CN-370000-HW555-DC063E.pdf

PDF 915 KB Posted

Attached to
Master Agreement FL|HW555|3626b1bfe23ad9cb6d0c11811d472cb2
Contract number
HW555
Issued by
Florida

About this file

This Task Assignment Notification Form (HW555 DC063E) is issued by the Florida Department of Environmental Protection (FDEP) to authorize GHD Services, Inc. to perform soil vapor extraction (SVE) well installation and underground piping work at the Dixie Cleaners site (ERIC_4590) located at 5711 Bowden Road, Jacksonville, Duval County, Florida. The document serves as an indefinite delivery task assignment under the broader HW555 state contract, with Kevin Kane designated as the FDEP Contract Manager and Brian Moore as the Contractor Representative. The task is structured in the Interim Source Removal (ISR) phase and operates under a fixed-price compensation model with no cost reimbursement or retainage provisions.

The scope of work comprises two subtasks: Subtask 1 involves project management calculated at 12.5 percent of direct labor costs, and Subtask 2 encompasses installation of three SVE wells to depths of 5.5 feet below land surface using hand auger drilling methods, followed by underground and exterior piping installation per the approved ISRP drawings. The total fixed-price task assignment value is $13,421.58, consisting of $1,015.27 attributed to project management and $12,406.31 for well and piping installation. The final deliverable—the SVE Piping Installation Summary including field documentation and as-built drawings—is due August 20, 2021, with task completion scheduled for December 3, 2021. Invoice authorization requires FDEP approval of all deliverables, with payment due upon completion of Subtasks 1 and 2. Cost estimates include direct labor ($3,064.68), overhead and administrative expenses ($4,102.20), fringe benefits ($781.49), travel ($907.00), subcontractor services for drum disposal ($418.00), laboratory analysis ($198.00), field equipment and supplies ($2,761.23), and a completion fee ($816.74).

View the file

Other files

File Type Posted
CN-370000-HW552-TDC007A.pdf PDF
CN-370000-HW555-A10.pdf PDF
CN-370000-HW555-A5.pdf PDF
CN-370000-HW555-CO1.pdf PDF
CN-370000-HW555-DC001A.pdf PDF
CN-370000-HW555-DC001H.pdf PDF
CN-370000-HW555-DC001I.pdf PDF
CN-370000-HW555-DC004F.pdf PDF
CN-370000-HW555-DC004K.pdf PDF
CN-370000-HW555-DC006H.pdf PDF
CN-370000-HW555-DC006L.pdf PDF
CN-370000-HW555-DC007F.pdf PDF
CN-370000-HW555-DC007H.pdf PDF
CN-370000-HW555-DC008E.pdf PDF
CN-370000-HW555-DC010D.pdf PDF
CN-370000-HW555-DC012H.pdf PDF
CN-370000-HW555-DC013H.pdf PDF
CN-370000-HW555-DC019G.pdf PDF
CN-370000-HW555-DC019L.pdf PDF
CN-370000-HW555-DC01ACO6.pdf PDF
CN-370000-HW555-DC01ACO8.pdf PDF
CN-370000-HW555-DC01J.pdf PDF
CN-370000-HW555-DC020J.pdf PDF
CN-370000-HW555-DC021i.pdf PDF
CN-370000-HW555-DC024I.pdf PDF
CN-370000-HW555-DC02C.pdf PDF
CN-370000-HW555-DC02D.pdf PDF
CN-370000-HW555-DC02E.pdf PDF
CN-370000-HW555-DC02HCO4.pdf PDF
CN-370000-HW555-DC02HCO6.pdf PDF
CN-370000-HW555-DC02I.pdf PDF
CN-370000-HW555-DC02K.pdf PDF
CN-370000-HW555-DC02M.pdf PDF
CN-370000-HW555-DC030K.pdf PDF
CN-370000-HW555-DC031K.pdf PDF
CN-370000-HW555-DC032G.pdf PDF
CN-370000-HW555-DC033G.pdf PDF
CN-370000-HW555-DC034O.pdf PDF
CN-370000-HW555-DC034Q.pdf PDF
CN-370000-HW555-DC035F.pdf PDF
CN-370000-HW555-DC035I.pdf PDF
CN-370000-HW555-DC035J.pdf PDF
CN-370000-HW555-DC038B.pdf PDF
CN-370000-HW555-DC039E.pdf PDF
CN-370000-HW555-DC03B.pdf PDF
CN-370000-HW555-DC03CCO1.pdf PDF
CN-370000-HW555-DC03D.pdf PDF
CN-370000-HW555-DC03J.pdf PDF
CN-370000-HW555-DC03J.pdf.crdownload CRDOWNLOAD file
CN-370000-HW555-DC040C.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW555

D000 N/ADC063E

GHD Services, Inc.

Brian Moore

(850) 245-8971Kevin Kane

ERIC_4590

Dixie Cleaners

5711 Bowden Rd, Jacksonville, Duval County

ISR

This Task Assignment authorizes GHD Services, Inc. to install underground piping associated with an SVE system in accordance with the June 2021 scope of work and cost proposal.

SVE Piping Installation Summary

08/20/2021

12/03/2021

$ 13,421.58 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Kevin Kane Digitally signed by Kevin Kane Date: 2021.07.08 13:25:04 -04'00'

Kevin Kane Digitally signed by Kevin Kane Date: 2021.07.08 13:25:25 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.07.08 14:34:42 -04'00'

Brian Moore Digitally signed by Brian Moore Date: 2021.07.08 22:09:07 -04'00'

$ 13,421.58

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

SVE Piping Installation Summary 08/20/2021

Upon delivery and FDEP approval of the SVE Piping Installation Summary (including field documentation of well installation and As-Built Drawings of the SVE piping) - Subtasks 1 and 2

$ 13,421.58

$ 13,421.58

HW555

DC063E

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Interim Secretary

TO: HW555 Contract File Dixie Cleaners

ERIC_4590

Jacksonville, Duval County

FROM: Kevin Kane, Contract Manager

DATE: July 7, 2021

SUBJECT: Task Assignment Summary

HW555 DC063E

ISR

This Task Assignment authorizes GHD Services, Inc. to install underground piping associated with the operation of a soil vapor extraction system in accordance with the June 2021 scope of work and cost proposal. Specific subtasks are detailed below:

Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.

Subtask 2: Well Installation and Underground Piping GHD will install 3 additional SVE wells in accordance with the approved ISRP using a hand auger. Following well installation, the SVE wells will be piped (below ground) to the rear of the building as shown in figures from the approved ISRP. The wells will be plumbed to the exterior of the building and attached to the exterior of the building and then capped for future use with the SVE system. Upon completion of installation, GHD will prepare an SVE Piping Installation Summary, which will include field documentation of well installation activities and As-Built Drawings of the SVE piping.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is August 20, 2021, and the completion date for the task assignment is December 3, 2021.

The final cost total for Task Assignment DC063E is $13,421.58.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 07/07/21

Task #: DC063E SubTask 1 Project Management SubTask 6

Site: Dixie Cleaners SubTask 2 SVE Well and underground piping SubTask 7

Activity/Phase: ISR SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$69.71 Project Manager BM 4.89 4.885 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$69.71 Sr. Professional Engineer BM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$40.00 Professional Engineer/Geologist ES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $42.64 Professional Engineer/Geologist GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.00 Professional Engineer/Geologist KC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.72 Staff Engineer/Scientist BG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.91 Project Manager/Engineer SC 12.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.73 Staff Engineer/Scientist VH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$22.00 Senior Technician DC 38.00 38.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 38.00 38.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.08 Junior Technician SC 18.00 18.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician PM 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.14 Staff Assistant SS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 117.89 4.885 113.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $3,064.68 $340.52 $2,724.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 113.00% $3,463.09 $384.79 $3,078.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $858.11 $95.35 $762.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $781.49 $86.83 $694.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $8,167.37 $907.49 $7,259.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $153.24 $17.03 $136.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

REV: 02/03 CEF GHD Services Inc. Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 07/07/21

Task #: DC063E SubTask 1 Project Management SubTask 6

Site: Dixie Cleaners SubTask 2 SVE Well and underground piping SubTask 7

Activity/Phase: ISR SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $291.00 $291.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $616.00 $616.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $907.00 $907.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $380.00 $380.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $380.00 $380.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $38.00 $38.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $418.00 $418.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $135.00 $135.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $63.00 $63.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $198.00 $198.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $97.50 $97.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $2,663.73 $2,663.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,761.23 $2,761.23 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $12,604.84 $924.52 $11,680.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $816.74 $90.75 $725.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $13,421.58 $1,015.27 $12,406.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GHD Services Inc. Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2

SITE : Dixie Cleaners

PROJECT NUMBER: 11152397

FDEP NO: ERIC_4590

SUBTASK: SVE Well and underground piping

DATE: 7/7/2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer BM As-Built Drawings (letter submittal) 4

Construction/Superintendent SC Mob/demob (1 trip to site) 4 Construction/Superintendent SC Material takeoffs, utility locate 2 Construction/Superintendent SC Project Kickoff & supervision 6

Senior Technician DC Mob/Demob 6 Senior Technician DC Install SVE Wells 4 Senior Technician DC Install interior SVE piping (trenching) 18 Senior Technician DC Exterior piping for SVE wells 10

Junior Technician JM Mob/Demob 6 Junior Technician JM Install SVE Wells 4 Junior Technician JM Install interior SVE piping (trenching) 18 Junior Technician JM Exterior piping for SVE wells 10

Junior Technician SC Mob/Demob (2 days) 2 Junior Technician SC Oversee interior SVE piping installation (as-built) 16

CADD Design PM Update As-Built Drawing 3

TOTAL LABOR 113

TRAVEL TYPE RATE UNIT USEAGE Miles Free techs for piping Truck $97.00 day 3 $291.00

TOTAL VEHICLE $291.00

PER DIEM TYPE RATE UNIT USEAGE Miles Free

2 techs Hotel $100.00 person/day 4 $400.00 2 techs Per diem $36.00 person/day 6 $216.00

TOTAL VEHICLE $616.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

Services Procurement

NAME PURPOSE COST UNIT USEAGE

Gulf Coast IDW Drum (soil) $95.00 drum 4 $380.00

TOTAL SUBS $380.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

Volatiles (IDW characterization) 8260 $135.00 1 $135.00 shipping (small cooler) $63.00 1 $63.00

TOTAL LAB $198.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Expendables $32.50 Day 3 $97.50 Sub-Total $97.50

SkidSteer (GHD owned) $175.00 day 2 $350.00 SVE Piping (2" with fittings) $1,227.59 each 1 $1,227.59 60lb bag sackcrete $2.89 each 56 $161.84 Concrete Saw $50.00 day 2 $100.00 Generator $66.00 day 3 $198.00 Durms (PPE and soil) $58.20 drum 4 $232.80 Construction Supplies $63.05 day 3 $189.15 hand auguer $8.25 day 1 $8.25 Well Screen (5 feet, 2-inch, 0.010-slot) $10.65 each 3 $31.95 Well Point (2-inch) $4.25 each 3 $12.75 compactor $75.70 day 2 $151.40

Sub-Total $2,663.73

TOTAL EQUIPMENT $2,761.23

TA_063E.xlsx\sub 2 Page 1 7/7/202111:11 AM

COST PROPOSAL FOR TASK DC063E

<Dixie Cleaners, ERIC_4590>

< SVE well and underground piping installation>

1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >

GHD Services Inc. (GHD) prepared an Interim Source Removal Plan (ISRP) that was recently approved by the FDEP. Task DC063E includes labor and expenses for the installation of SVE wells and underground piping in accordance with the approved ISRP. The underground piping is being tasked expeditiously in order to accommodate the property owner’s plans to lease the space.

Subtask 1: Project Management Subtask 1 includes all activities associated with management of the SVE well installation, and installation of associated underground piping.

Subtask 2: Well Installation and underground piping GHD will install 3 additional SVE wells in accordance with the approved ISRP using a hand auger.

The SVE wells will be to depths of 5.5 ft bls and will be screened from 0.5-5.5 ft bls. Following well installation, the SVE wells will be piped (below ground) to the rear of the building as shown in the ISRP drawings. The wells will be plumbed to the exterior of the building and attached to the exterior of the building. The wells will be capped for future use with the SVE system.

Upon completion of the field activities, GHD will provide field documentation of the well installation and piping activities as well as As-Built Drawings of the SVE piping.

Deliverables:

Deliverable Deliverable Due Date

Field Documentation and As-Built Drawings 8/20/2021

Gulf Coast Vacuum Truck Services 1744 Williams Ditch Rd

Cantonment, FL 32533 US

+1 8504500058 accounting@gcvts.net

Estimate

ADDRESS

GHD

ESTIMATE 1040

DATE 04/15/2021

DATE SERVICE DESCRIPTION QTY RATE AMOUNT

Drum Disposal Disposal of of 1 drum of contaminated water.

1 95.00 95.00

Island Cleaners - Sanibel TOTAL $95.00

Accepted By

Accepted Date

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

April 15, 2021

Re: Non-Hazardous Drum Disposal Quote – South and Central Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in south and central

Florida will be $100.00 per drum, total, for both transportation and disposal.

Pricing for the Florida Keys will be quoted separately on a case-by-case basis.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/28/21 Fri 7/9/21

2 Subtask 1: Project Management

30 days Mon 7/12/21 Fri 8/20/21

3 Subtask 2: SVE Well and Piping Installation

30 days Mon 7/12/21 Fri 8/20/21

4 Field Work Preparation 2 wks Mon 7/12/21 Fri 7/23/21

5 SVE Well Installation 1 day Mon 7/26/21 Mon 7/26/21

6 SVE Piping Installation 2 days Tue 7/27/21 Wed 7/28/21

7 AS‐Built Drawings 3 wks Mon 8/2/21 Fri 8/20/21

6/20 6/27 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC063E at the Dixie Cleaners site located in Jacksonville, Duval County

Project: TA_063E Date: Mon 6/28/21

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/28/21 Fri 7/9/21

2 Subtask 1: Project Management

30 days Mon 7/12/21 Fri 8/20/21

3 Subtask 2: SVE Well and Piping Installation

30 days Mon 7/12/21 Fri 8/20/21

4 Field Work Preparation 2 wks Mon 7/12/21 Fri 7/23/21

5 SVE Well Installation 1 day Mon 7/26/21 Mon 7/26/21

6 SVE Piping Installation 2 days Tue 7/27/21 Wed 7/28/21

7 AS‐Built Drawings 3 wks Mon 8/2/21 Fri 8/20/21

7/4 7/11

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC063E at the Dixie Cleaners site located in Jacksonville, Duval County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/28/21 Fri 7/9/21

2 Subtask 1: Project Management

30 days Mon 7/12/21 Fri 8/20/21

3 Subtask 2: SVE Well and Piping Installation

30 days Mon 7/12/21 Fri 8/20/21

4 Field Work Preparation 2 wks Mon 7/12/21 Fri 7/23/21

5 SVE Well Installation 1 day Mon 7/26/21 Mon 7/26/21

6 SVE Piping Installation 2 days Tue 7/27/21 Wed 7/28/21

7 AS‐Built Drawings 3 wks Mon 8/2/21 Fri 8/20/21 sasha cobb

Dalvise Curry,Jose Mu

Dalvise Curry

7/18 7/25 A

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC063E at the Dixie Cleaners site located in Jacksonville, Duval County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/28/21 Fri 7/9/21

2 Subtask 1: Project Management

30 days Mon 7/12/21 Fri 8/20/21

3 Subtask 2: SVE Well and Piping Installation

30 days Mon 7/12/21 Fri 8/20/21

4 Field Work Preparation 2 wks Mon 7/12/21 Fri 7/23/21

5 SVE Well Installation 1 day Mon 7/26/21 Mon 7/26/21

6 SVE Piping Installation 2 days Tue 7/27/21 Wed 7/28/21

7 AS‐Built Drawings 3 wks Mon 8/2/21 Fri 8/20/21 uniz ry,Jose Muniz,steven Custer

8/1 8/8 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC063E at the Dixie Cleaners site located in Jacksonville, Duval County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/28/21 Fri 7/9/21

2 Subtask 1: Project Management

30 days Mon 7/12/21 Fri 8/20/21

3 Subtask 2: SVE Well and Piping Installation

30 days Mon 7/12/21 Fri 8/20/21

4 Field Work Preparation 2 wks Mon 7/12/21 Fri 7/23/21

5 SVE Well Installation 1 day Mon 7/26/21 Mon 7/26/21

6 SVE Piping Installation 2 days Tue 7/27/21 Wed 7/28/21

7 AS‐Built Drawings 3 wks Mon 8/2/21 Fri 8/20/21 Brian Moore,Peter McLean

8/15 8/22

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC063E at the Dixie Cleaners site located in Jacksonville, Duval County

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule

File details come from the government source that posted it. Updated .