Task Assignment Summary
This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under DEP Contract No. HW552, a Bureau of Waste Cleanup Consolidated Services contract dated December 10, 2010. The task assignment authorizes Professional Service Industries, Inc. (PSI), an Intertek company, to perform operation and maintenance services and groundwater monitoring at the Westwood Cleaners facility located at 4513 Gunn Highway in Tampa, Hillsborough County, Florida. The FDEP Contract Manager is Killian Talley, and the contractor representative is Nana Westmark.
The task assignment authorizes PSI to conduct six months of operation and maintenance of the Soil Vapor Extraction (SVE) system, pay associated utility costs, perform annual groundwater monitoring, and submit a Remedial Action System Status Report and groundwater monitoring data. The scope includes six monthly operation and maintenance site visits with system optimization, quarterly air sampling via EPA Method TO-15, groundwater elevation measurements and sampling from 20 monitoring wells, and laboratory analysis of groundwater samples via EPA Method 8260. The total task assignment value is $38,679.96, comprised of a fixed price component of $33,579.96 and a cost-plus fixed fee component of $5,100.00 for utilities, plus a $240.00 handling fee. The period of performance extends from execution of the task assignment through October 29, 2021, with a final deliverable due date of July 30, 2021. No retainage was applied to this task assignment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW552
D000 N/ADC032E
Professional Service Industries (PSI)
Nana Westmark
850-245-8928Killian Talley
ERIC_4706
Westwood Cleaners
4513 Gunn Hwy, Tampa Hillsborough
Operation & Maintenance (O&M)
This Task Assignment authorizes PSI to perform six months of Operation & Maintenance of the Soil Vapor Extraction (SVE) system, as well as annual groundwater monitoring, in accordance with the October 9, 2020 scope of work and cost estimate forms.
The payment of utilities under this Task Assignment is the only portion of this Task Assignment that is Cost Plus Fixed Fee.
Submittal of Six Months paid utilities invoices
07/30/2021
10/29/2021
$ 33,579.96 $ 0.00 $ 5,100.00 $ 0.00
$ 0.00
Killian Talley Digitally signed by Killian Talley Date: 2020.10.13 12:40:10 -04'00'
Killian Talley Digitally signed by Killian Talley Date: 2020.10.13 12:40:20 -04'00'
David Phillips Digitally signed by David Phillips Date: 2020.10.13 15:59:29 -04'00'
Nana G Westmark Digitally signed by Nana G Westmark Date: 2020.10.19 10:52:36 -04'00'
$ 38,679.96
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2&3: Submittal of Quarters 1 & 2 O&M Checklists 06/16/2021
Subtask 1,4&6: Submittal of Remedial Action System Status Report & 2021 Groundwater Monitoring Data; GIS/ADaPT data 07/30/2021
Subtask 5: Submittal of Six Months paid utilities invoices 07/30/2021
Subtask 2-3: FDEP receipt and approval of Quarters 1 & 2 O&M Checklists $ 18,992.39
Subtask 1,4&6: FDEP receipt and approval of Remedial Action System Status Report & 2021 Groundwater Monitoring Data; GIS/ADaPT data $ 14,347.57
Subtask 5: FDEP receipt and approval of six months paid utilities invoices; Utilities (Cost Plus Fixed Fee): not to exceed $2,460.00 Handling Fee: $240.00
$ 5,340.00
$ 38,679.96
HW552
DC032E
Florida Department of Memorandum Environmental Protection
To: HW552 Contract Negotiation File
Westwood Cleaners Tampa, Hillsborough County
ERIC_5423
From: Killian Talley, Project Manager Date: October 13, 2020 Subject: Negotiation Summary
HW552 DC032E
Task Assignment DC032E is for PSI to conduct six months of Operation and Maintenance (O&M) for the Soil Vapor Extraction (SVE) system, pay the associated utilities, and submit a Remedial Action System Status (RASS) and Groundwater Monitoring.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2&3: Six Months of O&M (First & Second Quarter) This subtask includes all associated costs and labor hours for six months of O&M activities including monthly site visits, inspection and maintenance, trouble shooting, and air sampling. Air emissions will be monitored by EPA Method TO-15.
Subtask 4: Groundwater Monitoring & Semi-Annual RASS Report The RASS will be generated under this subtask. Report will outline and describe field events, analytical results, and provide conclusions and recommendations for the site.
Subtask 5: Utilities Subtask includes costs related to payment of utilities including account handling.
Subtask 6: Groundwater Sampling Subtask includes costs and labor for PSI to conduct annual groundwater sampling and analysis of the existing monitoring well network. Data from event will be included in the RASS Report.
This Task Assignment will be conducted for the fixed price amount of $33,579.96 with a cost-plus fixed price fee of $5,100.00 for a total of $38,679.96 with 220 labor hours. The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment.
FDEP COST ESTI MATEContractor: Professional Service Industries, Inc.
Date: 10/9/2020
Task #: SUBTASK 1: Project Management SUBTASK 6: Groundwater Sampling
Site: Westwood Cleaners SUBTASK 2: 1st Quarter Monthly O&M SUBTASK 7:
Activity/Phase: O&M, RASS, GW SUBTASK 3: 2nd Quarter Monthly O&M SUBTASK 8:
Project Manager: Nana Westmark SUBTASK 4: Semi-Annual RASS, Groundwater SUBTASK 9:
SUBTASK 5: Utilities SUBTASK 10:
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
Professional Service Industries, Inc.
$48.08 Project Manager 18 17.6 $62.50 Principal Consultant 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $52.89 Senior Engineer, MR 45 18.0 18.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 $48.08 Senior Geologist, NW 10 8.0 0.0 0.0 0.0 2.0 0.0 0.0 0.0 0.0 $45.20 Senior Scientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $34.62 Certified Industrial Hygientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $50.00 Certified Hazardous Materials Manager 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $50.00 Florida Licensed Asbestos Consultant 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $39.42 Project Manager 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $31.73 Project Engineer, MM 43 6.0 6.0 31.0 0.0 0.0 0.0 0.0 0.0 0.0 $32.94 Project Geologist, CC 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $29.81 Project Scientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $29.81 QA Officer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $32.21 Remediation Coordinator 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
$0.00 Professional Land Surveyor 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $0.00 Chemist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
$24.50 GIS Specialist, DG 9 0.0 0.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 $25.00 Staff Engineer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $24.04 Staff Scientist, RF 41 0.0 0.0 0.0 0.0 40.5 0.0 0.0 0.0 0.0 $24.76 Staff Scientist, RH 54 27.0 27.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $24.04 Environmental Specialist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $24.04 Environmental Scientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $18.30 Environmental Technician 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $18.75 Administrative Assistant 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $15.50 Secretary 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $15.00 Senior Laborer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $12.00 Laborer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Hours 220 18 59.0 51.0 49.0 0.0 42.5 0.0 0.0 0.0 0.0
Professional Service Industries, Inc.
Direct Labor $7,600.95 $844.55 $2,195.56 $1,810.92 $1,680.14 $0.00 $1,069.78 $0.00 $0.00 $0.00 $0.00
Overhead 170.96% $12,994.59 $1,443.84 $3,753.53 $3,095.95 $2,872.37 $0.00 $1,828.90 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $20,595.54 $2,288.39 $5,949.09 $4,906.87 $4,552.51 $0.00 $2,898.68 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $380.06 $42.23 $109.78 $90.55 $84.01 $0.00 $53.49 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF_PSI.XLS Page 1
FDEP COST ESTI MATEContractor: Professional Service Industries, Inc.
Date: 10/9/2020
Task #: SUBTASK 1: Project Management SUBTASK 6: Groundwater Sampling
Site: Westwood Cleaners SUBTASK 2: 1st Quarter Monthly O&M SUBTASK 7:
Activity/Phase: O&M, RASS, GW SUBTASK 3: 2nd Quarter Monthly O&M SUBTASK 8:
Project Manager: Nana Westmark SUBTASK 4: Semi-Annual RASS, Groundwater SUBTASK 9:
SUBTASK 5: Utilities SUBTASK 10:
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $1,002.00 $291.00 $291.00 $0.00 $0.00 $420.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,002.00 $291.00 $291.00 $0.00 $0.00 $420.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $5,100.00 $0.00 $0.00 $0.00 $5,100.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $5,100.00 $0.00 $0.00 $0.00 $5,100.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $240.00 $0.00 $0.00 $0.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $5,340.00 $0.00 $0.00 $0.00 $5,340.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $4,939.20 $1,974.60 $1,974.60 $0.00 $0.00 $990.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $4,939.20 $1,974.60 $1,974.60 $0.00 $0.00 $990.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $357.50 $97.50 $97.50 $0.00 $0.00 $162.50 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $4,006.10 $1,062.15 $1,062.15 $0.00 $0.00 $1,881.80 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $4,363.60 $1,159.65 $1,159.65 $0.00 $0.00 $2,044.30 $0.00 $0.00 $0.00 $0.00
Subtotal $36,620.40 $2,330.62 $9,484.12 $8,422.67 $4,636.52 $5,340.00 $6,406.47 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,059.56 $228.84 $594.91 $490.69 $455.25 $0.00 $289.87 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $38,679.96 $2,559.46 $10,079.03 $8,913.36 $5,091.77 $5,340.00 $6,696.34 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF_PSI.XLS Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Westwood Cleaners SUBTASK 2: 1st Quarter Monthly O&M
DATE: 10/9/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Geologist, N Westmark Develop Level of Effort, Cost Estimate 8
Senior Engineer, M Rothenburg Provide oversight and technical support (1 hr/monthly, 3 hrs/quarterly) 6 Telemetry check (3 times per week = 2 hours per month) 6 System evaluation (1 hr/month), review and submittal 3 O&M checklists (1 hr/month) 3
Staff Scientist, R Hanson Monthly
Load / Unload 1 Mobilization 1 Conduct O&M, optimize performance 2 Clear SVE lines of water 1 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Pickup / drop off samples 1
Monthly Load / Unload 1 Mobilization 1 Conduct O&M, optimize performance 2 Clear SVE lines of water 1 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Pickup / drop off samples 1
Monthly Load / Unload 1 Mobilization 1 Conduct O&M, optimize performance 2 Clear SVE lines of water 1 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Pickup / drop off samples 1
Additional hours to collect vapor analytical samples 3
Project Engineer, M Mui Preparation and recording of system data into the ongoing operational 6 tables
TOTAL LABOR 59.0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
Construction/O&M/Pilot Test Kit $291.00 day 3 $873.00 Construction/O&M supplies $63.05 day 3 $189.15
$1,062.15
Expendables $32.50 day 3 $97.50
TOTAL EQUIPMENT 1,159.65$
VEHICLE TYPE RATE UNIT USAGE
Equipment Van / Truck $97.00 day 3 $291.00
TOTAL VEHICLE 291.00$
PER DIEM STAFF RATE UNIT USAGE
TOTAL PER DIEM -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$200.00 9 0 $1,800.00
Summa cannisters $19.40 9 $174.60 $1,974.60
TOTAL LAB 1,974.60$
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
TO-15 (VOCs) (6 SVE wells, 1 eff - 1 month, 1 eff for next 2 months)
FINAL --7/24/96
Page 7 Westwood 0552-324023
SUBTASK 3:2nd Quarter Monthly O&M
DATE: 10/9/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Engineer, M Rothenburg Provide oversight and technical support (1 hr/monthly, 3 hrs/quarterly) 6 Telemetry check (3 times per week = 2 hours per month) 6 System evaluation (1 hr/month), review and submittal 3 O&M checklists (1 hr/month) 3
Staff Scientist, R Hanson Monthly
Load / Unload 1 Mobilization 1 Conduct O&M, optimize performance 2 Clear SVE lines of water 0 1 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Pickup / drop off samples 1
Monthly Load / Unload 1 Mobilization 1 Conduct O&M, optimize performance 2 Clear SVE lines of water 1 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Pickup / drop off samples 1
Monthly Load / Unload 1 Mobilization 1 Conduct O&M, optimize performance 2 Clear SVE lines of water 1 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Pickup / drop off samples 1
Additional hours to collect vapor analytical samples 3
Project Engineer, M Mui Preparation and recording of system data into the ongoing operational 6 tables
TOTAL LABOR 51.0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
Construction/O&M/Pilot Test Kit $291.00 day 3 $873.00 Construction/O&M supplies $63.05 day 3 $189.15
$1,062.15 Expendables $32.50 day 3 $97.50
TOTAL EQUIPMENT 1,159.65$
VEHICLE TYPE RATE UNIT USAGE
Equipment Van / Truck $97.00 day 3 $291.00
TOTAL VEHICLE 291.00$
PER DIEM STAFF RATE UNIT USAGE
TOTAL PER DIEM -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$200.00 9 0 $1,800.00
Summa cannisters $19.40 9 $174.60 $1,974.60
TOTAL LAB 1,974.60$
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
TO-15 (VOCs) (6 SVE wells, 1 eff - 1 month, 1 eff for next 2 months)
FINAL --7/24/96
Page 8 Westwood 0552-324023
SUBTASK 4: Semi-Annual RASS, Groundwater
DATE: 10/9/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Engineer, M Rothenburg Evaluate data 6 Review Final RASS 2 Sign and Seal RASS 1
Project Engineer, M Mui Data reduction/evaluation 10 Preparation of report 6 Groundwater quality data 10 Prrepare ADaPT package 3 Report - Prepare final tables and figures 2
GIS/CADD Specialist, D Grove Create Final figures 9
TOTAL LABOR 49.0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
Page 9 Westwood 0552-324023
SUBTASK 5: Utilities
DATE: 10/9/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
#REF!
TOTAL LABOR 0.0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
TOTAL EQUIPM $0.00
VEHICLE TYPE RATE UNIT USAGE
TOTAL VEHICLE -$
PER DIEM STAFF RATE UNIT USAGE
TOTAL PER DIE -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC IDW
O&M
$0.00 $0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Florida Power & Light Electric $750.00 Month 6 $4,500.00 Century Link Phone $100.00 Month 6 $600.00
$5,100.00
Handling fee Electric $20.00 Month 6 $120.00 Handling fee phone $20.00 Month 6 $120.00
$240.00
TOTAL $5,340.00
Page 10 Westwood 0552-324023
SITE : Main Street SUBTASK 6: Groundwater Sampling
DATE: 10/9/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Activities Senior Geologist, N Westmark Technical oversight 2
Staff Scientist, R Fetter Load / Unload 1 Travel (5 roundtrips for gw sampling) 5 Collect groundwater elevations (22 wells) (10 minutes per well) 3.5 Collect groundwater samples 9 shallow wells @ 1 hour each 9 8 intermediate wells @ 1.5 hours each 12 3 deep wells @ 2 hrs per well 6 Documentation of groundwater sampling & measurements 2 Pickup / drop off samples 2
40.5
TOTAL LABOR 42.5
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Shallow Groundwater Sampling Kit $208.55 day 4 $834.20 Deep Groundwater Sampling Kit $349.20 day 3 $1,047.60
$1,881.800
Expendables $32.50 day 5 $162.50
TOTAL EQUIPMENT $2,044.30
VEHICLE TYPE RATE UNIT USEAGE
Equipment Van / Truck (GW Sampling) $97.00 day 0 $0.00 $420.00 week 1 $420.00
TOTAL VEHICLE $420.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC #IDW
EPA Method 8260 $66.00 14 1 0 $990.00
TOTAL LAB $990.00
BCONTRACTOR COSTS
NAME PURPOSE UNIT COST
TOTAL $0.00
Page 11 Westwood 0552-324023
PSI Proposal Number: 0552- 324023 October 9, 2020
Professional Service Industries, Inc.
5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634
Phone: (813) 886-1075 Fax: (813) 249-4916 www.intertek.com/building
Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400
Attention: Mr. Killian Talley, Environmental Specialist III Contract Manager Telephone: (850) 245-8705 Email: Killian.Talley@FloridaDEP.gov
Re: Proposal for O&M, Groundwater Monitoring and Report Westwood Cleaners
4513 Gunn Highway Tampa, Florida, 33624 Facility ID No. 29950774, ERIC_4706
Dear Mr. Talley:
Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to provide remediation system Operation & Maintenance (O&M) services, documentation of the remediation system performance with the development of one Remedial Action System Status Report, and Annual Groundwater Monitoring for the former Westwood Cleaners located at 4513 Gunn Highway, Tampa, Florida. Included with this proposal is a brief discussion of project history to date, proposed scope of work, cost estimate and a proposed schedule for completion.
PROJECT BACKGROUND
The Westwood Cleaners operated from 1984 to 2003 and occupied a tenant space on the east portion of a multi-tenant commercial shopping center in Tampa, Florida. The cleaners operated one tetrachloroethene (PCE) drycleaning machine and the facility has two floor drains. Based on results from the Site Screening activities in May 1997 showing PCE in the soil at a concentration of 700,000 micrograms per kilogram (µg/kg), the drycleaner business was accepted into the Drycleaning Solvent Cleanup Program. The soil sample was collected near the backdoor of the drycleaner building.
mailto:Killian.Talley@FloridaDEP.gov
PSI Proposal Number: 0552-324023 FDEP – Westwood Cleaners
O&M
The former Westwood Cleaners tenant space is currently a martial arts studio, Carrollwood Tae Kwon Do, that trains numerous children typically on weekday afternoons. The business has been remodeled with an elevated bamboo floor for the martial arts training. No drycleaning equipment remains at the former drycleaners.
A Site Assessment / Interim Source Removal Plan was prepared by PSI for the FDEP and was submitted August 29, 2018, and subsequently approved by the FDEP on May 20, 2019. Of note is the very high PCE concentration detected in the shallow well installed next to the former dryclean machine at 64,000 ug/L in February 2018 and most recently at 12,000 ug/L in April 2020. The Interim Source Removal (ISR) Plan consisted of addressing the contaminant mass such that additional contaminant contribution to the surrounding soil and groundwater is minimized using Soil Vapor Extraction (SVE) technology.
An SVE system was transferred from the Hampton Cleaners (also in the Drycleaning Solvent Cleanup Program, ERIC_4713, FDEP Property No. 141948) and installed in October through December 2019 at the Westwood Cleaners facility, with start-up in December 2019. The system has been operating since December 2019. As the SVE system continues to show contaminant mass recovery, PSI recommends continuing the O&M for an additional 6 months, along with the annual groundwater monitoring.
PROPOSED SCOPE OF WORK
The proposal contained herein consists of monthly O&M events, groundwater monitoring, and one Remedial Action System Status / Groundwater Monitoring Report deliverable for the existing SVE system.
Specifically, the proposed scope of work consists of the following subtasks:
1. Project Management
This scope is provided for in the template worksheets.
2. Three Months of O&M (First Quarter)
Operations and Maintenance will be conducted on the SVE system. The work will be conducted as follows:
a. Mobilization to the site monthly.
b. Collect monthly vacuum and air flow readings from the SVE wells.
c. Collect monthly PID readings from SVE wells and system effluent.
d. Optimize system performance and recollect system readings as necessary to confirm enhanced system operation.
e. Utilize supplemental measures to help clear the SVE lines of water, if necessary.
O&M
f. Collect quarterly system air samples for influent, effluent, and select SVE wells for analyses by Method TO-15 by a National Environmental Laboratory Accreditation Conference (NELAC)- approved laboratory.
g. Document system readings in the site-specific O&M checklist; this checklist also serves as the deliverable.
The Level of Effort is detailed in Subtask 2.
3. Three Months of O&M (Second Quarter)
Operations and Maintenance will be conducted on the SVE system. The work will be conducted as follows:
a. Mobilization to the site monthly.
b. Collect monthly vacuum and air flow readings from the SVE wells.
c. Collect monthly PID readings from SVE wells and system effluent.
d. Optimize system performance and recollect system readings as necessary to confirm enhanced system operation.
e. Collect quarterly system influent and effluent for air analyses by Method TO-15 by a National Environmental Laboratory Accreditation Conference (NELAC)-approved laboratory.
f. Document system readings in the site-specific O&M checklist; this checklist also serves as the deliverable.
The Level of Effort is detailed in Subtask 3.
4. Utilities for remediation system operation
PSI used the previous utility costs from this system as well as similar equipment at other sites as a basis for the utility costs, as detailed in Level of Effort Subtask 4. We are currently running the system at 100%.
5. Annual Groundwater Sampling and Analysis
PSI will conduct groundwater sampling and analysis of the existing monitoring well network to evaluate groundwater quality at the drycleaning facility. The groundwater monitoring will consist of the following activities:
a. Mobilization to the site.
b. Collect groundwater elevation measurements of monitor wells.
c. Collect groundwater samples from the following monitor wells:
O&M
i. Shallow wells:
MW001S, MW004S, MW005S, MW006S, MW007S, MW008S, MW009S,
MW011S, MW00E.
ii. Intermediate Wells:
MW003D, MW004D, MW005D, MW006D, MW007D MW011D, MW00F.
iii. Deep Wells:
MW013DD, MW015DD, MW021DD.
d. Submit groundwater samples to a NELAC approved laboratory for analysis of
VOHs via EPA Method 8260.
e. Development of GIS tables and deliverable,
f. Development of ADaPT package deliverable.
The Level of Effort is detailed in Subtask 5.
The investigative derived waste (IDW) that will be generated during the annual groundwater monitoring is limited to purge water from the monitoring wells which will be put into the existing polytank and stored on-site.
Conclusions and recommendations will be made, which will include any modifications to the proposed annual groundwater sampling event. The report will incorporate specific recommendations and provide opinions based on professional experience in order to achieve the most efficient endpoints.
6. RASS and Groundwater Monitoring Report
A Remedial Action System Status / Groundwater Monitoring Report will be developed which will include an evaluation of the collected information and data. The report will detail and summarize the monthly O&M information, along with summary tables, figures and a graphical depiction of the system performance, as well as include current groundwater elevation maps and current groundwater quality data. Vapor sampling results will be tabulated and submitted in the report.
The report will be prepared in accordance with the Technical Worksheets or similar guidance documents, developed by the FDEP Drycleaning Solvent Cleanup Program. The report will also include the system shutdown procedures and data collected and analyzed.
Conclusions and recommendations will be made, which will include a summary of modifications made to the system to enhance the recovery rates or decrease system time to achieve targeted goals. The report will incorporate specific recommendations and provide opinions based on professional experience in order to achieve the most efficient cleanup endpoints. We understand that the Department’s goal is to achieve aggressive contaminant reduction in an efficient and cost-effective method.
O&M
The Level of Effort is detailed in Subtask 6.
COST ESTIMATE AND SCHEDULE
The estimated cost to perform the O&M, groundwater monitoring, and development of RASS / Groundwater Monitoring Report is shown on the attached Cost Estimate. All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No.
HW552, Bureau of Waste Cleanup Consolidated Services, dated December 10, 2010.
The O&M will start Dec 2020 - January 2021 with the checklists as a deliverable. Six months of O&M will continue until June 2021. Groundwater sampling will occur in April 2021 with the results incorporated into the RASS Report to be submitted at the end of July 2021.
PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075.
Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.
Michael Rothenburg, PE Nana Westmark, PG, CHMM Department Manager/ Senior Engineer Principal Consultant / Contract Manager
Enclosure: Cost Estimate Level of Effort
Z:\552-Env\FDEP BWC\05522477 Westwood Cleaners\Proposals\2020 - Oct 6 M O&M, Westwood 0552-324023.docx
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .