This is a Task Assignment Notification Form for Florida Department of Environmental Protection (FDEP) Contract No. HW555, issued on June 3, 2021. The contract involves GHD Services, Inc. as the contractor, with Kevin Kane serving as the DEP Contract Manager and Brian Moore as the Contractor Representative. The work is being performed at My Favorite Cleaners facility located at 1580-36 Wells Road, Orange Park, Clay County, Florida (FDEP Site No. ERIC_4255). Task Assignment DC066B is classified as a monitoring phase engagement under the indefinite delivery vehicle contract.
The scope of work encompasses groundwater monitoring services consisting of two subtasks: Project Management (calculated at 12.5 percent of direct labor) and Groundwater Monitoring. The groundwater monitoring includes sampling from six monitoring wells (MW001-MW006) in accordance with FDEP Standard Operating Procedures, analysis for volatile organic hydrocarbons using EPA Method 8260, and preparation of a Groundwater Monitoring Report with field notes, analytical results, and recommendations. The deliverable is due September 3, 2021, with task completion by December 3, 2021. The total task assignment value is $3,974.75 on a fixed price basis with zero retainage. This amount includes direct labor costs of $1,006.44, overhead and administrative charges totaling $1,681.73, travel expenses of $97.00, subcontractor costs for indisposed waste (IDW) disposal of $104.50, laboratory analytical services of $497.00, field expenses of $275.55, and a completion fee of $268.21. Invoice payment is contingent upon completion of groundwater sampling and FDEP approval of the final Groundwater Monitoring Report.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW555
D000 N/ADC066B
GHD Services, Inc.
Brian Moore
(850) 245-8971Kevin Kane
ERIC_4255
My Favorite Cleaners
1580-36 Wells Rd, Orange Park, Clay County
Monitoring
GHD Services, Inc. will conduct groundwater sampling in accordance with the June 2021 scope of work and cost proposal. A Groundwater Monitoring Report will be generated.
Groundwater Monitoring Report
09/03/2021
12/03/2021
$ 3,974.75 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Kevin Kane Digitally signed by Kevin Kane Date: 2021.06.03 08:22:56 -04'00'
Kevin Kane Digitally signed by Kevin Kane Date: 2021.06.03 08:23:17 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.06.03 10:17:08 -04'00'
Brian Moore Digitally signed by Brian Moore Date: 2021.06.09 11:21:49 -04'00'
$ 3,974.75
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report 09/03/2021
Upon completion of groundwater sampling and FDEP approval of the Groundwater Monitoring Report $ 3,974.75
$ 3,974.75
HW555
DC066B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
TO: HW555 Contract File My Favorite Cleaners
ERIC_4255
Orange Park, Clay County
FROM: Kevin Kane, Contract Manager
DATE: June 2, 2021
SUBJECT: Task Assignment Summary
HW555 DC066B
Monitoring
GHD Services, Inc. will conduct groundwater monitoring. Specific subtasks are detailed below:
Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.
Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at 6 monitoring wells present on site in accordance with FDEP SOPs. All samples will be submitted to a certified lab for testing and analyzed for VOHs by EPA Method 8260. IDW disposal is anticipated for this sampling event and has been accounted for under this subtask. All available site wells will also be sampled for water level measurements. Upon completion of groundwater sampling, a Groundwater Monitoring Report will be prepared and submitted to FDEP.
Report will include field notes, analytical results, and recommendations.
This work will be conducted in line with the scope of work included in the GHD proposal, received June 2, 2021.
Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is September 3, 2021, and the completion date for the Task Assignment is December 3, 2021.
The final cost total for Task Assignment DC066B is $3,974.75.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 06/02/21
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$69.71 Project Manager BM 1.60 1.604 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$69.71 Sr. Professional Engineer BM 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$40.00 Professional Engineer/Geologist ES 12.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $42.64 Professional Engineer/Geologist GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.00 Professional Engineer/Geologist KC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.72 Staff Engineer/Scientist BG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.91 Project Manager/Engineer SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.73 Staff Engineer/Scientist VH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$21.14 Junior Technician BJ 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.08 Junior Technician SC 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.51 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician PM 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.14 Staff Assistant SS 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 32.60 1.604 31.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,006.44 $111.83 $894.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 113.00% $1,137.28 $126.37 $1,010.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $281.80 $31.31 $250.49 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $256.65 $28.52 $228.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $2,682.17 $298.03 $2,384.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $50.32 $5.59 $44.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
REV: 02/03 CEF GHD Services Inc. Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 06/02/21
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $9.50 $9.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $104.50 $104.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $462.00 $462.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $35.00 $35.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $497.00 $497.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $243.05 $243.05 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $275.55 $275.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $3,706.54 $303.62 $3,402.92 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $268.21 $29.80 $238.41 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $3,974.75 $333.42 $3,641.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF GHD Services Inc. Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2
SITE : My Favorite Cleaners
PROJECT NUMBER: 11147374-03
FDEP NO: ERIC_4255
SUBTASK: Groundwater Monitoring
DATE: 6/2/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer BM Conclusions/Recommendations 1
Professional Geologist ES Specify laboratory data deliverable/Sample Kit 1 Professional Geologist ES Field sampling SOW/coordinate site access 1 Professional Geologist ES QA/QC field and laboratory data 1 Professional Geologist ES Coordinate IDW Disposal 1 Professional Geologist ES Project Background 1 Professional Geologist ES Groundwater Sampling Methods 1 Professional Geologist ES Groundwater flow evaluation 1 Professional Geologist ES Water Quality Parameter Summary 1 Professional Geologist ES Groundwater Analtycial Results 2 Professional Geologist ES QA/QC Laboratory Data 1 Professional Geologist ES Conclusions/Recommendations 1
Junior Technician SC Mob/demob 1 Junior Technician SC Water Levels (all wells - 6 total) 1 Junior Technician SC Groundwater Sampling (6 wells) 9
Drafting Technician PM Prepare GW Flow map 1 Drafting Technician PM Prepare VOC plume figures with updated concentration data 2
Staff Assistant SS Data Entry (6 wls, and 6 monitor wells) 1 Staff Assistant SS Update data tables 1 Staff Assistant SS Document Preparation/Publishing 2
TOTAL LABOR 31
TRAVEL TYPE RATE UNIT USEAGE Miles Free
Truck $97.00 day 1 $97.00
TOTAL VEHICLE $97.00
SUBCONTRACTOR
Equipment Procurement
NAME PURPOSE COST UNIT USEAGE
Services Procurement
NAME PURPOSE COST UNIT USEAGE
Gulf Coast IDW Disposal $95.00 drum 1 $95.00
TOTAL SUBS $95.00
LABORATORY
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA 8260 $66.00 6 1 $462.00 Sample Shipping Small Cooler (2 day) $35.00 1 $35.00
TOTAL LAB $497.00
FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS
Field Equipment
Expendables $32.50 Day 1 $32.50 Sub-Total $32.50
Groundwater Sampling Kit $208.55 day 1 $208.55 Poly Tubing (HDPE) $0.25 ft 90 $22.50 Silicon Tubing $2.00 ft 6 $12.00
Sub-Total $243.05
TOTAL EQUIPMENT $275.55
TA_066B.xlsx\sub 2 Page 3 6/2/20213:51 PM
COST PROPOSAL FOR TASK DC066B
<My Favorite Cleaners/FDEP ERIC_4255>
< Groundwater Monitoring >
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD Services Inc. (GHD) initially completed advanced site assessment (ASA) activities at the My Favorite Cleaners site. Although a site access agreement was signed by the current property owner, access to the interior space has not been authorized. Task DC066 B includes groundwater sampling at existing exterior monitor wells.
Subtask 1: Project Management Subtask 1 includes all tasks associated with project management for groundwater monitoring and reporting.
Subtask 2: Groundwater Monitoring
In accordance with discussions with FDEP, groundwater monitoring is proposed at available site monitor wells. GHD personnel will mobilize to the site for sampling. Prior to groundwater sampling, depth to water measurements will be gathered from all site monitor wells. Groundwater samples will be collected from MW001 through MW006. Groundwater sampling will be conducted in accordance with FDEP Standard Operating Procedures and groundwater samples will be submitted for volatile organic halocarbon analysis by EPA Method 8260.
Upon receipt of analytical data, a Groundwater Monitoring Report (GMR) will be prepared.
The GMR will include a summary of field sampling activities as well as analytical results. The GMR will also include recommendations for additional monitoring and/or cleanup activities.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 9/3/21
Gulf Coast Vacuum Truck Services 1744 Williams Ditch Rd
Cantonment, FL 32533 US
+1 8504500058 accounting@gcvts.net
Estimate
ADDRESS
GHD
ESTIMATE 1040
DATE 04/15/2021
DATE SERVICE DESCRIPTION QTY RATE AMOUNT
Drum Disposal Disposal of of 1 drum of contaminated water.
1 95.00 95.00
Island Cleaners - Sanibel TOTAL $95.00
Accepted By
Accepted Date
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
April 15, 2021
Re: Non-Hazardous Drum Disposal Quote – South and Central Florida
Mr. Moore:
The price for disposal of drums of non-hazardous soil or groundwater located in south and central
Florida will be $100.00 per drum, total, for both transportation and disposal.
Pricing for the Florida Keys will be quoted separately on a case-by-case basis.
This quote is valid for 180 days.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approva 2 wks Wed 6/2/21 Tue 6/15/21
2 Subtask 1: Project Management
57 days Wed 6/16/21
Thu 9/2/21
3 Subtask 2:
Groundwater Monitoring
46 days Thu 7/1/21 Thu 9/2/21
4 Field Work Preparatio2 wks Thu 7/1/21 Wed 7/14/21
5 Groundwater Samplin1 day Thu 7/15/21 Thu 7/15/21
6 Groundwater Monitoring Report
6 wks Fri 7/23/21 Thu 9/2/21
5/23 5/30 6/6 6/13 June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC066B at the My Favorite Cleaners facility located in Orange Park, Clay County
Project: TA_066B Date: Wed 6/2/21
Task Name Duration Start Finish
1 LOE Submittal/Approva 2 wks Wed 6/2/21 Tue 6/15/21
2 Subtask 1: Project Management
57 days Wed 6/16/21
Thu 9/2/21
3 Subtask 2:
Groundwater Monitoring
46 days Thu 7/1/21 Thu 9/2/21
4 Field Work Preparatio2 wks Thu 7/1/21 Wed 7/14/21
5 Groundwater Samplin1 day Thu 7/15/21 Thu 7/15/21
6 Groundwater Monitoring Report
6 wks Fri 7/23/21 Thu 9/2/21
Edwin Sie
Steven
6/20 6/27 7/4 7/11 July
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC066B at the My Favorite Cleaners facility located in Orange Park, Clay County
Task Name Duration Start Finish
1 LOE Submittal/Approva 2 wks Wed 6/2/21 Tue 6/15/21
2 Subtask 1: Project Management
57 days Wed 6/16/21
Thu 9/2/21
3 Subtask 2:
Groundwater Monitoring
46 days Thu 7/1/21 Thu 9/2/21
4 Field Work Preparatio2 wks Thu 7/1/21 Wed 7/14/21
5 Groundwater Samplin1 day Thu 7/15/21 Thu 7/15/21
6 Groundwater Monitoring Report
6 wks Fri 7/23/21 Thu 9/2/21 n Siersema even Custer
7/18 7/25 8/1 8/8 August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC066B at the My Favorite Cleaners facility located in Orange Park, Clay County
Task Name Duration Start Finish
1 LOE Submittal/Approva 2 wks Wed 6/2/21 Tue 6/15/21
2 Subtask 1: Project Management
57 days Wed 6/16/21
Thu 9/2/21
3 Subtask 2:
Groundwater Monitoring
46 days Thu 7/1/21 Thu 9/2/21
4 Field Work Preparatio2 wks Thu 7/1/21 Wed 7/14/21
5 Groundwater Samplin1 day Thu 7/15/21 Thu 7/15/21
6 Groundwater Monitoring Report
6 wks Fri 7/23/21 Thu 9/2/21 Brian Moore,Edwin Sier
8/15 8/22 8/29 9/5 September
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC066B at the My Favorite Cleaners facility located in Orange Park, Clay County
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .