CN-370000-HW552-DC004T.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW552|ef466f80f8dde60f2e51068b7f870c80
Contract number
HW552
Issued by
Florida

About this file

Task Assignment for Groundwater Remedial Action Plan Implementation

This document is a Task Assignment Notification Form under Florida Department of Environmental Protection (FDEP) Contract No. HW552, issued to Professional Service Industries, Inc. (PSI), an Intertek company. The task assignment authorizes PSI to oversee and conduct injection-based remediation activities at the Tempo Cleaners facility located at 233 Oxford Road, Fern Park, Seminole County, Florida (FDEP Site ID: ERIC_5476). The project involves the implementation of the approved Remedial Action Plan Modification to address perchloroethene (PCE) contamination in groundwater at this former drycleaning operation site.

The scope of work consists of six subtasks: project management, pre-injection activities, baseline groundwater monitoring, in situ chemical injection using EHC-L (zero valent iron) and KB-1® Plus bioaugmentation cultures, post-injection performance monitoring over two quarters, and preparation of an Injection Completion Report. The total contract value is $117,066.41 on a fixed-price basis with zero retainage, covering 433 labor hours. PSI selected Cascade Remediation Services as the injection subcontractor ($32,800.00), PeroxyChem for injection chemicals ($9,092.83), SiREM for bioaugmentation cultures and testing ($11,258.00), Petrotech Southeast for investigative derived waste disposal ($2,245.00 for five days of activities), and Sunbelt Rentals for equipment rental ($625.70 for a forklift). Deliverables include baseline sampling field notes due September 24, 2021; injection and performance monitoring field notes due December 3, 2021; and the final Injection Completion Report due April 30, 2022, with payment contingent upon FDEP receipt and approval of each milestone.

View the file

Other files

File Type Posted
CN-370000-HW552-A2.pdf PDF
CN-370000-HW552-CO1.pdf PDF
CN-370000-HW552-CO3.pdf PDF
CN-370000-HW552-CO4.pdf PDF
CN-370000-HW552-DC004N.pdf PDF
CN-370000-HW552-DC009M.pdf PDF
CN-370000-HW552-DC009O.pdf PDF
CN-370000-HW552-DC010I.pdf PDF
CN-370000-HW552-DC013I.pdf PDF
CN-370000-HW552-DC014H.pdf PDF
CN-370000-HW552-DC014I.pdf PDF
CN-370000-HW552-DC014J.pdf PDF
CN-370000-HW552-DC018V.pdf PDF
CN-370000-HW552-DC019G.pdf PDF
CN-370000-HW552-DC01A.pdf PDF
CN-370000-HW552-DC01ACO5.pdf PDF
CN-370000-HW552-DC01ACO6.pdf PDF
CN-370000-HW552-DC01ACO7.pdf PDF
CN-370000-HW552-DC01C.pdf PDF
CN-370000-HW552-DC01E.pdf PDF
CN-370000-HW552-DC01F.pdf PDF
CN-370000-HW552-DC01I.pdf PDF
CN-370000-HW552-DC020E.pdf PDF
CN-370000-HW552-DC020i.pdf PDF
CN-370000-HW552-DC023F.pdf PDF
CN-370000-HW552-DC023L.pdf PDF
CN-370000-HW552-DC023P.pdf PDF
CN-370000-HW552-DC028D.pdf PDF
CN-370000-HW552-DC02E.pdf PDF
CN-370000-HW552-DC02F.pdf PDF
CN-370000-HW552-DC031A.pdf PDF
CN-370000-HW552-DC031BCO.pdf PDF
CN-370000-HW552-DC032B.pdf PDF
CN-370000-HW552-DC037E.pdf PDF
CN-370000-HW552-DC03DCO3.pdf PDF
CN-370000-HW552-DC03DCO4.pdf PDF
CN-370000-HW552-DC03F.pdf PDF
CN-370000-HW552-DC03G.pdf PDF
CN-370000-HW552-DC03I.pdf PDF
CN-370000-HW552-DC04C.pdf PDF
CN-370000-HW552-DC04E.pdf PDF
CN-370000-HW552-DC04F.pdf PDF
CN-370000-HW552-DC04J.pdf PDF
CN-370000-HW552-DC04JCO1.pdf PDF
CN-370000-HW552-DC04KCO1.pdf PDF
CN-370000-HW552-DC04L.pdf PDF
CN-370000-HW552-DC04R.pdf PDF
CN-370000-HW552-DC04RCO2.pdf PDF
CN-370000-HW552-DC04S.pdf PDF
CN-370000-HW552-DC05ACO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW552

D000 N/ADC004T

Professional Service Industries, Inc. (PSI)

Nana Westmark

850-245-8928Killian Talley

ERIC_5476

Tempo Cleaners

233 Oxford Road, Fern Park, Seminole County

Construction

This Task Assignment authorizes PSI to oversee and conduct activities for injection based remediation at the Tempo Cleaners site in in accordance with the approved Remedial Action Plan Modification and attached scope of work, cost estimate, and bid documentation.

Injection Completion Report

04/30/2022

05/27/2022

$ 117,066.41 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Killian Talley Digitally signed by Killian Talley Date: 2021.06.24 14:53:45 -04'00'

Killian Talley Digitally signed by Killian Talley Date: 2021.06.24 14:53:50 -04'00'

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2021.06.24 21:21:56 -04'00'

Nana Westmark Digitally signed by Nana Westmark Date: 2021.06.25 15:19:23 -04'00'

$ 117,066.41

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2-3: Submittal of baseline sampling field event notes 09/24/2021

Subtasks 4-5: Submittal of injection and performance monitoring field notes 12/03/2021

Subtasks 1&6: Submittal of Injection Completion Report 04/30/2022

Subtasks 2-3: FDEP receipt and approval of baseline sampling field event notes $ 11,185.82

Subtasks 4-5: FDEP receipt and approval of Injection and performance monitoring field notes $ 93,543.30

Subtasks 1&6: FDEP receipt and approval of Injection Completion Report $ 12,337.29

$ 117,066.41

HW552

DC004T

Florida Department of Memorandum Environmental Protection

To: HW552 Contract Negotiation File

Tempo Cleaners Fern Park, Seminole County

ERIC_5476

From: Killian Talley, Project Manager Date: June 24, 2021 Subject: Negotiation Summary

HW552 DC004T

Task Assignment HW550 DC004T authorizes PSI to oversee and complete an injection event at the Tempo Cleaners site.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Pre-Injection Subtask authorizes labor and related costs for pre-inject activities including coordination with property owner, permitting, set up for field activities, and update health and safety as necessary.

Subtask 3: Baseline Monitoring Sub task authorizes labor and related costs for baseline sampling of the site. Depth to water for site wells will occur along with sampling for VOHs using EPA Method 8260B by a fixed-base laboratory. Certain samples will also be taken for total organic carbon, total dissolved solids, iron, and sodium in accordance with the performance monitoring plan. PSI will discuss results of sampling with the Department prior to further injection activities.

Subtask 4: Injection Subtask authorizes labor and related costs for injection activities. Solution will be mixed with 40,500 gallons of potable water before injection into the 8 injection wells. Along with injection of solution into site, 2-liters of KB-1® Plus culture and 1 liter of KB-1® Primer will be injected into the wells for bioaugmentation purposes. Support for injection will be provided by Cascade who has been selected as injection subcontractor following discussions with the FDEP based upon concerns with injection pressures and subcontractor’s experience with injecting the amendment.

Subtask 5: Performance Monitoring This subtask includes labor and related costs for performance monitoring. Groundwater samples will be analyzed by a fixed-based lab for underground injection control parameters and VOHs as summarized in the Remedial Action Plan Modification. Supplemental monitoring parameters include testing for Dehalococcoides population and volatile fatty acids to help quantify remedial action efficacy.

Tempo Cleaners Page Two

Subtask 6: Evaluation, Reporting Subtask includes labor for PSI to develop an Injection Completion Report including preparation and review of report, figures, as-builts, updated tables, and sign and seal of report. Report will include describing the field event, procedures, and analytical results. The report will also provide conclusion and recommendations.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost for this Task Assignment Change Order is $117,066.41 with 433 labor hours.

PSI may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTI MATEContractor: Professional Service Industries, Inc.

Date: 0/26/2020 Rev June 24, 2021

Task #: SUBTASK 1: Project Management SUBTASK 6: Evaluation, Reporting

Site: Tempo RAP Implementati SUBTASK 2: Pre-Injection SUBTASK 7:

Activity/Phase: SUBTASK 3: Baseline Monitoring SUBTASK 8:

Project Manager: Nana Westmark SUBTASK 4: Injection SUBTASK 9:

SUBTASK 5: Performance Monitoring SUBTASK 10:

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

Professional Service Industries, Inc.

$48.08 Project Manager 33 32.5 $62.50 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $52.89 Senior Engineer, MR 26 0 0 16 0 10 0 0 0 0 $48.08 Senior Geologist, NW 27 17 2 0 8 0 0 0 0 0 $45.67 Senior Scientist 0 0 0 0 0 0 0 0 0 0 $34.62 Certified Industrial Hygientist 0 0 0 0 0 0 0 0 0 0 $56.50 Certified Hazardous Materials Manager 0 0 0 0 0 0 0 0 0 0 $50.00 Florida Licensed Asbestos Consultant 0 0 0 0 0 0 0 0 0 0 $48.08 Project Manager 0 0 0 0 0 0 0 0 0 0 $31.73 Project Engineer, MM 159 14 0 71 22 52 0 0 0 0 $32.94 Project Geologist, CC 16 0 16 0 0 0 0 0 0 0 $29.81 Project Scientist, RF 0 0 0 0 0 0 0 0 0 0 $29.81 QA Officer 0 0 0 0 0 0 0 0 0 0 $32.21 Remediation Coordinator 0 0 0 0 0 0 0 0 0 0

$0.00 Professional Land Surveyor 0 0 0 0 0 0 0 0 0 0 $0.00 Chemist 0 0 0 0 0 0 0 0 0 0

$24.50 GIS Specialist, DG 28 0 4 4 8 12 0 0 0 0 $25.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0 $24.04 Staff Scientist, RF 0 0 0 0 0 0 0 0 0 0 $24.76 Staff Scientist, RH 142 0 24 57 61 0 0 0 0 0 $24.04 Environmental Specialist 0 0 0 0 0 0 0 0 0 0 $24.04 Environmental Scientist 0 0 0 0 0 0 0 0 0 0 $18.30 Environmental Technician, RR 0 0 0 0 0 0 0 0 0 0 $18.75 Administrative Assistant 2 0 0 0 0 2 0 0 0 0 $15.50 Secretary 0 0 0 0 0 0 0 0 0 0 $15.00 Senior Laborer 0 0 0 0 0 0 0 0 0 0 $12.00 Laborer 0 0 0 0 0 0 0 0 0 0

Total Hours 433 33 31 46 148 99 76 0 0 0 0

Professional Service Industries, Inc.

Direct Labor $14,045.43 $1,560.60 $1,261.58 $1,315.44 $4,608.39 $2,789.06 $2,510.36 $0.00 $0.00 $0.00 $0.00

Overhead 170.96% $24,012.07 $2,668.00 $2,156.80 $2,248.88 $7,878.50 $4,768.18 $4,291.71 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (PSI) $38,057.50 $4,228.60 $3,418.38 $3,564.32 $12,486.89 $7,557.24 $6,802.07 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $702.27 $78.03 $63.08 $65.77 $230.42 $139.45 $125.52 $0.00 $0.00 $0.00 $0.00

RAP Implementation - Injection

REV: 02/03 CEF_PSI.XLS Page 1

FDEP COST ESTI MATEContractor: Professional Service Industries, Inc.

Date: 0/26/2020 Rev June 24, 2021

Task #: SUBTASK 1: Project Management SUBTASK 6: Evaluation, Reporting

Site: Tempo RAP Implementati SUBTASK 2: Pre-Injection SUBTASK 7:

Activity/Phase: SUBTASK 3: Baseline Monitoring SUBTASK 8:

Project Manager: Nana Westmark SUBTASK 4: Injection SUBTASK 9:

SUBTASK 5: Performance Monitoring SUBTASK 10:

Totals 1 2 3 4 5 6 7 8 9 10

RAP Implementation - Injection

Travel Vehicle Rental $1,713.00 $0.00 $194.00 $1,034.00 $485.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $2,025.00 $0.00 $675.00 $1,350.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $3,738.00 $0.00 $869.00 $2,384.00 $485.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling, (Unconventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying / GPR $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $2,475.00 $0.00 $115.00 $2,245.00 $115.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Injection Chemicals $21,282.47 $0.00 $0.00 $21,282.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Injection Services $32,800.00 $0.00 $0.00 $32,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment $625.70 $0.00 $0.00 $625.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $57,183.17 $0.00 $115.00 $56,953.17 $115.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $5,718.32 $0.00 $11.50 $5,695.32 $11.50 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $62,901.49 $0.00 $126.50 $62,648.49 $126.50 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $3,685.00 $0.00 $1,491.00 $0.00 $2,194.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $3,685.00 $0.00 $1,491.00 $0.00 $2,194.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $422.50 $0.00 $65.00 $195.00 $162.50 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $174.60 $0.00 $58.20 $0.00 $116.40 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $3,579.30 $0.00 $766.30 $1,770.25 $1,042.75 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $4,176.40 $0.00 $889.50 $1,965.25 $1,321.65 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $113,260.66 $4,306.63 $3,481.46 $7,006.09 $79,715.05 $11,823.84 $6,927.59 $0.00 $0.00 $0.00 $0.00 Completion Fee $3,805.75 $422.86 $341.84 $356.43 $1,248.69 $755.72 $680.21 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $117,066.41 $4,729.49 $3,823.30 $7,362.52 $80,963.74 $12,579.56 $7,607.80 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF_PSI.XLS Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Tempo RAP Implementation SUBTASK 2: Pre-Injection DATE: 10/26/2020 Rev June 24, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist, N Westmark Develop Cost Estimate and Level of Effort 9 Solicit bids from subcontractors 8

Project Engineer, M Mui Update HASP 1

Coordinate access 2 Evaluate water availability (hydrant, wells, etc) 4 Tenant and Owner notification, schedule 2 Order injection materials 3 Schedule well injections 2

TOTAL LABOR 31.0

EQUIPMENT ITEM RATE UNIT USAGE TOTALS

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM -$

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE

$0.00

TOTAL SUBCONTRACTOR $0.00

Page 3 HW552_DC004T_CEFLOE

SUBTASK 3: Baseline Monitoring DATE: 10/26/2020 Rev June 24, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist, NW Technical oversight 2

Staff Scientist, R Hanson Load / Unload 1 Travel (1 roundtrips for gw sampling) 4 Collect groundwater elevations (14 wells) (10 minutes per well) 2.5 Collect groundwater samples 1 shallow wells @ 1 hour each 1 7 intermediate wells @ 1.5 hours each 10.5 1 deep wells @ 2 hrs each 2 Documentation of groundwater sampling & measurements 1 Pickup / drop off samples 2

Project Geologist, C Cummins Data reduction/evaluation 5

Preparation of field deliverable of monitoring 6 Prrepare ADaPT package 3 Report - Prepare tables and figures 2

GIS/CADD Specialist, D Grove Create figures 4

TOTAL LABOR 46.0

EQUIPMENT ITEM RATE UNIT USAGE TOTALS

Shallow Groundwater Sampling Kit $208.55 day 2 $417.10 Deep Groundwater Sampling Kit $349.20 day 1 $349.20 Drum for IDW $58.20 each 1 $58.20

$766.30 Expendables $32.50 day 2 $65.00

TOTAL EQUIPMENT $889.50

VEHICLE TYPE RATE UNIT USAGE

Equipment Van / Truck (staff scientist) $97.00 day 2 $194.00

TOTAL VEHICLE $194.00

PER DIEM STAFF RATE UNIT USAGE

Lodging, (Staff Scientist) $99.00 2 $495.00 Meals, (Staff Scientist) $36.00 2 $180.00

TOTAL PER DIEM $675.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs by EPA Method 8260 $66.00 2 1 $198.00 Iron $11.50 2 0 $23.00 Sodium $11.50 2 $23.00 Total Dissolved Solids $11.50 2 $23.00 Total Organic Carbon $26.00 4 $104.00 Methane, Ethane, Ethene $160.00 7 $1,120.00 Gene-Trac® FGA/Dhc Included in SiREM scope 3 $0.00

TOTAL LAB $1,491.00

SUBCONTRACTOR COSTS

NAME PURPOSE Units

Petrotech Southeast IDW transport and dispos $115.00 1 $115.00

TOTAL $115.00

Page 4 HW552_DC004T_CEFLOE

SUBTASK 4: Injection DATE: 10/26/2020 Rev June 24, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Remediation Injection Senior Engineer M Rothenburg Provide technical oversight 8

Updates to FDEP 3

Project Engineer, M Mui Project review prior to mobilization 3 Travel (1 roundtrip) 4 On-site injection activities 50 Documentation of injection procedures 8

Staff Scientist, R Hanson Load / Unload 1 Travel (1 roundtrip) 4 Assist with material receipt 2 On-site injection activities 50

Field Deliverable

Senior Engineer M Rothenburg Review of field deliverable 5

Project Engineer, M Mui Prepare field deliverable 6 GIS/CADD Specialist, DG Create and prepare figures 4

TOTAL LABOR 148.0

EQUIPMENT ITEM RATE UNIT USAGE TOTALS

Construction/O&M/Pilot Test Kit $291.00 day 1 $291.00 $1,164.00 week 1 $1,164.00

Construction/O&M supplies $63.05 day 1 $63.05 $252.20 week 1 $252.20

Expendables $32.50 day 6 $195.00

TOTAL EQUIPMENT $1,965.25

VEHICLE TYPE RATE UNIT USAGE

Equipment Van / Truck (Project Engineer) $97.00 day 1 $97.00 $420.00 week 1 $420.00

Equipment Van / Truck (staff scientist) $97.00 day 1 $97.00 $420.00 week 1 $420.00

TOTAL VEHICLE $1,034.00

PER DIEM STAFF RATE UNIT USAGE

Lodging, (Project Engineer) $99.00 5 $495.00 Meals, (Project Engineer) $36.00 5 $180.00 Lodging, (Staff Scientist) $99.00 5 $495.00 Meals, (Staff Scientist) $36.00 5 $180.00

TOTAL PER DIEM $1,350.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE Rate USE

Injection Chemicals PeroxyChem EHC Liquid, ELS Concentrate, KHCO3 $9,092.83 1 $9,092.83 SiREM KB-1 Plus, KB-1 Primer $11,258.00 1 $11,258.00 Sodium Ascorbate Bulk Apothecary' $931.64 1 $931.64

$21,282.47 Injection Activities Cascade Injection services $32,800.00 1 $32,800.00

Equipment Rental Forklift Sunbelt Rental $625.70 1 $625.70

IDW

PetroTech Southeast transport, disposal IDW soil, per 55-gal drum $150.00 5 $750.00 water, per 55-gal drum $115.00 13 $1,495.00

$2,245.00

TOTAL $56,953.17

Page 5 HW552_DC004T_CEFLOE

SUBTASK 5: Performance Monitoring DATE: 10/26/2020 Rev June 24, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist, NW Provide technical support for performance monitoring 8 4 hours per quarter

Month 1 Staff Scientist, RH Load / Unload 1

Travel (1 roundtrip for gw sampling) 4 Collect groundwater elevations (4 wells) (10 minutes per well) 0.5 Collect groundwater samples 1 shallow well @ 1 hour each 1 3 intermediate wells @ 1.5 hours each 4.5 Documentation of groundwater sampling & measurements 1 Pickup / drop off samples 2

Quarter 1 Staff Scientist, RH Load / Unload 1

Travel (2 roundtrips for gw sampling) 8 Collect groundwater elevations (8 wells) (10 minutes per well) 1.5 Collect groundwater samples 1 shallow well @ 1 hour each 1 7 intermediate wells @ 1.5 hours each 10.5 Documentation of groundwater sampling & measurements 1 Pickup / drop off samples 2

Quarter 2 Staff Scientist, RH Load / Unload 1

Travel (2 roundtrips for gw sampling) 8 Collect groundwater elevations (6 wells) (10 minutes per well) 1 Collect groundwater samples 1 shallow well @ 1 hour each 1 5 intermediate wells @ 1.5 hours each 7.5 Documentation of groundwater sampling & measurements 1 Pickup / drop off samples 2

21.5 60.5

Qtrly Evaluation and Reporting Project Engineer, MM Data reduction/evaluation 8

Preparation of report 6 Prepare ADaPT package 4 Report - Prepare tables and figures 4

GIS/CADD Specialist, D Grove Create quarterly figures 8

TOTAL LABOR 99

Page 6 HW552_DC004T_CEFLOE

SUBTASK 5: Performance Monitoring DATE: 10/26/2020 Rev June 24, 2021

EQUIPMENT ITEM RATE UNIT USAGE TOTALS

Month 1 Shallow Groundwater Sampling Kit $208.55 day 1 $208.55 Expendables $32.50 day 1 $32.50 Drum $58.20 each 2 $116.40

Quarter 1 Shallow Groundwater Sampling Kit $208.55 day 2 $417.10 Expendables $32.50 day 2 $65.00

Quarter 2 Shallow Groundwater Sampling Kit $208.55 day 2 $417.10 Expendables $32.50 day 2 $65.00

$1,042.75 $162.50

TOTAL EQUIPMENT $1,321.65

VEHICLE STAFF RATE UNIT USAGE

Month 1 Equipment Van / Truck $97.00 day 1 $97.00

Quarter 1 Equipment Van / Truck $97.00 day 2 $194.00

Quarter 2 Equipment Van / Truck $97.00 day 2 $194.00

TOTAL VEHICLE $485.00

PER DIEM STAFF RATE UNIT USAGE

$0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Month 1 Total Organic Carbon $26.00 4 0 $104.00

Quarter 1 Iron $11.50 4 $46.00 Sodium $11.50 4 $46.00 Total Dissolved Solids $11.50 4 $46.00 Total Organic Carbon $26.00 8 $208.00 Methane, Ethane, Ethene $160.00 7 $1,120.00 Gene-Trac® FGA/Dhc Included in SiREM scope 3 $0.00 Volatile fatty acids (VFAs) Included in SiREM scope 3 $0.00

Quarter 2 VOHs by EPA Method 8260 $66.00 4 1 $330.00 Iron $11.50 4 $46.00 Sodium $11.50 4 $46.00 Total Dissolved Solids $11.50 4 $46.00 Total Organic Carbon $26.00 6 $156.00 Gene-Trac® FGA/Dhc Included in SiREM scope 3 $0.00 Volatile fatty acids (VFAs) Included in SiREM scope 3 $0.00

TOTAL LAB $2,194.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Petrotech Southeast $115.00 1 $115.00

TOTAL $0.00

IDW transport & disposal

Page 7 HW552_DC004T_CEFLOE

SUBTASK 6: Evaluation, Reporting DATE: 10/26/2020 Rev June 24, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer MR Review Tables 2 Review Figures 2 Sign and seal documents 1 Evaluate data 5

Project Engineer, MM Prepare tables and draft maps 12 Summarize injection event 16 Data Reduction / evaluation 16 Prepare summary tables 8

GIS/CADD Specialist, DG Create and prepare figures 12

Administrative Assistance Compile report 2

TOTAL LABOR 76.0

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

Page 8 HW552_DC004T_CEFLOE

PSI Proposal Number: 0552- 325594-Rev 1 October 26, 2020, Revised June 24, 2021 www.intertek.com/building

Professional Service Industries, Inc.

5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634 Phone: (813) 886-1075

Fax: (813) 249-4916

Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400

Attn: Mr. Killian Talley, Environmental Specialist III

Contract Manager Telephone: (850) 245-8705 Email: Killian.Talley@FloridaDEP.gov

Re: Proposal – Groundwater Remedial Action Plan Implementation – Revision 1

Tempo Dry Cleaners 233 Oxford Road Fern Park, Seminole County, Florida FDEP Facility ID No. ERIC_5476

Dear Mr. Talley:

Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to implement the Remedial Action Plan Modification – Revision 4 to address impacted groundwater at the Tempo Dry Cleaners in Fern Park, Seminole County, Florida. Included with this proposal is the project history to date, proposed scope of work, cost estimate and a proposed schedule for completion.

PROJECT BACKGROUND

Drycleaning operations at the Tempo Dry Cleaners began in January 1978 and utilized perchloroethene (PCE). In November 1994, a 150-gallon aboveground storage tank (AST) containing PCE was reportedly tipped over. On or prior to November 30, an area approximately 4 feet by 4 feet was excavated, in an attempt to remove the contaminated soil associated with the AST discharge. The excavated soil was later used as backfill. A soil sample collected from the former excavation area had a PCE concentration of 49,000,000 milligrams per kilogram (mg/kg).

In May 1995, the PCE drycleaning operations ceased at Tempo, and the business was sold and converted to a dry drop-off as documented by a FDEP inspection in March 1997. The drycleaner was accepted into the Drycleaning Solvent Cleanup Program in June 1998, and assessment activities conducted by WRS commenced in October 2002.

mailto:Killian.Talley@FloridaDEP.gov mailto:Killian.Talley@FloridaDEP.gov

Tempo Dry Cleaners, RAP Implementation

October 26, 2020, revised June 24, 2021

In February 2007, an air sparge curtain system, consisting of six (6) air sparge wells was implemented at the site. An Interim Source Removal was conducted at Tempo Cleaners in April 2008.

PSI was tasked with providing remediation system start-up in January 2011. Monthly O&M activities commenced in February 2011 and were discontinued in August 2011. A Membrane Interface Probe study was conducted in November 2011 which revealed more specific data to interpret the contamination plume which is widespread and is migrating vertically. The air sparge system appears to have been successful in decreasing contaminant levels in the shallow zone. However, historic efforts to remediate the intermediate zone have had little impact.

Annual groundwater monitoring data from 2013 to 2018 indicate the continued presence of contaminant concentrations above applicable regulatory Cleanup Target Levels. A groundwater PCE concentration as high as 32,000 μg/L has been reported for samples collected from monitoring well EMW012, which was located in the same location as the former PCE AST where the reported discharge occurred (ECS, 2000).

Over the last 15 years or so, groundwater PCE concentrations have generally decreased in the AST spill area and increased in some of the downgradient wells. Contaminant reduction in the AST spill area appears to be attributable to a combination of source removal activities (ISR and SVE), contaminant migration, and natural attenuation.

In April 2015, PSI representatives met with the owner due to planned construction to remodel the former drycleaner space and expand the convenience store. PSI modified the interior SVE trenching system to underground and performed Soil Oxidant Demand (SOD) testing activities on soil samples to evaluate future remedial strategies. Approximately 12 tons of contaminated soil was removed and transported for off-site treatment and disposal. Two vapor points were abandoned, and one shallow well was installed inside the building.

During discussions with the Department in March 2016, various injection point locations were evaluated for PeroxyChem’s EHC® product. EHC® is composed of zero valent iron (ZVI), controlled release carbon and nutrients, which stimulate the chemical reduction and abiotic degradation of the contaminants. A buffer will also be introduced to ensure the pH is maintained above 6 SU. The selected target zone is the interval 40 to 55 feet bls.

A RAPMOD, dated November 2018, revised September 26, 2019 has been submitted to the FDEP. The RAPMOD proposes in situ chemical reduction, which combines abiotic chemical reduction (zero valent iron) and anaerobic bioremediation. The target treatment areas include the original release area and the on-site portion of the groundwater plume that exceeds NADC levels.

Groundwater testing performed in August 2019 revealed a concentration of PCE in temporary point of compliance (TPOC) well BMW034 exceeding the GCTL. The FDEP has therefore requested a new TPOC well to be located downgradient of BMW034. Additionally, FDEP has requested the installation of intermediate depth wells along the western edge of the groundwater VOH plume for horizontal delineation. Four new monitoring wells and eight permanent injection wells were installed in August 2020. Three of the monitoring wells, designated as BMW044 through BMW046, were located on-site, adjacent to and south of the dispenser area. The fourth monitoring well, designated as BMW047, was located off-site to the south in a residential area which was established as the new Temporary Point of Compliance (TPOC). The revised RAP Modification Revision 4 was submitted to the Department October 15, 2020.

PROPOSED SCOPE OF WORK

The proposal contained herein consists of the performance of the Groundwater Injection Events (injection of EHC Liquid, KB-1 Plus bioaugmentation cultures, and associated amendments into eight locations, as outlined in the RAP) and report deliverable, along with baseline and performance groundwater monitoring events post injection and a post injection report deliverable.

Specifically, the proposed scope of work consists of the following subtasks:

1. Project Management

This scope is provided for in the template worksheets.

2. Pre-Injection Activities

Various tasks will be conducted prior to the actual groundwater injection which will consist of:

• Arrange access with site owner to the site injection areas and common areas for temporary equipment and product storage

• Coordinate with local agencies regarding any permitting requirements

• Obtain permit for use of potable water from a nearby fire hydrant

• Arrange for forklift to be utilized on site for moving the injection reagents

• Receive the injection reagents, unload the injection reagents from the delivery truck, and store the injection reagents on-site beneath a waterproof covering until they are ready to be used.

• Prepare or update a site-specific Health and Safety Plan applicable to the proposed field activities in this RAP

October 26, 2020, revised June 24, 2021 www.intertek.com/building

3. Baseline Monitoring

PSI will perform the baseline monitoring in general accordance with the approved RAP to include the following:

Monitoring Well VOH

UIC Parameters (Fe, Na, TDS) TOC

Dissolved Gases

AMW017 X

AMW042 X X X X

BMW020 X X X X

BMW022 X X

BMW030 X X X X

BMW033R X

BMW034 X

BMW043 X X X X

BMW044 X X X X

BMW045 X X X

BMW046 X X X

BMW047 X

DMW027 X

DMW028 X

X = Highlighted parameters were included in sampling event

4. Groundwater Injection

Eight permanent injection wells have been installed at the site. The injection well locations and well construction details are indicated on Figure 7 of RAP (RAPMod, Revision 4; PSI, 2020).

Cascade was selected as the injection subcontractor during previous discussions with the FDEP based on the FDEP’s concerns with injection pressures and Cascade’s experience with injecting EHC-L.

PeroxyChem will supply the EHC-L and potassium bicarbonate. The EHC-L will be delivered as two components that will be mixed together in the field. The first component is 100% Emulsified Lecithin Substrate (ELS), which will be provided in 55-gallon drums, with 50 gallons of ELS per drum. The second component is the EHC Liquid Mix, which contains ferrous iron powder, and is delivered as a dry powder in 24.6-pound bags.

SiREM will supply the KB-1 Plus bioaugmentation cultures and KB-1 Primer for preparing anaerobic water.

The sodium ascorbate will be purchased from a retail vendor. Quotes from Cascade, PeroxyChem and SiREM are enclosed with this proposal.

The injection mixture will be either transferred to a feed tank connected to a pump, or directly pumped from the mixing tank into an injection manifold. The injection manifold allows simultaneous injection into up to eight injection points, though field applicability and production rates will be determined by site conditions and what the formation will accept at each injection point. The expected injection flow rate is no more than 5 gallons per minute (gpm).

Injection Procedures

1. Cascade will mix and prepare the EHC-L solution for application.

2. Cascade will supply all necessary injection equipment, including pumps, mixing tanks, delivery manifold, injection heads with flow & pressure gauges, safety bypass valve, PPE and safety equipment for Cascade personnel, and first aid station.

3. Using a diaphragm pump, the Cascade solution will be transferred from the poly tank into the injection wells.

4. Cascade will perform real time reagent distribution monitoring for optimization of the injection design during the injection activities.

5. The visual observance of the volume in the graduated tanks and an in-line flow meter will be used to calculate injection volumes at each injection point.

6. Cascade will provide daily injection logs detailing material quantities, elapsed time, injection pressures, and field observations.

Injection points and surrounding areas will be monitored for any signs of surfacing, and spill prevention/control supplies will be on hand to respond as needed. Injection pressures and flow rates will be monitored at each injection point, and appropriate field adjustments will be made as needed to properly distribute the remedial agents. Potential field adjustments include changes in injection point locations and injecting in stages (i.e., injecting what the formation will accept, then moving on to other points and returning to the original point later).

Dilution water will be obtained from a permitted fire hydrant and pretreated with sodium ascorbate at a mixing ratio of approximately 2.5 pounds per 1,000 gallons (approximately 300 mg/L). DO levels will be monitored and the mixing ratio will be adjusted as needed to maintain DO levels at or below 0.5 mg/L.

A 30-fold dilution of ECH-L is proposed, followed by an adequate volume of chase water to achieve an injection radius of at least 6 feet. The recommended mixing ratio is summarized below and can be scaled as appropriate for the size of the mixing tank:

EHC-L and KHCO3 Mixing Ratio

Unit Qty ELS 100% Liquid Emulsion, 50 gal (460 lb) Drum 1 EHC Liquid Mix, 24.6 lb Bags 4.5 Potassium Bicarbonate (KHCO3) Buffer Pounds 450 Pretreated Water from Fire Hydrant Gallons 1,600

SiREM will supply the KB-1 Plus bioaugmentation cultures and KB-1 Primer. The KB-1 Plus cultures will be directly injected from the shipping vessel into the injection well using an in-line tee fitting. The cultures will be injected between layers of anaerobic water (prepared with KB-1 Primer) to disperse electron donors and protect the anaerobic bioaugmentation cultures. The injection of cultures and anaerobic water will be performed between layers of EHC-L to promote contact between the bacteria and electron donor.

Anaerobic Water Mixing Ratio

Unit Qty KB-1 Primer Package 1 Water from Fire Hydrant Gallons 250

KB-1 Plus Injection Ratio

Unit Qty KB-1 Plus per Injection Well Liters 2 Anaerobic Water per Well (approximate) Gallons 100

The estimated injection volumes per well and total injection quantities are summarized below, based on a 30-fold EHC-L dilution and a target injection radius of at least 6 feet:

Approximate Injection Volumes Per Well

Unit Qty EHC-L Mixture (Pre KB-1 Plus) Gallons 206 KB-1 Plus and Anaerobic Water Gallons 100 EHC-L Mixture (Post KB-1 Plus) Gallons 206 Chase Water Gallons 4,564 Total Injection Volume per Well Gallons 5,076 Injection Volume per Vertical Foot Gallons 338

Approximate Total Injection Quantities

Unit Qty Number of Injection Wells Each 8 ELS Concentrate Drums 2 EHC Liquid Mix Bags 9 Potassium Bicarbonate Pounds 900 Sodium Ascorbate Pounds 100 KB-1 Plus Liters 16 KB-1 Primer Pouches 4 Anaerobic Water Gallons 800 Dilution Water Gallons 3,200 Chase Water Gallons 36,500 Total Injection Volume Gallons 40,500

Flowcharts illustrating the mixing ratios, injection volumes per well, and total injection quantities are provided in Appendix E of the RAP (RAPMod, Revision 4; PSI, 2020), and are also incorporated in the injection services quote (Cascade) enclosed with this proposal.

The injection of EHC-L and KB-1 Plus may cause a temporary exceedance of the drinking water standard for iron, sodium and total dissolved solids (TDS), although a significant deviation is not anticipated.

Paragraph 62-520.310(8)(c), F.A.C., allows these parameters to temporarily exceed standards in a temporary zone of discharge (ZOD) upon FDEP approval of this RAPMod, provided the RAPMod addresses the duration and size of the ZOD, and groundwater monitoring requirements.

PSI will monitor for the following underground injection control (UIC) parameters prior to injection, and on a quarterly basis thereafter:

• Iron, 0.3 milligrams per liter (mg/L), maximum

• Sodium, 160 mg/L, maximum

• Total dissolved solids, 500 mg/L, maximum

A field deliverable consisting of field notes, logs, a brief summary of injection procedures, and laboratory data will be submitted prior to the final report.

5. Performance Monitoring

Post-injection groundwater quality, UIC monitoring, and injection performance will include one or more of the following analytical parameters during each sampling event: VOHs, iron, sodium, TDS and total organic carbon (TOC). The proposed groundwater monitoring schedule is summarized in Table 7 of the RAPMod, Revision 4; PSI, 2020, with modifications due to contract end dates. The monitoring will only include two quarters, not the original four quarters.

Supplemental performance monitoring parameters included in the KB-1 Plus quote (SiREM) include testing for Dehalococcoides (Dhc) population and volatile fatty acids (VFAs). These tests help quantify and characterize the bioaugmented microbial community and provide indicators of whether electron donor fermentation is occurring.

6. Reporting

An Injection Completion Report will be submitted within 90 days of completing the injection event and monitoring event. The report will include injection drawings certified by a professional engineer registered in the State of Florida.

COST ESTIMATE AND SCHEDULE

The estimated cost to implement the RAP is presented on the attached Cost Estimate and Level of Effort.

All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No. HW552, Bureau of Waste Cleanup Services, dated December 10, 2010. Upon authorization, we anticipate performing baseline monitoring in August 2021, injection in September 2021, and quarterly monitoring in December 2021 and March 2022. The final reporting will be in May 2022.

PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075.

Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.

Michael Mui Nana Westmark, PG, CHMM Project Engineer Principal Consultant / Contract Manager

Michael Rothenburg, PE, CIH Senior Engineer / Department Manager

Enclosures: Cost Estimate / Level of Effort Quotes

• Injection Services (Cascade)

• EHC Liquid and Potassium Bicarbonate (PeroxyChem)

• KB-1 Plus, KB-1 Primer, and Gene-Trac® and VFA Tests (SiREM)

• Equipment Rental (Sunbelt)

P:\552-Env\FDEP BWC\0552593 Tempo Cleaners\Proposal\2020 - GW RAPMod Implement\Tempo RAP Implement 0552-325594-Rev 1.docx

Cascade Remediation Services • 1020 South 82nd Street • Tampa, FL 33619 • (813) 626-1717

Well Injections of EHC-L with KB-1 Bioaugmentation Based on the information provided by Intertek-PSI and the remediation design provided by PeroxyChem, Cascade Technical Services (Cascade) will mobilize to 223 Oxford Road, Fern Park Florida. Equipped with custom built injection equipment, reagent mixing equipment, experienced 40-hour HAZWOPER trained crew, material handling equipment, secondary containment, site safety materials and all necessary consumables. There is a total of eight (8) injection wells.

Cascade will provide multiple tanks for mixing reagents and producing deoxygenated (DO) water for injecting and chasing KB-1 cultures. Water will be procured from a nearby fire hydrant, and the Intertek site representative will test the DO parameters with a YSI (or similar) meter prior to injecting. Pressure rates, flow rates and volume totals will be closely monitored and recorded in Cascade injection logs and made available to the Intertek site representative at the end of each day. Injection points and surrounding areas will be monitored for any signs of surfacing, and spill prevention equipment (absorbent materials and wet vac) will be on hand to respond to any such conditions should they occur. Excess “mounding” or surfacing conditions could cause delays to the projected production rate. Cascade will communicate with Intertek-PSI immediately if surfacing conditions could extend the estimated days onsite.

Cascade assumes water for this injection event can be procured from a nearby fire hydrant (within 750 feet of injection area). Should water need to be obtained from another source, this could impact the estimated production rate.

• (8) injection wells

• Total Injection Volume: 40,500 gallons

• Per well volume: 5,076 gallons

• 3 person crew

• Manifold to 8 wells simultaneously

• Assume 5 gpm per well and 40 gpm total flow rate output

• Assume 11,000 gallons injected per day

Cascade will be equipped with a custom-built injection platform, low DO water tank (sodium ascorbate and water mixture), reagent mixing tank (EHC-L mixture), 250-gallon anaerobic water tank (KB-1 Primer mixture), multi-port manifold with individual pressure gauges and flow totalizers, secondary containment and safety devices (shower and eye wash), spill response kits, site control equipment, and a forklift.

• Each injection well will be fitted with a custom injection well head equipped with a pressure relief valve for safe operating procedures to inject the EHC-L /KB-1 amendments.

• A multi-point injection manifold will be used to inject into up to eight (8) wells simultaneously.

• Prior to mixing EHC-L, hydrant water will be treated with sodium ascorbate to lower DO/remove chlorine at a rate of 2.5 pounds every 1,000 gallons of hydrant water.

• EHC-L will be mixed and kept suspended in a mixing tank separate from a DO water holding tank.

• Once the appropriate volume of solution has been injected, bioaugmentation cultures will be injected through a dedicated port designed to keep the culture from coming into contact with the atmosphere. Anaerobic flush water will then be injected to push the culture into the formation.

mgerber@cascade-env.comEmailMichael GerberPrepared By

223 Oxford Rd Casselberry, FL 32730

Work Site

Intertek PSI - Fern Park, FL - Tempo Dry Cleaners - ISCR – ZVI/Other - 00148936

Opportunity Name

10/2/2020 8:18 AMQuote Revision Date

00057608Quote Number

(813) 886-1075Phone michael.mui@intertek.comEmail

Michael MuiContact Name

5801 Benjamin Center Dr Tampa, FL 33634

Address

Intertek PSIAccount Name

Cascade Rep Contact Information

Scope of Work

Cascade Remediation Services • 1020 South 82nd Street • Tampa, FL 33619 • (813) 626-1717

Cascade provides management of investigation derived waste. Call us today for information on a full range of additional options to meet your drilling needs.

Signature of Authorized Cascade Representative

Name & Title of Authorized Cascade Representative

Date

Signature of Client/ Owner Authorized Representative

Name & Title of Authorized Representative and Company

Date

This quote is based on information provided by you and is valid for 45 days from the bid date. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. On-site soil disposal, unless Cascade expressly assumes responsibility in writing.Cascade shall not be responsible for damages to underground improvements not clearly and accurately marked.

If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade. Additional costs may apply if scope is significantly changed. Prices assume standard labor rates and no work hour restrictions. Proposal is subject to final review of terms and conditions.

$32,800.00Quote Total

$0.00Taxes

0.0000%Tax Percentage

$32,800.00Pre-Tax Total

• Anaerobic water will be created in a sperate mix tank using KB-1 primer. Client will use an ORP meter (or equivalent) to measure the oxygen level in the water before it is injected.

• Injection areas will be monitored for signs of surfacing, and spill containment equipment will be on standby.

• Injection data will be closely monitored and recorded in Cascade injection logs and made available to the Intertek site representative at the end of each day.

Client provided Injection Flowcharts 2020 are attached for reference.

Product Description Quantity Unit Sales Price Optional Subtotal

Mobilization/Demobilization 1.00 LS $3,425.00 $3,425.00

Project Setup/Breakdown 2.00 Day $1,500.00 $3,000.00

Material Handling w/ Certified Operator 5.00 Day $425.00 $2,125.00

Remediation Services 5.00 Day $3,150.00 $15,750.00

Per Diem (3 Person Crew) 5.00 Day $595.00 $2,975.00

Water Meter and Management 1.00 LS $1,650.00 $1,650.00

Mixing Tanks 1.00 LS $2,675.00 $2,675.00

HASP and Reporting 1.00 LS $1,200.00 $1,200.00

CASCADE REMEDIATION SERVICES, LLC (“Cascade”)

TERMS AND CONDITIONS

{CTS 07162019} KK\c:\users\kkosarska\desktop\contracts\templates\crs bid terms (07162019) - net 30.doc Page - 1 of 1

Quote No: ______________

ACCEPTANCE & CONSIDERATION& TERM: By authorizing Cascade

Technical Services, LLC (Cascade) to commence work, Client agrees to these terms and conditions and Cascade agrees to perform work and/or extend credit in exchange.

PAYMENT & INTEREST: Invoices will be submitted by Cascade once a month with payment due from Client within 30 days of the invoice date. Interest at the rate of 1½% per month (18% per annum) will be charged on the principal amount owing after the due date.

ATTORNEYS’ FEES & COSTS: The prevailing party shall be entitled to recover all of its costs, fees and expenses incurred in any dispute regarding collecting the balance due, enforcing the terms and conditions, or pertaining to

Cascade’s work. Such fees and expenses shall include attorneys’ fees, recording fees, and title report fees whether or not legal proceedings are instituted, and if instituted, shall include all other costs, fees expenses and, including without limitation, court costs and expert witness fees incurred in the trial/arbitration, appellate proceedings, and post-judgment.

DISCLAIMER OF WARRANTY: Cascade will exercise reasonable skill and judgment in performing its work. All express or implied guarantees, representations and warranties, including, without limitation, any implied warranty of merchantability, fitness for a particular purpose, whether written or oral, are hereby excluded and are expressly disclaimed by Cascade. Cascade does not warrant any specific results of any kind. To the extent an implied guarantee, representation, or warranty, cannot be excluded, CASCADE’S LIABILITY, IF ANY, IS LIMITED

TO THE AMOUNT PAID BY CLIENT TO CASCADE, AND SHALL IN NO

EVENT EXCEED THAT AMOUNT.

LIMITATION OF LIABILITY: Cascade shall not be liable to Client or any other party for damages of any type, including, but not limited to, indirect, consequential, incidental, special, or punitive damages, whether arising out of contract, negligence, tort, warranty, strict liability or any other legal theory.

CASCADE’S LIABILITY, IF ANY, IS LIMITED TO THE AMOUNT PAID BY

CLIENT TO CASCADE,AND SHALL IN NO EVENT EXCEED THAT

AMOUNT.

NOTICE OF CLAIM: Any and all claims related to or arising from Cascade’s work shall be made in writing to Cascade within one (1) year after Cascade’s completion of its work. Any subsequent claims are waived.

DELAYS/CONDITIONS BEYOND CASCADE’S CONTROL: Cascade shall not be liable for delays in performance beyond Cascade’s control, including, but not limited to, acts of third parties, inability to obtain permits, fire, earthquake, flood, windstorm or other natural disasters, labor stoppages, lockouts, strikes or other differences with employees, war, riot, embargoes, or stoppages created by any government agency or authority. Cascade’s liability, if any, is limited as provided in the limitation of liability provision.

JOB SITE SAFETY: Cascade is not responsible for providing safety monitoring for the site on behalf of Client or any other trade on site. If Cascade observes that safety monitoring is not being performed in strict compliance with the site-specific health and safety plan, applicable federal, state or local laws, and/or as contractually required, Cascade may cease operations and go on standby until safety monitoring is resumed. Cascade shall be entitled to an equitable adjustment in its contract price, including standby time, and for time to perform its work.

INFORMATION: Client has superior knowledge of the job site, site history, access routes to the job site, known or suspected contaminants, surface and subsurface conditions, etc. The Client is obligated to advise Cascade of all or any conditions that may affect Cascade’s work. Client agrees to provide Cascade with such specifications, plans, site history information, reports, studies or other information on surface and subsurface conditions as will be reasonably required by

Cascade for safe, proper and timely performance of its work. Client shall locate all underground utilities and structures. Client shall obtain all necessary permits and rights-of-way and indemnify, defend, and hold Cascade harmless for its failure to do so and for claims of trespass or damage to property, including underground utilities or structures, which arise out of the performance of Cascade’s work.

DISPOSAL: Cascade is not, and has no authority to act as a generator, operator, treater, storer, transporter or disposer of hazardous waste, substances, pollutants or contaminants found or identified at the site. Cascade shall have no responsibility for the transportation, storage, treatment or disposition of contaminated or potentially contaminated waste materials of any kind which are directly or indirectly generated from Cascade’s performance of work, other than hazardous wastes, substances, pollutants or contaminants brought to the work site by Cascade.

Client or its agents shall be responsible for the disposal of any such waste materials.

CHANGED CONDITIONS: The discovery of any hazardous waste, substance, pollutant, contaminant, underground obstruction, condition or utilities on or under the job site which were not brought to the attention of Cascade prior to Cascade commencing work, and which create health and safety risks, or requires Cascade to perform work outside the original scope or beyond its capabilities, will constitute a materially different site condition entitling Cascade to immediately terminate its work (and to receive payment for all work performed up to and including the date of termination). If Cascade elects to continue its work, it is entitled to receive an equitable adjustment in its contract price, including standby time, and for time to perform its work.

REMEDIATION TERMS: Cascade is not responsible for the remediation design and bears no responsibility for the remediation results or impact to existing conditions. Notwithstanding anything contained herewithin this agreement to the contrary, Client indemnifies, holds harmless and shall defend Cascade and its affiliates, directors, officers, employees, agents and Subcontractors against any claims or actions, including third party claims or actions, arising from any remediation design, results or impact to existing conditions.

INDEMNIFICATION: Client agrees to indemnify, defend, and hold Cascade and its agents harmless from and against any and all claims, demands, causes of action

(including third party claims for contribution or indemnification), liability and costs

(including attorneys’ fees and other costs of defense) which result from (i) any release or threatened release of any substance (whether hazard or not); (ii) any claim that Cascade, or any of its subcontractors was a “generator” or “transporter” of hazardous waste or an “operator” of the job site (as such terms are used…