINMENT

144 Base Comm Center Generator 480 Diesel Doublewall Steel 152 Water Pump Station 275 Diesel Metal Catch Pan 165 Network Ops Center 200 Diesel DW Steel 219 Missile Trainer 212 Diesel Singlewall Steel 98 Diesel Singlewall Steel 94 Diesel Singlewall Steel 295 Law Enforcement Desk 10 Diesel Doublewall Steel 349 Base Fire Station 300 Diesel Doublewall Steel 407 CE Complex 150 Diesel Doublewall Steel 429 Military Gas Station 75 Diesel Doublewall Steel 430 Military Gas Station 10,000 Diesel Doublewall Steel 10,000 Diesel Doublewall Steel 10,000 Gasoline Doublewall Steel 434 Hazardous Waste Storage 1,000 Contaminated

Fuel Doublewall Steel

1,000 Used Oil Doublewall Steel 450 Aircraft AGE 2,000 JP-8 SCAT 470 Civil Engineer 170 Diesel Doublewall Steel 530 Telephone Switch Center 175 Diesel Doublewall Steel

A-2

Storm Water Pollution Prevention Plan September 2006

TABLE A-3

ABOVEGROUND STORAGE TANKS

BLDG # USER/OCCUPANT VOLUME

[Gallons]

CONTENT CONTAINMENT

685 AAFES Service Station 330 New Oil Metal Catch Basin 660 Used Oil Doublewall Steel 780 Missile Services Facility 300 Diesel Doublewall Steel 870 LRS Vehicle Management 100 New Oil Catch Basin 100 New Oil Catch Basin 100 New Oil Catch Basin 882 660 Used Oil Doublewall Steel 910 Base Water Tower Beacon

Generator 75 Diesel Doublewall Steel

1075 Elkhorn Diner 200 Diesel Doublewall Steel 1082 Base Telephone Switch 25 Diesel Singlewall Steel 500 Diesel Concrete Catch Basin 1246 Skill Development Center 660 Used Oil Doublewall Steel 1320 Commissary 25 Diesel Metal Catch Pan 1408 Airfield Lighting 275 Diesel Metal Catch Pan 1439 Missile Maintenance 100 Diesel Doublewall Steel 1439 Periodic Maintenance Team 745 Used Oil Doublewall Steel 1440 Helicopter & Weather Ops 200 Reclaimed

JP-8

Singlewall Steel

1441 Helicopter Ops 150 Diesel Doublewall Steel 1448 Truck Tractor 660 Used Oil Doublewall Steel 1450 RHS Vehicle Maintenance 660 Used Oil Doublewall Steel 1459 Fire Pump #1 300 Diesel Concrete Catch Basin Fire Pump #2 300 Diesel Concrete Catch Basin 1459 Fire Pump #3 300 Diesel Concrete Catch Basin 1468 RED HORSE 2,000 Diesel SCAT 1470 RED HORSE Vehicle Fuel 1,000 Gasoline SCAT 1482 POL Distribution 500 Diesel Doublewall Steel 1831 WSA 295 Diesel Doublewall Steel 1832 WSA Vehicle Fuel 500 Gasoline SCAT 1839 Munitions Flight Facility 300 Diesel Doublewall Steel 1845 Missile Handling 100 Diesel Doublewall Steel 1879 Receiver Site 2,000 Diesel SCAT 1881 TACAN Generator 110 Diesel Doublewall Steel 1884 South Airfield Lights 2,500 Diesel Concrete Catch Basin 1890 Rivet MILE 50 Diesel Self Contained

A-3

Storm Water Pollution Prevention Plan September 2006

TABLE A-3

ABOVEGROUND STORAGE TANKS

BLDG # USER/OCCUPANT VOLUME

[Gallons]

CONTENT CONTAINMENT

100 Gasoline Self Contained 1996 Sewage Lift Station 200 Diesel Doublewall Steel 2040 Clinic 295 Diesel Doublewall Steel 3080 Fire Pump 300 Diesel Doublewall Steel 13415 Instrument Landing System 370 Diesel Concrete Catch Basin 41100 Bulk POL Storage Tank 1,050,000 Deactivated Cement/Earthen

Berm 41101 Bulk POL Storage Tank 474,600 Deactivated Cement/Earthen

Berm 41102 Bulk POL Storage Tank 1,050,000 Deactivated Cement/Earthen

Berm 41103 M-I Gasoline Fuel Storage 10,000 Gasoline Metal Catch Basin 41120 Bulk POL JP-8 Tank 199,200 JP-8 Cement/Earthen

Berm 41121 Bulk POL JP-8 Tank 199,200 JP-8 Cement/Earthen

Berm 82110 Heat Plant 6,000 Diesel SCAT

A-4

TABLE A-4

UNDERGROUND STORAGE TANKS

BLDG

OWNER/OCCUPANT YEAR

INSTALLED

CAPACITY

(GALLONS)

CONTENTS MAT

USED

295 Law Enforcement Desk 1993 600 Diesel DFRP 430** Military Gas Station 2004 10,000 Diesel DWP 10,000 MoGas/E-85 DWP 500 Command Post 2000 12,000 Diesel DFRP 685 AFFES Gas Station 2003 3-10,000 MoGas DFRP 1440 Missile Maintenance 1993 750 Diesel DFRP 1450 RED HORSE Vehicle

Maintenance (Upg 96)

2,500 Waste DFRP

1464 RED HORSE 1989

(Upg 96)

550 Waste DFRP

1480** Supply Pump Station 1996 4,000 JP-8 DFRP 1831 Weapon Storage Area 1993 6,000 Diesel DFRP 1832 Weapon Storage Area 1980

(Upg 93) 4,000 MoGas FRP

1845 Missile Handling 1993 3,000 Diesel DFRP 1879** Receiver site 1996 2,000 Diesel DWP

82110** Heat Plant 2004 6,000 Diesel DWP

** System is AST with underground piping Upg = Upgraded DWP = Double wall piping DFRP = Double wall fiberglass reinforced plastic FRP = Fiberglass reinforced plastic

3. OUTDOOR STORAGE: Precipitation constantly exposes outdoor storage areas. Any drips, leaks or spills from these areas have the potential to enter the storm water drainage system. In addition, hazardous waste accumulation areas located outside are potential storm water polluters.

A-5

TABLE A-5

OUTDOOR STORAGE THAT POTENTIALLY COULD AFFECT

THE STORM WATER SYSTEM

BLDG

USE / OCCUPANT MATERIAL USE/ESTIMATED

AMOUNT

434 Hazardous Waste

Central Accumulation Point

Waste solvents, oils, paints, sludges, etc.

Temporary storage for hazardous wastes – Up to 55 gallon drum & 1,000 gal each for contaminated fuel and used oil

82110 Central Coal-Fired Heating Plant

Coal Diesel Fuel Lube Oil Antifreeze

Coal car unloading & movement of coal from stock pile to plant/6,000 tons Transport of ash to landfill/700 tons.

3. OUTDOOR PROCESS ACTIVITIES:

3.1. WSA Vehicle Washing (341 SFG): Vehicle washing is allowed at the weapons storage area next to building 1867 in a grassy area. The washing operation has been limited to prevent wash water from entering a field storm drain inlet. The surrounding grassed area takes up rinsate from this operation.

3.2. Street De-icing and Sanding (341 CES/CEOHH): FreezGard Zero (magnesium chloride hexahydrate), has been applied to streets as needed for deicing since 1997. Sand is no longer used for street deicing.

3.3. Defense Reutilization Marketing Office yard (DRMO): DRMO disposes of excess property received from the military services throughout Montana and Idaho. The inventory changes daily and includes many items: from air conditioners to vehicles, clothing to computers, scrap metal and much more. Any item that can degrade with exposure to the elements is stored inside warehouses. Other items such as scrap metal, vehicles and tires are stored outside in specially designated cells with secondary containment or cover when appropriate. This paved yard discharges to a grassy swale that empties into an open channel that discharges off boundary.

3.4. Civil Engineer Compound (341 CES/CEO): This area lies directly east of Bldg 471.

There are numerous fenced lots that are used to store excess materials such as piping, scrap metal and appliances. These materials are stored until there is sufficient quantity to transfer to the DRMO yard. Storm water is discharged through inlets into the storm system.

A-6

Storm Water Pollution Prevention Plan September 2006

4. DUST OR PARTICULATE GENERATING PROCESSES

4.1. Bldg. 82110 - Central Coal-Fired Heating Plant (341 CES/CEOIP): The heat plant stores and transports coal as a fuel source. The coal is stored on a coal pad, which is concrete with storm drain inlet pipes, which transport runoff into a holding pond. The fly ash is stored in a hopper and approximately once a week is hauled out for disposal at a local landfill.

4.2. Construction Activities (341 CES/CEC): During the construction season, any number of construction or demolition projects occur on the installation. All projects that disturb one acre or more are required to obtain storm water construction permits. Project specifications also require erosion control plans. The responsible wing official must sign the notice of intent (NOI) and storm water protection plan (SWPP) before submittal to the Montana Department of Environmental Quality (MDEQ). Proper management of soil erosion and sediment is essential for construction projects that will disturb less than one acre to ensure compliance with the Clean Water Act. The selection of the best soil erosion and sediment controls for the site shall be based upon the nature of the construction and the conditions that exist at the site. The primary goals of soil control for construction projects are: 1) Prevent runoff from offsite areas from flowing across disturbed areas, 2) Slow down the runoff traveling across the site and 3) Remove sediment from onsite runoff before it leaves the site. For a listing of the construction BMPs employed at MAFB, see Annex P or contact the 341st CES Environmental Flight.

4.3. Gravel storage piles (341 CES/CEOHH and 819 RHS): Gravel, clean fill, and old asphalt are stored for re-use on an old abandoned runway in the southeast corner of the base. The area around the site is covered with prairie grass and has less than a 2% slope in any direction.

4.4. Landfarm for fuel contaminated soil (341 CES/CEV): The landfarm is located on the west portion of the old abandoned runway used to store gravel. The land farm is permitted by the MDEQ and has a one-foot earthen berm surrounding the entire site. The site is approximately 100 feet wide and 1,400 feet long.

4.5. Wood pile (341 CES/CEVV): The woodpile is located east of the RV storage area on Perimeter Road. Scrap lumber is stored in this area until sufficient quantity has accumulated to chip. The resulting mulch is then used for compost or trucked to the local landfill to be used for roads within the landfill. The area slopes to the center, therefore no run-off is associated with this activity.

4.6. Construction & Demolition Rubble yard (341 CES/CEO): This is central location for concrete and demolition rubble from various construction activities on the installation.

Most C&D rubble is contracted to be disposed of off-site in a licensed landfill, this area is for MAFB generated waste and for other small demolition projects. Once enough debris is collected, a contractor is procured to crush the debris for reusable material. Access is controlled by a locked gate and signs are posted on rules of use. Storm water flows through the site to grassy swales that discharge to Pow Wow Pond.

A-7

Storm Water Pollution Prevention Plan September 2006

5. ILLICIT CONNECTIONS: An illicit cross-connect survey was completed in 1996 by Thomas, Dean and Hoskins, a contracted consulting engineer. The study identified cross-connects in the following facilities.

Bldg. 122 - Proof Load Test Facility, Bldg. 349 - Crash and Structural Fire Station, Bldg. 870 - Vehicle Maintenance Shop, Bldg. 1192 - Family Services, Bldg. 1305 - Open Mess, Bldg. 1712 - Filter Separator Building and Bldg. 1840 – AS&I Building

Malmstrom has corrected all these cross connections.

6. WASTE DISPOSAL PRACTICES:

6.1. Power Production (341 CES/CEOIG) Bldg. 200: Used hydraulic fluid, sulfuric acid, lube oil, test fluid and antifreeze are stored for disposal.

6.2. Electric Shop (341 CES/CEOIE) Bldg. 407 (Satellite Accumulation Point): Lithium & Ni-Cad batteries and mercury vapor light bulbs are stored for disposal.

6.3. Central Hazardous Waste Accumulation Point (341 CES/CEVV) Bldg. 434: All wastes from satellite accumulation point areas are delivered to this storage yard for characterization.

6.4. AGE (341 MOS/MXOPA) Bldg. 450 (Satellite Accumulation Point): JP-8 fuel filters with benzene are stored for disposal. This facility will be moving to a new facility, Bldg 368 along with the Corrosion Control. Once the move has been completed this plan will be updated to reflect the change.

6.5. Vehicle Maintenance Shops (341 LRS/LGRVM) Bldg. 870 (Satellite Accumulation Point): Used oil and antifreeze are stored for recycling. Waste oil is stored in a 660 gallon AST.

6.6. Missile Maintenance (341 MOS/MXOPP) Bldg.1439 (Satellite Accumulation Point):

Sodium chromate solution with cadmium and battery acid are stored for disposal.

6.7. Helicopter Operations (40 OPG/HS) Bldg. 1440 (Satellite Accumulation Point):

Products used include diesel fuel, solvent, 2 butoxy-ethanol, lube oil, hydraulic fluid, paint thinner, JP-8, and methyl ethyl ketone (MEK). Waste materials are stored in the satellite accumulation point for disposal. Rags contaminated with solvents are the primary waste streams. The largest containers are 55-gallon drums, which are stored on spill pallets.

6.8. Defense Reutilization and Marketing Office (DRMO) Bldg. 1535 (Location of Treatment, Storage And Disposal Facility (TSDF)): All materials for sale and disposal are stored inside facility in specially designed cells.

6.9. Weapon Assembly Building (341 MMXS/MXMW) Bldg. 1840 (Satellite Accumulation Point): Materials stored in the facility include Mono-methyl Hydrazine (MMH) and Nitrogen Tetroxide (N204). In addition, small quantities of paints, oils, greases, adhesives and solvents are stored for daily use. Small quantities of low-level radioactive

A-8

Storm Water Pollution Prevention Plan September 2006 wastes and low-level radioactive mixed wastes are also generated. The small quantities of paints, oils, greases, adhesives, and solvents are stored in a flammable storage locker with a liquid tight 2-inch bottom well for secondary containment. Hazardous wastes derived from missile maintenance operations are stored in approved metal drum containers with locking rings inside an approved flammable locker designated for waste materials only.

6.10. MXS Corrosion Facility (341 MMXS/MXMEC) Bldg. 3065 (Satellite Accumulation Point): Various small amounts of hazardous wastes are stored in a room that has a three-inch high aluminum pan surrounding the containers. This facility will be moving to a new facility, Bldg 368 along with the AGE. Once the move has been completed this plan will be updated to reflect the change.

6.11. Central Coal Fired Heating Plant (341 CES/CEOIP) Bldg. 82110: Fly ash is stored in a hopper and periodically loaded in containers and trucked to the local permitted landfill.

6.12. Helicopter Maintenance 3-Bay Hangar (40 HF) Bldg 1440, Aqueous Film Forming Foam chemical (AFFF). The fire fighting chemical AFFF is made of: Diethylene Glycol Monobutyl Ether 209, Hydrocarbon Surfactants, Fluoro Surfactants, Inorganic Salts and water. AFFF commonly causes high BOD and foaming therefore this discharge is directed to a holding tank that controls final discharge to the sanitary sewer system.

6.13. Missile Transfer Building (341 MMXS/MXMNH) Bldg 1845: An AFFF system is installed with 400 gallons of AFFF (mixed 3% AFFF 97% water = 12,933 gallons liquid). This foam would enter a floor drain leading to a manhole and be pumped to a holding pond.

6.14. Landfills (341 CES/CEVR): There are two closed landfills on Malmstrom AFB.

One is northeast of the Weapons Storage Area (WSA). The Flightline Landfill is located off the northeast end of the runway northeast of perimeter road. Both of these landfills are Resource Conservation Recovery Act (RCRA) Solid Waste Management Units (SWMU). The landfills are neither capped (by RCRA standard) nor lined. The Flightline Landfill (SWMU SW-2) was used primarily for construction debris and rubble.

Corrective actions for SW-2 are complete. The landfill near the WSA (SWMU SW-3) was used for domestic waste and was operated under the applicable state standards during the time it was in operation. RCRA facility investigations were completed at both sites.

No contamination was found that posed a risk to human health or the environment at the Flightline landfill. Long term monitoring of surface water and subsurface water at the landfill northeast of WSA (SW-3) is underway. The U.S. Environmental Protection Agency, Region VIII Montana Office has given authority for these sites to the MDEQ and Malmstrom is required to manage these sites under the RCRA Corrective Actions Program.

A-9

Storm Water Pollution Prevention Plan September 2006

P-1

UNCLASSIFIED

ANNEX P to 341 SW OPLAN 32-7041

STORM WATER MANAGEMENT CONTROLS

1. EMPLOYEE TRAINING (341 CES/CEVC)

1.1. Base-wide storm water pollution prevention training ensures personnel responsible for storm water management are aware of the objectives and components of the storm water pollution prevention plan and how to utilize the plan’s best management practices.

An initial storm water orientation is provided in the Right Start Briefing for all base newcomers. Malmstrom AFB also provides other training venues including annual storm water awareness training classes that incorporate one of several videos on storm water best management practices.

1.2. Shop foremen provide individualized shop training, which includes shop procedures, shop safety, and hazardous waste training. Certain shops also receive hazardous waste satellite accumulation point training. This training program meets the requirements of the Montana General Permit for Storm Water Discharges Associated with Industrial Activity. As additional information becomes available or as objectives and components change, supplemental fact sheets will be distributed to affected organizations and facilities, or to any organization that may request them.

2. GOOD HOUSEKEEPING PROGRAM

2.1. Operations and Maintenance:

2.1.1. Maintain dry, clean floors and ground surfaces by using brooms, shovels, vacuum cleaners, or cleaning machines.

2.1.2. Regularly pickup and dispose of garbage and waste material.

2.1.3. Make sure equipment is working properly (See Preventative Maintenance, Section 3)

2.1.4. Practice waste segregation where applicable.

2.1.5. Routinely inspect for leaks or conditions that could lead to discharges of chemicals or contact of storm water with raw materials, intermediate materials, waste materials, or products (See Preventative Maintenance, Section 3).

2.1.6. Ensure employees understand spill cleanup procedures (See Employee Training, Section 1 and Spill Prevention and Response, MAFB OPlan 32-4).

2.2. Material Storage Practices:

2.2.1. Provide adequate aisle space to facilitate material transfer and easy access for inspection

2.2.2. Store containers, drums and bags away from direct traffic routes to prevent accidental spills (See Spill Prevention and Response, MAFB OPLAN 32-4).

Storm Water Pollution Prevention Plan September 2006

P-2

UNCLASSIFIED

2.2.3. Stack containers according to manufacturer's instructions to avoid improper weight distribution damaging the containers.

2.2.4. Store containers on pallets or secondary containment devices to prevent corrosion of the containers.

2.2.5. Assign the responsibility for hazardous material inventory to a limited number of people who are trained to handle hazardous materials.

2.3. Material Inventory Controls

2.3.1. Malmstrom AFB has implemented a Hazardous Material Pharmacy (PMI/LGRSC), "Hazmart Pharmacy" to validate hazardous material requirements, control and manage hazardous material purchases, regulate distribution of hazardous materials within/between base organizations and collect unused hazardous materials for reissue, alternate use, or recycling.

2.3.2. Material Safety Data Sheets (MSDS) are required for all hazardous materials before they can be issued for use.

2.3.3. A waste minimization program is in place (341 CES/CEVV).

2.3.4. A resource recovery and recycling program is in place (341 CES/CEVV).

3. PREVENTATIVE MAINTENANCE PROGRAM & VISUAL INSPECTIONS

PROGRAM

3.1. The preventative maintenance program identifies equipment, systems, and facility areas that will be inspected. This program provides a schedule for inspections and tests, and addresses appropriate adjustment, cleaning, repair or replacement of devices, equipment, and systems. The preventative maintenance program requires timely inspections and maintenance of storm water management systems to discover any potential problems that could lead to the contamination of storm water. Equipment and systems requiring inspection are identified in the following sections.

3.1.1. Aboveground storage tanks (AST):

3.1.1.1. Fuel levels checked periodically. Fuel consumption records maintained and reviewed by the using organization.

3.1.1.2. Tanks will be inspected regularly upon refilling by Fuels Management.

3.1.1.3. Timely repair of leaking valves, lines, and tanks will be accomplished.

Storm Water Pollution Prevention Plan September 2006

P-3

UNCLASSIFIED

3.1.2. Underground storage tanks (USTs): There are 16 active tank systems on Malmstrom AFB. They include one single walled fiberglass UST, 12 double-walled fiberglass USTs, and four underground pipes with secondary containment that run from ASTs. A soil sentry communications interface program is used for interstitial monitoring in the double walled tanks and piping. The single walled tank is monitored using Arizona Instruments Inc. (AZI) automatic gauging. Timely repair of leaking valves, lines, and tanks is also practiced. All USTs are inspected by a third party contracted inspector for compliance with MDEQ requirements on a three-year cycle.

3.1.3. Sanitary sewer lift station: The lift station requires weekly inspections by the utility shop (341 CES/CEOFD) to ensure the pumps are in good working order and that there are no signs of leaks, overflows or other operational concerns.

3.1.4. Hazardous waste accumulation points: A visual inspection of accumulation areas for signs of leaking or damaged containers is done on a weekly basis, and the site manager must keep all records of inspection.

3.1.5. Hazardous materials storage areas: Items are managed on a first in, first-out basis to avoid expired shelf life. Inspections on a regular basis are required to ensure shelf life have not expired. In the case of expired shelf life, items either are turned in for disposal or are tested for use. Visually inspect storage areas on a regular basis for signs of leaking or damaged containers.

3.1.6. Loading and unloading areas: Individual facility managers are responsible for maintenance and housekeeping of these areas. Proper spill cleanup equipment will be maintained and readily available during loading and unloading operations.

3.1.7. Oil/water separators, catch basins, slide gates, and other structural best management practices.

3.1.7.1. All oil/water separators are the responsibility of the shop that utilizes them (See MAFB Instruction 32-7001).

3.1.7.2. An inspection that meets the requirements of the manufacturer at a minimum shall include a check of liquid levels and operation and maintenance requirements.

3.1.8. All storm water drain inlets, channels and slide gates are inspected by the horizontal section (341 CES/CEOHH) periodically through a reoccurring work order to ensure they are functioning properly.

3.1.9. Street Clean up: The horizontal section (341 CES/CEOHH) performs street sweeping approximately once a week. This practice reduces the total suspended solids (TSS) buildup in the storm water system.

Storm Water Pollution Prevention Plan September 2006

P-4

3.1.10. Construction Best Management Practices (BMPs):

3.1.10.1. Prevent runoff from offsite areas from flowing across disturbed areas using methods such as the following: earth dikes, interceptor dikes and swales, drainage swales and pipe slope drains.

3.1.10.2. Slow down the runoff traveling across the site by: gradient terraces and surface roughing (e.g. permanent seeding, Geo-textiles, sod stabilization and mulching).

3.1.10.3. Remove sediment from onsite runoff before it leaves the site by using such things as: sediment traps, silt fences, gravel filter berm, sediment basins and inlet protection.

3.1.10.4. Keep vehicle tire treads from transferring soil from the job site to base roadways and storm system by using metal exit grates and daily street sweeping.

3.1.10.2. For additional information on construction BMP’s see EPA website at http://cfpub.epa.gov/npdes/stromwater/memuofbmps/con_site.cfm http://cfpub.epa.gov/npdes/stromwater/memuofbmps/con_site.cfm

Storm Water Pollution Prevention Plan September 2006

R-1

ANNEX R TO 341 SW OPLAN 32-7041

SITE INFORMATION, OUTFALL AND DRAINAGE INFORMATION

1. SITE INFORMATION

1.1. Malmstrom AFB is located in north central Montana (latitude 47°31’ N, longitude 111°11’ W) about one mile east of the Great Falls city limits. The base consists of 3,260 acres and has restrictive easements on an additional 441 acres.

1.2. Located in a section of rolling plains about 75 miles east of the Rocky Mountains, Malmstrom AFB lies at an elevation of 3,525 feet above sea level on a plateau that slopes away from the Little Belt Mountains, north towards the Missouri River. The Missouri River flows north and northeast of the base. Stream valleys are interspersed throughout the area, but most of the year these valleys are dry. Any water runoff north of the flight line is directed into pipes, coulees or ditches that ultimately join one principle, but unnamed coulee (locally referred to as the Whitmore Ravine) that discharges into the Missouri River. Any water runoff south of the flight line is directed into coulees or ditches into Pow Wow Pond or exits the installation boundary via sheet flow. The greatest natural physical relief (40 to 50 feet) occurs in the northeast section of the base where runoff has carved a course through the glacial till.

2. SITE MAP

2.1. Appendix 1 to Annex R contains the MAFB storm water system map that delineates the base drainage areas, surface water bodies, discharge points, structural controls, facilities of concern, and the existing storm water system.

3. TOPOGRAPHIC MAP

4.1. Appendix 2 to Annex R contains copies of the USGS maps that delineate Malmstrom AFB. Appendix 2 to Annex R illustrates the surface water bodies, and the topography in and around MAFB.

4. DIRECTION OF FLOW

4.1. Outfalls 1 through 6 all have point discharges upstream in the storm sewer system.

The storm system for these outfalls flow north to the installation boundary then through easements to the unnamed coulee locally referred to as Whitmore Ravine. Figures R-1 and R-2 illustrate the drainage areas and the flow routes respectively.

Storm Water Pollution Prevention Plan

R-2

Figure R-1 – Drainage Areas located on Malmstrom AFB.

4.2. Drainage areas 7, 8 and 9 do not have a point discharge. Hence sampling of these drainages is not required. All the drainages on the installation that have point discharges travel across open farm land and eventually discharge into the Missouri River at a point approximately one mile north.

Storm Water Pollution Prevention Plan

R-3

Figure R-2 – Direction of Flow off Malmstrom AFB.

5. SAMPLE DATA

5.1. During the last permit term, October 2001-September 2006, Malmstrom AFB has sampled the five outfalls along the north boundary of the installation. This historic data is provided in Annex W to the Basic plan. Due to a re-evaluation by the Water Protection Bureau at the state of Montana is has been determined that only those facilities affected under the Administrative Rule of Montana Title 17 Chapter 30 Sub-Chapter 11 Section 1304(29) are required to sample. MAFB conducts one activity that is identified in Part IIIA.2., of the General Permit; Petroleum Storage and Fueling; that is required to conduct sampling pursuant to the General Permit . This activity is located in two separate areas of the installation, see Appendix 2 to Annex W-MAFB Sampling Locations for these locations. For sampled parameters see Annex W.

Storm Water Pollution Prevention Plan September 2006

APPENDIX 1 TO ANNEX R TO 341 SW OPLAN 32-7041

MAFB STORM WATER SYSTEM MAP

R-1-1

Storm Water Pollution Prevention Plan September 2006

APPENDIX 2 TO ANNEX R TO 341 SW OPLAN 32-7041

USGS MAP

R-2-1

Storm Water Pollution Prevention Plan September 2006

U-1

ANNEX U TO 341 SW OPLAN 32-7041

COMPREHENSIVE SITE INSPECTIONS

1. PURPOSE

1.1. The comprehensive site compliance evaluation is an annual inspection conducted by 341st Civil Engineer Squadron Environmental Flight (341 CES/CEVC). Material handling, storage areas, and other potential contributing areas are visually inspected for evidence of actual or potential pollutant discharges to the storm water drainage system.

Structural storm water management devices and pollution prevention equipment are also inspected to confirm their proper working order. The environmental flight documents the results of each inspection in a report signed by an authorized official as specified in the Montana Pollutant Discharge Elimination System (MPDES) permit. When new storm water pollutant sources are identified or existing sources are significantly altered, this plan shall be amended.

1.2. Areas must be inspected to:

1.2.1. Identify any evidence of or potential for pollutants entering the storm water drainage system.

1.2.2. Determine if measures to reduce pollutants loading are adequate and properly implemented.

1.2.3. Determine if additional controls are needed and if existing structural control measures are operating correctly.

1.2.4. Visually determine status of pollution prevention equipment (i.e., spill response equipment).

1.3. A compliance evaluation report will be prepared and retained as part of the storm water pollution prevention plan for at least 5 years after coverage of permit expiration.

The report must be signed in accordance with the regulatory signatory requirements as outlined in the MPDES permit. The report will discuss all items listed in Part IV.A.4 of the general permit, MT00197.

1.4. This report must be submitted to the Montana Department of Environmental Quality (MDEQ) by January 28th of each year.

Storm Water Pollution Prevention Plan September 2006

U-2

STORM WATER INSPECTION CHECKLIST

Facility # / name____________________________________ Date(s)____________ (includes parking lots, storage yard, etc.)

Drainage Area______ Inspectors)__________________________________

Materials stored and estimated average amounts_________________________________

Is there evidence of, or potential for pollutants entering the storm water drainage system?

Yes___No___Explain______________________________________________________

-- Loading or unloading of dry bulk materials or liquids___________________________

-- Outdoor storage_________________________________________________________

-- Dust or particulate generating processes______________________________________

-- Waste disposal practices_________________________________________________

Are measures to reduce pollutant runoff properly implemented (secondary containment, housekeeping, preventative maintenance, etc.)?__________________________________

Assessment of risk (high / med / low) Explain?__________________________________

Inspection of pollution prevention equipment. Yes/ No

Observations / recommendations_____________________________________________

Sediment and erosion prevention_____________________________________________

Other comments or observations:

Signature______________________

Storm Water Pollution Prevention Plan September 2006

APPENDIX 2 TO ANNEX W TO 341 SW OPLAN 32-7041

MAFB Industrial Storm Water Potential Pollution Sources

W-2-1

Storm Water Pollution Prevention Plan September 2006

W-1

ANNEX W TO 341 SW OPLAN 32-7041

STORM WATER SAMPLING AND MONITORING PROGRAM

341st Medical Operations Squadron Bio-Environmental Engineering (341 MDOS/SGOAB) performs all storm water sampling at Malmstrom AFB. For a complete standard operating procedure for sampling see, SGOAB OI 48-119-2, 06 Feb 2002 Storm Water Sampling and Monitoring.

1. PARAMETERS RECORDED: The following parameters are recorded for all storm water sampling discharges associated with industrial activity:

1.1. The exact place, date, time sample was taken and duration (in hours) of the storm event(s) sampled.

1.2. Rainfall measurements or estimates (in inches) of the storm event which generated the sampled runoff.

1.3. Names of individuals who performed the sampling or measurements.

1.4. Analytical laboratory test result data and reports for storm water samples and/or records that minimally indicate date(s) analyses were performed and the time analyses were initiated.

1.4.1. The initials or name of individuals who performed the analyses.

1.4.2. References and written procedures, when applicable, for the analytical techniques or methods used.

1.4.3. The results of such analyses, including the bench sheets, instrument readouts, computer disks or tapes, etc., used to determine the results.

2. MONITORING FREQUENCY

2.1. MAFB is required to sample storm water runoff semi-annually (two times per year).

If possible, samples will not be taken from back-to-back storms. Sampling data will be obtained by collecting a grab sample. This sample will be taken in the first 30-minutes of the discharge. If this is not practicable a sample can be taken during the first hour of the discharge. An explanation for the deviation must accompany the Department Discharge Monitoring Report.

Storm Water Pollution Prevention Plan

W-2

3. MONITORED PARAMETERS

3.1. Montana multi-sector general permit MTR000197 Part III.A.2.a., requires that the parameters reported will include:

3.1.1. Oil and grease (EPA Method 1664)(mg/L)

3.1.2. Chemical oxygen demand (COD) (mg/L)

3.1.3. Total suspended solids (TSS) (mg/L)

3.1.4. Estimated flow rate (gpm)

4. SAMPLING LOCATIONS

4.1. The following sites are required to be sampled in accordance with the General Permit.

4.1.1. SW-5171(a) is located at the following coordinates:

Lat 47 ° 30’ 18.04” N Long 111° 11’ 45.34”

4.1.2.. SW-5171(b) is located at the following coordinates:

Lat 47 ° 31’ 0.378” N Long 111 ° 10’ 37.27”

4.2. The following sites have been identified as possible sampling locations if required by the Montana Water Protection Bureau.

4.2.1. SW-4214

4.2.2. SW-4522

4.2.3. SW-4119

4.2.4. SW-2439/3449

The sampling locations have been identified on the map located at Annex W Appendix 2- Sampling Locations.

5. SAMPLING PROCEDURES

5.1. Obtain grab samples of runoff during the first 30 minutes of runoff, if possible.

Samples will be taken within the first hour of runoff, if obtaining a sample in the first 30 minutes is not possible. One sample per drainage is required. Samples and measurements taken for the purpose of monitoring shall be conducted according to test procedures approved under 40 CFR Part 136.

5.2. Reporting Requirements

5.2.1. Sample results must be submitted for each six-month reporting period to the Montana Water Quality Bureau on discharge monitoring report form(s). They must be

Storm Water Pollution Prevention Plan September 2006

W-3 received no later than the 28th day of July for the first reporting period and the 28th day of January for the second period. Signed copies of monitoring reports and all other reports required herein shall be submitted to the department address below:

Montana Department of Environmental Quality Water Quality Bureau Storm Water Program

P.O. BOX 200901

Helena, MT 59620-0901

(406) 444-3080

6. RECORD KEEPING REQUIREMENTS

6.1. Records of monitoring information, copies of all reports and inspections required by the storm water permit, and all records of all data used to complete the general permit application required by this permit shall be retained for a minimum of 5 years.

Malmstrom AFB OPLAN 32-7041

Storm Water Pollution Prevention Plan September 2006

W-1-1

APPENDIX 1 TO ANNEX W TO 341 SW OPLAN 32-7041

STORM WATER DISCHARGE SAMPLING MATRIX

TABLE W-1-1

STORM WATER DISCHARGE ANAYLITICAL RESULTS

Date Location Oil & Grease

BOD

mg/L

COD

mg/L

TSS

mg/L

TKN

mg/L

Phos mg/L pH

7/8/94 SW1 N 17 78 459 4.6 0.18 7.7

SW2 N 17 74 164 2.4 0.29 7.6

SW3 N 17 48 1730 5.3 0.18 7.7

SW4 N 3 <1 8 0.7 0.33 7.4

SW5 N 5 21 80 1.2 0.16 7.4

No Glycols

Date Location Oil & Grease

BOD

mg/L

COD

mg/L

TSS

mg/L

TKN

mg/L

Phos mg/L pH

25/5/95 SW1 N <9 29 10 1.7 0.18 8.1

SW2 N <8 18 12 1.1 0.18 7.8

SW3 N <8 9 12 0.3 0.12 7.9

SW4 N <6 11 13 1.8 0.52 7.1

SW5 N <7 15 14 0.7 0.10 7.7

BOD

mg/L

COD

mg/L

TSS

mg/L

TKN

mg/L

Phos mg/L pH

18/7/96 SW1 N 24.0 100 518 4.20 0.60 7.48

SW2 N 10.0 110 778 3.27 0.85 7.71

SW3 N 5.0 20 1125 1.27 0.50 7.85

SW4 N 6.0 65 34 .962 0.18 7.52

SW5 N 4.0 10 11 1.37 0.06 8.02

BOD

mg/L

COD

mg/L

TSS

mg/L

TKN

mg/L

Phos mg/L pH

25/8/97 SW1 N 7 32 159 2.14 0.22 8.17

SW2 N 4 30.0 59 <1.16 0.10 8.15

SW3 N <3 30.0 16 <0.96 0.05 8.09

SW4 N <3 8.00 5 <0.92 0..23 7.27

SW5 N <3 10.0 9 <1.00 0.05 8.15

Storm Water Pollution Prevention Plan

W-1-2

TABLE W-1-1

STORM WATER DISCHARGE ANAYLITICAL RESULTS

Date Location Oil & Grease

BOD

mg/L

COD

mg/L

TSS

mg/L

TKN

mg/L

Phos mg/L pH

1/7/98 SW1 N 68 90.0 71 1.60 0.320 7.46

SW2 N 52 70 390 1.60 0.590 7.49

SW3 N 12 30 13 1.10 0.090 7.89

SW4 N 9 <5 9 0.42 0.090 7.05

SW5 N 10 5 19 0.80 0.050 8.12

Glycol testing not required

Storm Water Pollution Prevention Plan

W-1-3

TABLE W-1-2

RECENT STORM WATER SAMPLING DATA

Out Fall 1 06/19/2000 05/21/2002 08/04/2002 05/25/2003 09/16/2003 05/18/2004 11/03/2004 TSS [mg/L] 52 1080 119 144 167 43 292 COD [mg/L] 90 97 120 31 24 30 44 Flow [gpm] 227 30,380 6,000 3,756 2,041 22,561

Out Fall 2

TSS [mg/L] 306 682 85 74 49 180 COD [mg/L] 25 92 172 39 18 22 41 Flow [gpm] 390 2,886 1,000 390 218 2,298

Out Fall 3

TSS [mg/L] 133 1090 108 112 37 53 COD [mg/L] 50 81 168 11 7 67 36 Flow [gpm] 4,047 13,016 3,900 10,812 24,859 16,348

Out Fall 4

TSS [mg/L] 15 92 955 No data 290 COD [mg/L] 38 21 22 17 12 Flow [gpm] 12 0 10 1,505 0 21,377 2,332

Out Fall 5

TSS [mg/L] 24 692 1380 35 COD [mg/L] 15 13 25 29 Flow [gpm] 57 0 55 18,107 0 3,664 0

Storm Water Pollution Prevention Plan September 2006

ANNEX Z TO 341 SW OPLAN 32-7041

DISTRIBUTION LIST:

This annex is meant for all units on Malmstrom AFB. It is the responsibility of each unit to ensure that all agencies under their authority receive and adhere to this plan. In order to conserve paper an electronic version of this plan is available on the Malmstrom web page under Wing Staff Agencies/ XP Wing Plans & Programs and can be referenced by subordinates instead of printing another hard copy. It is highly encouraged to use the electronic copy. Each Unit/Office Symbol is assigned one copy each.

341 SW/CC DRMO (Defense Reutilization Marketing Office) 341 SW/XP USAF CAP LIAISON - Det 8

341 SW/JA 819 RHS

341 SW/SE Corps of Engineers (CENPS) 341 SW/HC Commissary (DECA) 341 SW/PA AAFES (BX) Army Air Force Exchange Services

341 CPTS/CC 40 HF/CC

341 MSG/CC 341 MDG/CC

341 MDOS/CC 341 MDOS/CC

341 LRS/CC 341 MDSS/CC

341 CONS/CC 341 SFG/CC

341 SVS/CC 341 SFS/CC

341 CES/CC 341 SSPTS/CC

341 MSS/CC 341 MSFS/CC

341 MXG/CC 741 MSFS/CC

341 OG/CC AFOSI DET 806

10 MS/CC ADC (Air Defense Council) 12 MS/CC ARC (American Red Cross) 490 MS/CC DSS (Defense Security Service)

564 MS/CC

341 OSS/CC

Z-1

001_Cover Pg.doc
002_MEMORANDUM FOR SEE DISTRIBUTION.doc
003_Security_let.doc
004_Recrd of Change.doc
005_Summary.doc
341 SW OPLAN 32-7041
1. PURPOSE: This plan is designed to provide Malmstrom AFB personnel with the following information:
a) Potential sources of pollutants in runoff from industrial and construction activity.
b) Best management practices to eliminate/reduce pollutants.