CN-370000-HW555-DC017S.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|HW555|3626b1bfe23ad9cb6d0c11811d472cb2
Contract number
HW555
Issued by
Florida

About this file

This is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) involving groundwater monitoring services at McNatt's Cleaners facility located in Tampa, Hillsborough County. The contract is executed under DEP Contract No. HW555, Task Assignment DC017S, with GHD Services, Inc. serving as the contractor and Kevin Kane designated as the FDEP Contract Manager. The project site is identified as ERIC_4752, and the work falls under the monitoring phase of environmental remediation activities.

GHD Services, Inc. will conduct annual groundwater sampling and monitoring at 15 monitoring wells in accordance with FDEP Standard Operating Procedures and the June 2021 scope of work. The scope includes depth-to-water measurements at 33 total wells, groundwater sampling analyzed for volatile organic hydrocarbons via EPA Method 8260, select wells analyzed for additional parameters including total organic carbon, total dissolved solids, and dissolved gases, and preparation of a Groundwater Monitoring Report with field notes, analytical results, and recommendations. The fixed-price task assignment is valued at $8,588.88 with no retainage, covering labor costs ($4,573.17), overhead and administrative expenses ($2,056.56), travel ($194.00), laboratory services ($2,292.00), field expenses ($893.10), and subcontractor costs for Industrial Disposal Waste disposal ($93.50). The final deliverable—the Groundwater Monitoring Report—is due August 13, 2021, with task completion scheduled for December 17, 2021. The work is scheduled to commence June 21, 2021, with field sampling occurring June 28-29, 2021, and report preparation extending through mid-August 2021.

View the file

Other files

File Type Posted
CN-370000-HW555-A1.pdf PDF
CN-370000-HW555-A3.pdf PDF
CN-370000-HW555-A4.pdf PDF
CN-370000-HW555-A7.pdf PDF
CN-370000-HW555-C23BCO1.pdf PDF
CN-370000-HW555-DC007I.pdf PDF
CN-370000-HW555-DC007K.pdf PDF
CN-370000-HW555-DC013I.pdf PDF
CN-370000-HW555-DC015J.pdf PDF
CN-370000-HW555-DC017M.pdf PDF
CN-370000-HW555-DC017R.pdf PDF
CN-370000-HW555-DC01ACO1.pdf PDF
CN-370000-HW555-DC01ACO2.pdf PDF
CN-370000-HW555-DC01ACO9.pdf PDF
CN-370000-HW555-DC01E.pdf PDF
CN-370000-HW555-DC01K.pdf PDF
CN-370000-HW555-DC020F.pdf PDF
CN-370000-HW555-DC021H.pdf PDF
CN-370000-HW555-DC023G.pdf PDF
CN-370000-HW555-DC023K.pdf PDF
CN-370000-HW555-DC024o.pdf PDF
CN-370000-HW555-DC02BCO3.pdf PDF
CN-370000-HW555-DC02F.pdf PDF
CN-370000-HW555-DC02FCO1.pdf PDF
CN-370000-HW555-DC02GCO1.pdf PDF
CN-370000-HW555-DC031M.pdf PDF
CN-370000-HW555-DC033F.pdf PDF
CN-370000-HW555-DC034J.pdf PDF
CN-370000-HW555-DC035E.pdf PDF
CN-370000-HW555-DC045A.pdf PDF
CN-370000-HW555-DC046C.pdf PDF
CN-370000-HW555-DC04A.pdf PDF
CN-370000-HW555-DC04B.pdf PDF
CN-370000-HW555-DC04DCO1.pdf PDF
CN-370000-HW555-DC04E.pdf PDF
CN-370000-HW555-DC04FCO1.pdf PDF
CN-370000-HW555-DC04H.pdf PDF
CN-370000-HW555-DC050A.pdf PDF
CN-370000-HW555-DC052A.pdf PDF
CN-370000-HW555-DC053A.pdf PDF
CN-370000-HW555-DC05B.pdf PDF
CN-370000-HW555-DC065B.pdf PDF
CN-370000-HW555-DC065C.pdf PDF
CN-370000-HW555-DC066B.pdf PDF
CN-370000-HW555-DC069B.pdf PDF
CN-370000-HW555-DC06C.pdf PDF
CN-370000-HW555-DC06D.pdf PDF
CN-370000-HW555-DC06E.pdf PDF
CN-370000-HW555-DC06F.pdf PDF
CN-370000-HW555-DC07E.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW555

D000 N/ADC017S

GHD Services, Inc.

Brian Moore

(850) 245-8971Kevin Kane

ERIC_4752

McNatt's Cleaners

5227 Ehrlich Rd, Tampa, Hillsborough County

Monitoring

GHD Services, Inc. will conduct groundwater sampling in accordance with the June 2021 scope of work and cost proposal. A Groundwater Monitoring Report will be generated.

Groundwater Monitoring

08/13/2021

12/17/2021

$ 8,588.88 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Kevin Kane Digitally signed by Kevin Kane Date: 2021.06.10 13:52:31 -04'00'

Kevin Kane Digitally signed by Kevin Kane Date: 2021.06.10 13:52:49 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.06.10 15:54:28 -04'00'

Brian Moore Digitally signed by Brian Moore Date: 2021.06.11 10:32:37 -04'00'

$ 8,588.88

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report 08/13/2021

Upon completion of groundwater sampling and FDEP approval of the Groundwater Monitoring Report $ 8,588.88

$ 8,588.88

HW555

DC017S

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Interim Secretary

To: HW555 Contract File McNatt’s Cleaners

ERIC_4752

Tampa, Hillsborough County

From: Kevin Kane, Project Manager

Date: June 10, 2021

Subject: Negotiation Summary

HW555 DC017S

Monitoring

GHD Services, Inc. will conduct groundwater monitoring. Specific subtasks are detailed below:

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at 15 monitoring wells present on site in accordance with FDEP SOPs. All samples will be submitted to a certified lab for testing and analyzed for VOHs by EPA Method 8260. Select wells (8 total) will also be analyzed for the presence of total organic carbon, total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrite, chloride, and nitrate. Monitor wells MW051 and MW052 will also be analyzed for the presence of dissolved gases (methane, ethane, and ethene). IDW disposal is anticipated for this sampling event and has been accounted for under this subtask. All available site wells will also be sampled for water level measurements. Upon completion of groundwater sampling, a Groundwater Monitoring Report will be prepared and submitted to FDEP. Report will include field notes, analytical results, and recommendations.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is August 13, 2021, and the completion date for the task assignment is December 17, 2021.

The final cost total for Task Assignment DC017S is $8,588.88.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 06/09/21

Task #: DC017S SubTask 1 Project Management SubTask 6

Site: McNatts Cleaners SubTask 2 GW Monitoring SubTask 7

Activity/Phase: O&M SubTask 3 SubTask 8

Project Manager: Brian Moore, P.E. SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$69.71 Project Manager BM 2.74 2.735 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$69.71 Sr. Professional Engineer BM 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$44.21 Professional Engineer/Geologist JH 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $42.01 Professional Engineer/Geologist GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.00 Professional Engineer/Geologist KC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.04 Staff Engineer/Scientist MT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.88 Project Manager/Engineer NS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.91 Staff Engineer/Scientist SL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$22.76 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.18 Junior Technician SA 18.00 18.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.51 Junior Technician WO 16.50 16.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician PM 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.14 Staff Assistant SS 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 62.74 2.735 60.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,716.01 $190.67 $1,525.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 113.00% $1,939.09 $215.46 $1,723.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $480.49 $53.39 $427.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $437.58 $48.62 $388.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,573.17 $508.14 $4,065.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $85.80 $9.53 $76.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

REV: 02/03 CEF GHD Services Inc. Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 06/09/21

Task #: DC017S SubTask 1 Project Management SubTask 6

Site: McNatts Cleaners SubTask 2 GW Monitoring SubTask 7

Activity/Phase: O&M SubTask 3 SubTask 8

Project Manager: Brian Moore, P.E. SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $85.00 $85.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $85.00 $85.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $8.50 $8.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $93.50 $93.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $2,188.00 $2,188.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,292.00 $2,292.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $828.10 $828.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $893.10 $893.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $8,131.57 $517.67 $7,613.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $457.31 $50.81 $406.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $8,588.88 $568.48 $8,020.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GHD Services Inc. Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2

SITE : McNatts Cleaners

PROJECT NUMBER: 090113

FDEP NO: ERIC_4752

SUBTASK: GW Monitoring

DATE: 6/9/2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer BM Conclusions/Recommendations 1

Professional Engineer JH Specify laboratory data deliverable/Sample Kit 1 Professional Engineer JH Field sampling SOW/coordinate site access 1 Professional Engineer JH QA/QC field and laboratory data 1 Professional Engineer JH Project Background 1 Professional Engineer JH Groundwater Sampling Methods 1.5 Professional Engineer JH Water Quality Parameter Summary 1.5 Professional Engineer JH Groundwater Analtycial Results (VOCs) 2 Professional Engineer JH Groundwater Analytical Results (UIC/performance) 2 Professional Engineer JH QA/QC Laboratory Data 2 Professional Engineer JH Conclusions/Recommendations 1

Junior Technician SA Mob/Demob (2 days) 2 Junior Technician SA Water levels (all wells - 33 total) 4 Junior Technician SA Groundwater Sampling (8 wells) 12

Junior Technician WO Mob/Demob (2 days) 2 Junior Technician WO Water levels (all wells - 33 total) 4 Junior Technician WO Groundwater Sampling (7 wells) 10.5

16.5

Drafting Technician PM Groundwater elevation figures (4 zones) 2.5 Drafting Technician PM Groundwater analytical figures (4 zones) 2

4.5

Staff Assistant SS Data Entry (15 monitor wells, 33 wls) 2 Staff Assistants SS Update summary tables 2 Staff Assistant SS Document Preparation/Publishing 2

TOTAL LABOR 60

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $97.00 day 2 $194.00

TOTAL VEHICLE $194.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

Services Procurement

NAME PURPOSE COST UNIT USEAGE

Lewis Environmental IDW drum disposal $85 drum 1 $85.00

TOTAL SUBS $85.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

VOHs EPA Method 8260 $66.00 15 $990.00

TOC EPA 9060 $26.00 1 $26.00

TDS EPA 160.1 $11.50 3 $34.50

TRPH FL-PRO $84.00 3 $252.00

sodium EPA 6010 $11.50 3 $34.50 ammonia SM4500 $21.00 3 $63.00 chloride EPA 352.2 $14.00 2 $28.00 nitrate EPA 353.2 $20.00 3 $60.00 nitrite EPA 353.2 $20.00 3 $60.00 dissolved gases (methane, ethane, ethene) $160.00 4 $640.00 Sample Shipping Large Cooler (1 day) $104.00 1 $104.00

TOTAL LAB $2,292.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Expendables $32.50 Day 2 $65.00 Sub-Total $65.00

Groundwater Sampling Kit $208.55 day 3 $625.65 Poly Tubing (HDPE) $0.25 ft 457 $114.25 Silicon Tubing $2.00 ft 15 $30.00 55-gallon drum $58.20 drum 1 $58.20

Sub-Total $828.10

TOTAL EQUIPMENT $893.10

TA_017S.xlsx\sub 2 Page 3 6/9/20214:54 PM

COST PROPOSAL FOR TASK DC017S

McNatt’s Cleaners, 299502136

Groundwater Monitoring

1. INTRODUCTION:

GHD prepared a RAP Modification that was implemented in 2017. Following remedial injections and a period of SVE system operations, the system was recently shutdown. In order to continue to evaluate the performance of the remedial injections in accordance with the RAP Modification, groundwater monitoring is recommended. Task DC017S includes annual groundwater sampling in accordance with GHD’s recommendations from the semi-annual RASR dated April 2021.

Subtask 1: Project Management Includes all tasks associated with project management for annual groundwater sampling and reporting.

Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater monitoring. Prior to groundwater sampling, depth to water measurements will be gathered at all available monitor wells (33 total). Groundwater sampling will be conducted at fifteen (15) monitor wells including: MW001, MW002, MW004, MW019, MW025, MW030, MW031, MW033, MW040, MW042, MW043, MW045, MW051, MW052, and MW053. Groundwater sampling will be conducted in accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of Volatile Organic Halocarbons. Select wells (MW025, MW039, MW040, MW042, MW043, MW045, MW051, and MW052) will also be analyzed for the presence of total organic carbon, total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrite, chloride, and nitrate. In addition, monitor wells MW051 and MW052 will also be analyzed for dissolved gases (methane, ethane, ethene). The dissolved gas sampling will be conducted at MW051 and MW052 only, and will include a duplicate and an equipment blank.

Following receipt of analytical data, a Groundwater Monitoring Report (GMR) will be prepared. The GMR will include a summary of groundwater sampling methods and analytical results. The GMR will provide recommendations for additional remediation and/or testing.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 8/13/21

May 25, 2021

Bryan Moore GHD Engineering 525 Technology Park #181 Lake Mary, FL 32746

Re: Non-Hazardous Drummed Waste Disposal Services Multiple Sites in Tampa and Orlando Florida Lewis Proposal No. 210350LA

Dear Bryan:

Lewis Environmental (Lewis) is pleased to present GHD, this proposal for non-hazardous drum disposal services. This scope of work includes the transportation and disposal of non-hazardous PCW drums in the Orlando and Tampa, FL areas. The following is offered for your review and consideration.

Scope of Work:

Lewis has provided cost for one technician, one rack truck, drum dollies and miscellaneous tools to complete the tasks as outlined below:

Lewis will provide waste profiles for approval and signature by the generator (if required).

Lewis will arrive on-site to load the containerized waste onto the truck. Lewis will only transport drums that are in DOT shippable condition.

Lewis will transport the drum(s) to the approved disposal facility.

Lewis will provide fully executed waste manifests and disposal documentation to Generator.

Pricing:

Drummed Waste Transportation and Disposal Non-Hazardous Waste Loading/Transportation $550.00/Load Non-Hazardous Waste Disposal - PCW $85.00/Drum Supply Overpack Drum (if required) $250.00/Drum

Assumptions and Clarifications:

Lewis assumes a GHD and/or Generator site representative will be onsite to assist with site access, locating the waste and to sign manifest document(s) if required.

Lewis assumes free and clear access to the site on scheduled workdays.

Waste disposal pricing is contingent upon facility approval.

Disposal pricing assumes drum weights to be under 600 pounds. Drums exceeding 600 pounds will incur an additional $15.00 per drum surcharge.

Lewis has included 1-hour of loading into the above pricing. Additional time to load and/or unload the drums will be invoiced per quarter hour at $135.00/hour.

Lewis assumes drums will contain non-hazardous waste that possesses no chemical characteristics or constituents that will disqualify it from non-hazardous disposal.

Lewis assumes drums are stored on a concrete or asphalt surface and are accessible with a skid steer and drum grabber attachment.

All waste must meet acceptability criteria of the designated disposal facility and comply with Local, State, and Federal regulations. This proposal is contingent upon sample evaluation and waste approval at the disposal facility. Any waste not meeting facility criteria will be subject to surcharges or possible facility rejection. In the event of a waste surcharge or facility rejection the associated costs will be invoiced additionally.

The drums must be of sound structure, non-leaking and conform to all Department of Transportation Regulations. Drums not meeting these requirements may require over packs at additional cost.

Lewis assumes any analytical required by the waste facility will be provided by Generator.

All minimum waste volumes/weights assessed by the disposal facility will be passed on to the Generator/client.

The disposal pricing provided represents one cost effective means for proper disposal of waste(s) associated with this proposal. Ultimately the generator of the waste is responsible for the selection of the disposal, recycling or treatment facility.

We appreciate the opportunity to offer GHD pricing for this project and look forward to working with you its successful completion. If you have any questions, please do not hesitate to contact me at 484-942-3093. Thank you for your time and consideration.

Sincerely, Paul Mansur Environmental Compliance Manager

Gulf Coast Vacuum Truck Services 1744 Williams Ditch Rd

Cantonment, FL 32533 US

+1 8504500058 accounting@gcvts.net

Estimate

ADDRESS

GHD

ESTIMATE 1040

DATE 04/15/2021

DATE SERVICE DESCRIPTION QTY RATE AMOUNT

Drum Disposal Disposal of of 1 drum of contaminated water.

1 95.00 95.00

Island Cleaners - Sanibel TOTAL $95.00

Accepted By

Accepted Date

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

April 15, 2021

Re: Non-Hazardous Drum Disposal Quote – South and Central Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in south and central

Florida will be $100.00 per drum, total, for both transportation and disposal.

Pricing for the Florida Keys will be quoted separately on a case-by-case basis.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/7/21 Fri 6/18/21

2 Subtask 1: Project Management

40 days Mon 6/21/21

Fri 8/13/21

3 Subtask 2: Groundwater Monitoring

40 days Mon 6/21/21

Fri 8/13/21

4 Field Work Preparation 1 wk Mon 6/21/21Fri 6/25/21

5 Groundwater Sampling 2 days Mon 6/28/21Tue 6/29/21

6 Groundwater Monitoring Report

6 wks Mon 7/5/21 Fri 8/13/21

5/30 6/6 6/13 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017S at the McNatts Cleaners facility located in Tampa, Hillsborough County

Project: TA_017S Date: Mon 6/7/21

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/7/21 Fri 6/18/21

2 Subtask 1: Project Management

40 days Mon 6/21/21

Fri 8/13/21

3 Subtask 2: Groundwater Monitoring

40 days Mon 6/21/21

Fri 8/13/21

4 Field Work Preparation 1 wk Mon 6/21/21Fri 6/25/21

5 Groundwater Sampling 2 days Mon 6/28/21Tue 6/29/21

6 Groundwater Monitoring Report

6 wks Mon 7/5/21 Fri 8/13/21

Jeremy Hess

Skylar Albritton,William Ouchie

6/20 6/27 7/4 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017S at the McNatts Cleaners facility located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/7/21 Fri 6/18/21

2 Subtask 1: Project Management

40 days Mon 6/21/21

Fri 8/13/21

3 Subtask 2: Groundwater Monitoring

40 days Mon 6/21/21

Fri 8/13/21

4 Field Work Preparation 1 wk Mon 6/21/21Fri 6/25/21

5 Groundwater Sampling 2 days Mon 6/28/21Tue 6/29/21

6 Groundwater Monitoring Report

6 wks Mon 7/5/21 Fri 8/13/21

7/11 7/18 7/25

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017S at the McNatts Cleaners facility located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 6/7/21 Fri 6/18/21

2 Subtask 1: Project Management

40 days Mon 6/21/21

Fri 8/13/21

3 Subtask 2: Groundwater Monitoring

40 days Mon 6/21/21

Fri 8/13/21

4 Field Work Preparation 1 wk Mon 6/21/21Fri 6/25/21

5 Groundwater Sampling 2 days Mon 6/28/21Tue 6/29/21

6 Groundwater Monitoring Report

6 wks Mon 7/5/21 Fri 8/13/21 Brian Moore,Jeremy Hes

8/1 8/8 8/15 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017S at the McNatts Cleaners facility located in Tampa, Hillsborough County

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule

File details come from the government source that posted it. Updated .