Document Summary
This is a Task Assignment Notification Form under DEP Contract No. HW552 issued by the Florida Department of Environmental Protection (FDEP), Bureau of Waste Cleanup Services, to Professional Service Industries, Inc. (PSI), an Intertek company. The task assignment authorizes PSI to conduct annual groundwater monitoring activities at the Rene Cleaners facility located at 2710 Blanding Boulevard, Middleburg, Clay County, Florida (FDEP Site ERIC_4266). The contract was executed in March 2021, with signatures from DEP Task Manager Killian Talley and contractor representative Nana G. Westmark. The assignment is designated as Task Assignment DC015H under Module D000 with no associated grant funding.
The scope of work consists of two subtasks: (1) project management with labor hours automatically calculated based on direct labor costs, and (2) annual groundwater sampling and analysis including installation of a temporary monitoring well, collection of groundwater elevations from ten monitoring wells, sampling of five monitoring wells for volatile organic compounds via EPA Method 8260, management of investigative derived waste (IDW), and development of a comprehensive Groundwater Monitoring Report with GIS tables and an ADaPT package deliverable. The total task assignment value is $6,165.85 on a fixed-price basis with no retainage, comprised of $470.17 for project management and $5,695.68 for groundwater sampling activities. Direct labor costs total $4,231.47 (54 hours), with additional expenses for travel ($466.00), laboratory analysis ($462.00), field equipment ($340.14), other direct costs ($78.09), and IDW disposal services ($150.00) provided by Clark Environmental. The final deliverable—a Groundwater Monitoring Report and GIS/ADaPT package—was due August 27, 2021, with completion of the task assignment through December 3, 2021.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW552
D000 N/ADC015H
Professional Service Industries, Inc. (PSI)
Nana Westmark
850-245-8928Killian Talley
ERIC_4266
Rene Cleaners
2710 Blanding Boulevard, Middleburg, Clay County
Monitoring
This Task Assignment authorizes PSI to conduct annual groundwater monitoring activities in accordance with the attached scope of work, cost estimate, and bid documentation.
Groundwater Monitoring Report; GIS/ADaPT
08/27/2021
12/03/2021
$ 6,165.85 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Killian Talley Digitally signed by Killian Talley Date: 2021.03.04 05:54:38 -05'00'
Killian Talley Digitally signed by Killian Talley Date: 2021.03.04 05:54:44 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.03.05 08:58:24 -05'00'
Nana G Westmark Digitally signed by Nana G Westmark Date: 2021.03.08 11:05:27 -05'00'
$ 6,165.85
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtasks 1-2: Groundwater Monitoring Report; GIS/ADaPT 08/27/2021
Subtasks 1-2: FDEP receipt and approval of Groundwater Monitoring Report;
GIS/ADaPT $ 6,165.85
$ 6,165.85
HW552
DC015H
Florida Department of Memorandum Environmental Protection
Printed on recycled paper.
To: HW552 Contract Negotiation File Rene Cleaners Middleburg, Clay County
ERIC_4266
From: Killian Talley, Project Manager Date: March 4, 2021 Subject: Negotiation Summary
HW552 DC015H
Task Assignment authorizes PSI to conduct annual groundwater monitoring at the Rene Cleaners site.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2: Annual Groundwater Sampling and Analysis and Report Subtask includes costs and labor for PSI to conduct groundwater sampling along with analysis and reporting. Field event will be comprised of the following activities; collection of depth to water will be measured from site monitoring wells, field parameters for geochemical data, five (5) groundwater samples for analysis of volatile organic compounds via EPA Method 8260B, and management of investigative derived waste. Upon receipt of the groundwater analytical data, PSI will generate a Groundwater Monitoring Report outlining and describing the field event, procedures, and analytical results. The report will also provide conclusion and recommendations. IDW will be transported and disposed by Clark Environmental as the lowest responsive and responsible bidder.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $6,165.85 with 54 labor hours.
PSI may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.
FDEP COST ESTI MATE
Contractor: Professional Service Industries, Inc.
Date: 3/3/2021
Task #: SUBTASK 1: Project Management SUBTASK 6:
Site: Rene Cleaners SUBTASK 2: Groundwater Sampling SUBTASK 7:
Activity/Phase: Groundwater Sampling SUBTASK 3: SUBTASK 8:
Project Manager: Nana Westmark SUBTASK 4: SUBTASK 9:
SUBTASK 5: SUBTASK 10:
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
Professional Service Industries, Inc.
$48.08 Project Manager 4 3.6 $62.50 Principal Consultant 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $52.89 Senior Engineer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $48.08 Senior Geologist, NW 6 6.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $45.20 Senior Scientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $34.62 Certified Industrial Hygientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $50.00 Certified Hazardous Materials Manager 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $50.00 Florida Licensed Asbestos Consultant 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $39.42 Project Manager 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $31.73 Project Engineer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $32.94 Project Geologist, CC 6 6.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $29.81 Project Scientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $29.81 QA Officer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $32.21 Remediation Coordinator 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0
$0.00 Professional Land Surveyor 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $0.00 Chemist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0
$24.50 GIS Specialist, DG 3 3.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $25.00 Staff Engineer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $24.04 Staff Scientist, RF 19 19.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $24.76 Staff Scientist, RH 14 13.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $24.04 Environmental Specialist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $24.04 Environmental Scientist 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $18.30 Environmental Technician 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $18.75 Administrative Assistant 2 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $15.50 Secretary 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $15.00 Senior Laborer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 $12.00 Laborer 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0
Total Hours 54 4 49.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0
Professional Service Industries, Inc.
Direct Labor $1,561.66 $173.52 $1,388.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 170.96% $2,669.81 $296.65 $2,373.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (PSI) $4,231.47 $470.17 $3,761.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $4,231.47 $470.17 $3,761.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Page 1 Rene ERIC_4266 GW 0552-336491
FDEP COST ESTI MATE
Contractor: Professional Service Industries, Inc.
Date: 3/3/2021
Task #: SUBTASK 1: Project Management SUBTASK 6:
Site: Rene Cleaners SUBTASK 2: Groundwater Sampling SUBTASK 7:
Activity/Phase: Groundwater Sampling SUBTASK 3: SUBTASK 8:
Project Manager: Nana Westmark SUBTASK 4: SUBTASK 9:
SUBTASK 5: SUBTASK 10:
Totals 1 2 3 4 5 6 7 8 9 10
Other Direct Costs $78.09 $8.68 $69.41 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $272.00 $272.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $466.00 $466.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling, Conventional $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling, Non-Conventional $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drum $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $462.00 $462.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $462.00 $462.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $58.20 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $249.44 $249.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $340.14 $340.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $5,742.70 $478.85 $5,263.85 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $423.15 $47.02 $376.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,165.85 $525.87 $5,639.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Page 2 Rene ERIC_4266 GW 0552-336491
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Rene Cleaners SUBTASK 2: Groundwater Sampling
DATE: 3/3/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Activities Senior Geologist, N Westmark Develop cost estimate and level of effort, obtain bids 3
Profiling, Manifest for IDW 1
Staff Scientist, R Fetter Load / unload 1 Travel (1 round trip) 6.5 Collect groundwater elevations (10 wells) (10 minutes per well) 2 Collect groundwater samples 4 shallow wells @ 1 hour per well 4 1 intermediate wells @ 1.5 hour per well 1.5
Staff Scientist, Robert Hanson Load / unload 1
Travel (1 round trip) 6.5 Install temporary well 3 Abandon temporary well/ patch concrete 1 Pick up / drop off sample kits 2
13.5 Report
Project Geologist (C Cummins) Data reduction / evaluation, prepare report 6
Staff Scientist, R Fetter Prepare tables and draft maps 4
GIS / CADD Specialist, D Grove Create maps, figures 3
Senior Geologist, N Westmark Report Review, sign and seal 2
Administrative Assistance, B Meynardie Compile document, obtain invoice proof of payment 2
TOTAL LABOR 49.5
EQUIPMENT ITEM RATE COSTING UNIUSEAGE TOTALS
55-gallon drum $58.20 each 1 $58.20
Shallow groundwater sampling kit $208.55 day 1 $208.55
PVC well screen, 2 inch 5 ft screen, 10 or 20 slot $22.00 each 1 $22.00 PVC casing, 5 ft lengths for riser $15.00 each 0 $0.00 2 in PVC cap $8.00 each 1 $8.00 2 inch PVC SCH 40 coupling $1.14 each 1 $1.14 concrete mix, 80 lb $4.65 each 1 $4.65 2 inch orange locking plug $4.95 each 0 $0.00 sand, silica 20-30 $5.10 each 1 $5.10
$249.44 Expendables $32.50 day 1 $32.50
TOTAL EQUIPMENT $340.14
VEHICLE TYPE RATE UNIT USEAGE
Equipment Van / Truck $97.00 day 2 $194.00
TOTAL VEHICLE $194.00
PER DIEM STAFF RATE UNIT USEAGE
Staff Scientist, Ryan Fetter lodging $100.00 day 1 $100.00 meals $36.00 day 1 $36.00
Staff Scientist, Robert Hanson lodging $100.00 day 1 $100.00 meals $36.00 day 1 $36.00
TOTAL PER DIEM $272.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC IDW
EPA Method 8260, GC / MS groundwater $66.00 5 1 1 $462.00
TOTAL LAB $462.00
SUBCONTRACTOR COSTS
NAME PURPOSE UNIT COST
Clark Environmental IDW drum & pickup 1 $150.00 $150.00
TOTAL $150.00
Page 4 Rene ERIC_4266 GW 0552-336491
PSI Proposal Number: 0552-336491 March 3, 2021
Professional Service Industries, Inc.
5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634
Phone: (813) 886-1075 Fax: (813) 249-4916 www.intertek.com/building
Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Attention: Mr. Killian Talley, Environmental Specialist III Phone: (850) 245-8705 Email: Killian.Talley@FloridaDEP.gov
Re: Proposal for Annual Groundwater Monitoring Rene Cleaners 2710 Blanding Boulevard Middleburg, Clay County, Florida FDEP Facility ID No. 10 9502097 / ERIC_4266
Dear Mr. Talley:
Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to provide temporary monitoring well installation and annual groundwater monitoring for the Rene Cleaners at 2710 Blanding Boulevard, Middleburg, Florida. Included with this proposal is a discussion of project history to date, proposed scope of work, cost estimate and a proposed schedule for completion.
PROJECT BACKGROUND
The Rene Drycleaner, located in a strip mall, began drycleaning operations in January 1988. The site was accepted into the Drycleaning Solvent Cleanup Program based on a soil sample with PCE at 2100 micrograms per kilogram (µg/kg). The site is currently a drop-off facility but the drycleaning equipment remains.
According to the site assessment, the site lithology consists of interspersed lenses of sand and clay, with a layer of stiff clay at 24 to 50 feet bls. The assessment also revealed that no contaminants of concern were identified below 24 feet below land surface (bls).
A Remedial Action Plan for short term Dual Phase Extraction (DPE) was implemented in May through June 2001. The DPE was evaluated as ineffective due to short-circuiting of the system believed to be the result of a severely cracked surface seal. In March 2002, a source removal near the sewer line was conducted. During the annual groundwater monitoring, a Modified Active Gas Sampling (MAGS) event was performed which identified residual PCE beneath the facility.
mailto:Killian.Talley@FloridaDEP.gov
PSI Proposal 0552-336491 FDEP – Rene Cleaners
Although a short-term soil treatment strategy was recommended, additional remediation has not been performed at the site.
Groundwater monitoring has occurred in 2011, 2012, 2013, 2014 and 2017 with results indicating no VOH compounds present at concentrations exceeding GCTL criteria.
In October 2014, soil sampling was also performed to evaluate if the site soil had achieved Soil Cleanup Target Levels (SCTLs) and could be closed. Four soil samples were collected and analyzed near previous locations where elevated concentrations of VOH compounds were detected. One soil sample (SB015, 1 ft.) beneath the former dryclean machine exhibited elevated PCE concentrations with an SPLP sample also above Leachability criteria.
In 2018, PSI installed a temporary monitoring well (MW013) inside Rene Cleaners and adjacent to the former dryclean machine. MW013 was subsequently sampled along with monitoring wells MW003R, MW005 and DMW009R as part of the annual groundwater monitoring program.
Analytical results from MW003R, MW005 and DMW009R indicated no VOHs above GCTL criteria.
However, PCE, TCE and vinyl chloride were present in MW013 at 5.6 ug/L, 12 ug/L and 1.6 ug/L, respectively, above the GCTL criteria.
In 2020, another temporary monitoring well was installed near the former dryclean machine which revealed vinyl chloride at 1.7 ug/L in MW013R. Based on these results, the site will not qualify for a clean closure. The Department may wish to negotiate a conditional closure with the property owner, but until that time, we recommend continuing with groundwater monitoring at the Rene Cleaners.
PROPOSED SCOPE OF WORK
The proposal contained herein consists of conducting groundwater sampling and analysis, along with a report deliverable. The results will be used to confirm current groundwater quality conditions. Specifically, the proposed scope of work consists of the following subtasks:
1. Project Management
This scope is provided for in the Level of Efforts sheets.
2. Annual Groundwater Sampling and Analysis
a. Mobilization to the site.
b. Install a temporary well at the former MW013 location.
c. Collect groundwater elevation measurements of ten monitoring wells (MW001, MW002, MW003R, MW005, MW008, DMW009R, DMW010, MW011, MW012 and MW013).
PSI Proposal 0552-336491 FDEP – Rene Cleaners
d. Collect groundwater samples from five monitoring wells: shallow wells MW001, MW003R and MW005, the proposed temporary well, and deep well DMW009R.
The groundwater samples will be analyzed by EPA Method 8260 for Volatile Organic Halocarbons (VOHs) by a laboratory in accordance with protocols approved by the National Environmental Laboratory Accreditation Laboratory Conference (NELAC).
e. The decontamination fluids, soil cuttings and other associated investigative derived waste will be stored in 55-gallon drums, labeled and transported off-site to an approved facility for disposal and treatment.
f. Development of GIS tables and deliverable,
g. Development of an ADaPT package deliverable.
h. Development of a Groundwater Monitoring Report which will include current groundwater elevation maps, current groundwater quality data, and recommendations, as necessary.
COST ESTIMATE AND SCHEDULE
The estimated cost to perform the above described services is shown on the attached Cost Estimate and Level of Effort sheets. All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No. HW552, Bureau of Waste Cleanup Services, dated December 10, 2010. Depending on site access, well installation and groundwater sampling and analysis can be completed at the end of June 2021. The letter report will be submitted by end of August 2021.
PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075.
Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.
Erin Lennox Nana G. Westmark, PG, CHMM Project Scientist Principal Consultant/Contract Manager
Enclosure: Cost Estimate Level of Effort
Z:\552-Env\FDEP BWC\0552620 Rene, Clay County\PSI Proposal\2021 GW\Rene ERIC_4266 GW 0552-336491.docx
PSI - Intertek Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment
PROJECT BID TABULATIONS IDW
Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various
Description of Service
Tampa Area Orlando - Central
Florida Jacksonville Area, North Florida
South Florida (Miami, Fort Myers, Naples) Panhandle water $90.00 $90.00 $100.00 $100.00 $110.00 soil $110.00 $110.00 $120.00 $120.00 $130.00 low volume fee if< 6 drums +$50 if< 6 drums +$50 if< 6 drums +$50 if< 6 drums +$50 if< 6 drums +$200 Pick-up fee NA NA NA NA NA Total Per One Drum Water $140.00 $140.00 $150.00 $150.00 310.00$ Total Per One Drum Soil $160.00 $160.00 $170.00 $170.00 330.00$
Plus $150 per day / per diem water $115.00 $115.00 Non service area Non service area Non service area soil $150.00 $150.00 Non service area Non service area Non service area water $92.00 $92.00 $92.00 $92.00 $92.00 soil $67.00 $67.00 $67.00 $67.00 $67.00 low volume fee if 3 drums or less add $35 if 3 drums or less add $45 if 3 drums or less add $55 if 3 drums or less add $55 if 10 drums or less add $450
Pick-up Fee 30 40 50 50 95.00$ Total Per One Drum Water $157.00 $177.00 $197.00 $197.00 637.00$ Total Per One Drum Soil $132.00 $152.00 $172.00 $172.00 612.00$
Plus $150 per day / per diem
* = DOT shippable drums on hard concrete or asphalt surface easily accessible with tractor trailer with no dirt, grass or curbs to get drums to tailgate of truck ** = Need TCLPs for VOHS for soils, Totals only for VOHSs for water 100% liquids.
1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.
2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste
5. ) Waste is considered not hazardous.
6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.
7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.
55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.
State of Florida
3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.
The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.
4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Bureau of Waste Cleanup,Hazardous Waste Cleanup Section.
Petrotech Southeast, Inc.
Clark Environmental, Inc. * and **
NRC / US Ecology(formerly SWS)
Page 1 of 1 PSI IDW Bids 1-31-2020
PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment
PROJECT BID TABULATIONS IDW
Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various
Description of Service
Tampa Area Orlando - Central
Florida Jacksonville Area, North Florida
South Florida (Miami, Fort
Myers, Naples) Panhandle water soil low volume fee Pick-up fee
$0.00 $0.00 $0.00 $0.00 $0.00
1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.
2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste
5. ) Waste is considered not hazardous.
6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.
7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.
Description 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.
State of Florida
3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.
The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.
4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Bureau of Waste Cleanup,Hazardous Waste Cleanup Section.
$115.00 $150.00
$115.00 $150.00
Petrotech Southeast, Inc.
Phone: 407 - 656-8114 Fax: 407 - 358-5030 Natacha Mitchell-Jackson
Quote # TP02077
US Ecology Waste (IDW) IDW Pick-up, Transport & Disposal Services
Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida
Description of Service
State of Florida
Description
Tampa Area
Orlando - Central
Florida
Jacksonville Area, North Florida
South Florida (Miami, Fort
Myers, Naples)
Panhandle 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.
water soil low volume fee Pick-up fee
$0.00 $0.00 $0.00 $0.00 $0.00
1. Drums must be in DOT Shippable containers before being transported.
2. Pricing does not include over-packing Non-DOT shippable containers (drums).
3. Disposal pricing offered is based on the non-hazardous waste being containerized in 55/Gal drums. 15/Gal, 30/Gal, 85/Gal & 95/Gal containers are not included.
4. All waste must be profiled and acknowledged by Intertek PSI as well as providing signed waste manifests for each site.
5. Pricing for waste is upon disposal facility acceptance. Off-spec charges and/or surcharges will be priced accordingly.
6. All waste pickups will be scheduled during normal business hours, Monday - Friday. Nights, weekends and holidays are not included
7. The Panhandle pricing will apply to drum pickups in the Florida Keys.
Intertek PSI Representative
$92.00 $67.00 $67.00
$92.00 $67.00 $92.00 $92.00
$67.00 $67.00 $92.00
$95.00 $450 / 10 Drums or Less35 / 3 Drums or Less
$30.00 $40.00 $45 / 3 Drums or Less
$50.00 $55/ 3 Drums or Less
$50.00 $55/ 3 Drums or Less
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .