This is a Task Assignment Change Order Form (Change Order No. 1) issued by the Florida Department of Environmental Protection (FDEP) for an existing contract with Colliers Engineering & Design, Inc. (formerly Bergmann Associates). The change order modifies Task Assignment TA9 under FDEP Contract No. CN300 for the Guana Tolomato Matanzas National Estuarine Research Reserve Visitor Center and ADA Trail Improvements project located in St. Johns County, Florida. Michael Leonard, P.E., represents the consultant, while Ralph Perkins serves as the FDEP Contract Manager. The document was signed and approved on July 16, 2024.

The change order adds construction administration services to the existing task, increasing the fixed fee component by $13,594.00 with no change to the reimbursable costs or task timeline. The net increase brings the total task amount to $87,898.22 (consisting of $100.00 in reimbursement and $87,798.22 in fixed fee). Construction administration services are organized into six subtasks: bidding assistance ($1,388.00), shop drawing and contractor submittal review ($5,800.00), requests for information and contractor permitting assistance ($2,776.00), and three construction site visits ($990.00, $990.00, and $1,650.00 respectively). All services are fixed-price with no mileage reimbursement. The task execution period remains unchanged with an end date of December 30, 2025. Payment will be made upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN300-CMC5.pdf PDF
CN-370000-CN300-T14.pdf PDF
CN-370000-CN300-T14CO1.pdf PDF
CN-370000-CN300-T2.pdf PDF
CN-370000-CN300-T2CO3.pdf PDF
CN-370000-CN300-T3.pdf PDF
CN-370000-CN300-T4.pdf PDF
CN-370000-CN300-T6CO6.pdf PDF
CN-370000-CN300-T8.pdf PDF
CN-370000-GC861-CO1.pdf PDF
CN-370000-CN300-CMC6.pdf PDF
CN-370000-CN300-T1CO1.pdf PDF
CN-370000-CN300-T1CO2.pdf PDF
CN-370000-CN300-T2CO2.pdf PDF
CN-370000-CN300-T6.pdf PDF
CN-370000-CN300-T7.pdf PDF
CN-370000-CN300-T1.pdf PDF
CN-370000-CN300-T10.pdf PDF
CN-370000-CN300-T13.pdf PDF
CN-370000-CN300-T15.pdf PDF
CN-370000-CN300-T6CO4.pdf PDF
CN-370000-CN300-T9.pdf PDF
CN-370000-CN300-TA3CO1.pdf PDF
CN-370000-CN300-TA5.pdf PDF
CN-370000-CN300.pdf PDF
CN-370000-CN300-A1.pdf PDF
CN-370000-CN300-CMC1.pdf PDF
CN-370000-CN300-CMC2.pdf PDF
CN-370000-CN300-CMC3.pdf PDF
CN-370000-CN300-T15CO1.pdf PDF
CN-370000-CN300-T15CO1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN300-T2CO1.pdf PDF
CN-370000-CN300-T3CO1.pdf PDF
CN-370000-CN300-T6CO1.pdf PDF
CN-370000-CN300-T6CO2.pdf PDF
CN-370000-CN300-T6CO3.pdf PDF
CN-370000-CN300-T6CO5.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN300 TA9 CO1 RM2203

Guana Tolomato Matanzas National Estuarine Research Reserve Visitor Center and ADA Trail Improvements

Colliers Engineering & Design (Formerly Bergmann Associates)

Michael Leonard, P.E. (904) 760-4503 michael.leonard@collierseng.com

Ralph Perkins (850) 245-2460 ralph.perkins@floridadep.gov

The addition of construction administration services, per the attached dated June 18, 2024.

$ 100.00 $ 74,204.22 $ 74,304.22 $ 100.00 $ 74,204.22 $ 74,304.22 $ 0.00 $ 13,594.00 $ 13,594.00

$ 100.00 $ 87,798.22 $ 87,898.22

03/06/2023

12/30/2025

12/30/2025

12/30/2025

Lisa Yarborough Lisa Yarborough Digitally signed by Lisa Yarborough Date: 2024.07.02 16:11:48 -04'00'

Richard Marcil Richard Rene Marcil, III Digitally signed by Richard Rene Marcil, III Date: 2024.07.03 08:57:59 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.07.08 09:31:11 -04'00'

Michael Leonard, P.E. michael p leonard Digitally signed by michael p leonard Date: 2024.07.10 08:37:43-04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2024.07.16 08:50:52 -04'00'

RM2203 37538060000 083643/22 423001 U3210 241000 QK $ 13,594.00

$ 13,594.0037202423001375004000008364322

File details come from the government source that posted it. Updated .