C007139 - Division 1 - Project Specifications.pdf

PDF 1 MB Posted

Attached to
2027 Milling and Resurfacing Project
Solicitation number
146156
Issued by
Polk County, Florida

About this file

This is a Project Specifications document and related contract materials for the Central Florida Tourism Oversight District (CFTOD) 2027 Milling & Resurfacing Project (Contract C007139), dated September 9, 2026. The project encompasses pavement resurfacing work on two primary roadways: Bonnet Creek Parkway and adjoining roadways from Buena Vista Drive to Vista Boulevard, and Hotel Plaza Boulevard from East Buena Vista Drive to State Road 535. The scope of work includes maintenance of traffic and temporary traffic control, erosion and sedimentation control, existing paver and concrete header curb demolition, milling and resurfacing, signage and pavement markings, and patterned pavement installation. The contractor must provide dedicated full-time staff including a part-time project manager, full-time general superintendent, and foreman dedicated to maintenance of traffic and stormwater pollution prevention. Normal work hours are 7:00 AM to 4:00 PM Monday through Friday, with temporary lane closures potentially required between 11:00 PM and 7:00 AM Sunday through Thursday. Work activities during major holiday periods (Christmas through New Years, July 4th, Easter/Spring Break, Memorial Day, Labor Day, and Thanksgiving) require coordination with Reedy Creek Energy Services and may be restricted. The project drawings and specifications were prepared by Kisinger Campo & Associates Corp. and include 24 drawing sheets for Bonnet Creek Parkway and 16 drawing sheets for Hotel Plaza Boulevard, plus supplemental attachments addressing electrical utilities, insurance requirements, and storm preparation procedures.

The contract is awarded to the lowest bidder based on combined pricing for the Base Bid, with the Owner reserving the right to purchase selected materials directly at values of $25,000 or more to take advantage of the district's sales tax exemption status. The contractor assumes full responsibility for Owner Furnished Products from the point of origin until final completion, including protection, storage, and installation. The contractor must submit a Project Specific Safety Plan, Severe Weather Preparedness Plan, and Construction Schedule prior to mobilization, and is required to maintain daily erosion control inspections, provide power brooms and water trucks for dust control, and submit a Storm Water Pollution Prevention Plan to CFTOD Planning and Engineering within 30 days. All permits except those obtained directly by the Owner—including SWPPP permits, CFTOD Haul Permits, and RCES Dig permits—must be procured and paid for by the contractor. The contractor is responsible for all utility coordination with Reedy Creek Energy Services and other utility providers, and must adhere to Florida Underground Damage Prevention and Safety Act requirements, including submission of Sunshine 811 locate tickets a minimum of three business days (or ten business days for underwater excavation) before commencing work. Failure to utilize approved haul routes results in a $500 daily deduction from the contract sum, and the contractor is liable for any contamination of ponds, lakes, wetlands, or canals resulting from its operations.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT Section 00850

2027 Milling & Resurfacing Project List of Drawings and Specifications

Contract: C007139 September 9, 2026

00850-1

SECTION 00850

LIST OF DRAWINGS AND SPECIFICATIONS

The following list of drawings and specifications, all prepared as noted, shall form a part of the Project Manual:

Project Manual

Entitled: 2027 Milling & Resurfacing Project

Dated: September 9, 2026

DRAWINGS:

The following list of drawings/materials is applicable to the foregoing.

LIST OF DRAWINGS / MATERIALS:

DRAWING

NO.

DRAWING TITLE

ISSUE

DATE

EOR

BONNET CREEK PARKWAY & ADJOINING ROADWAYS FROM BUENA VISTA DRIVE TO VISTA BLVD. RESURFACING

PAVEMENT ONLY PROJECT

1 Key Sheet 4/24/2026 Kisinger Campo &

Associates Corp.

2 Typical Sections 4/24/2026 Kisinger Campo &

Associates Corp.

3 Project Layout 4/24/2026 Kisinger Campo &

Associates Corp.

4 General Notes 4/24/2026 Kisinger Campo &

Associates Corp.

5 Roadway Plan (01) 4/24/2026 Kisinger Campo &

Associates Corp.

6 Roadway Plan (02) 4/24/2026 Kisinger Campo &

Associates Corp.

7 Roadway Plan (03) 4/24/2026 Kisinger Campo &

Associates Corp.

8 Roadway Plan (04) 4/24/2026 Kisinger Campo &

Associates Corp.

9 Roadway Plan (05) 4/24/2026 Kisinger Campo &

Associates Corp.

10 Roadway Plan (06) 4/24/2026 Kisinger Campo &

Associates Corp.

11 Roadway Plan (07) 4/24/2026 Kisinger Campo &

Associates Corp.

12 Roadway Plan (08) 4/24/2026 Kisinger Campo &

Associates Corp.

13 Roadway Plan (09) 4/24/2026 Kisinger Campo &

Associates Corp.

00850-2

14 Roadway Plan (10) 4/24/2026 Kisinger Campo &

Associates Corp.

15 Roadway Plan (11) 4/24/2026 Kisinger Campo &

Associates Corp.

16 Roadway Plan (12) 4/24/2026 Kisinger Campo &

Associates Corp.

17 Roadway Plan (13) 4/24/2026 Kisinger Campo &

Associates Corp.

18 Roadway Plan (14) 4/24/2026 Kisinger Campo &

Associates Corp.

19 Roadway Plan (15) 4/24/2026 Kisinger Campo &

Associates Corp.

20 Roadway Plan (16) 4/24/2026 Kisinger Campo &

Associates Corp.

21 Roadway Plan (17) 4/24/2026 Kisinger Campo &

Associates Corp.

22 Stormwater Pollution Prevention Plan (1) 4/24/2026 Kisinger Campo &

Associates Corp.

23 Stormwater Pollution Prevention Plan (2) 4/24/2026 Kisinger Campo &

Associates Corp.

24 Temporary Detour (01) 4/24/2026 Kisinger Campo &

HOTEL PLAZA BLVD. FROM E. BUENA VISTA DRIVE TO SR 535 RESURFACING PAVEMENT ONLY PROJECT

1 Key Sheet

Associates Corp.

2 Typical Section 4/24/2026 Kisinger Campo &

Associates Corp.

3 Typical Section Details 4/24/2026 Kisinger Campo &

Associates Corp.

4 Typical Section Details 4/24/2026 Kisinger Campo &

Associates Corp.

5 Project Layout 4/24/2026 Kisinger Campo &

Associates Corp.

6 General Notes 4/24/2026 Kisinger Campo &

Associates Corp.

7 General Notes 4/24/2026 Kisinger Campo &

Associates Corp.

8 Roadway Plan (1) 4/24/2026 Kisinger Campo &

Associates Corp.

9 Roadway Plan (2) 4/24/2026 Kisinger Campo &

Associates Corp.

10 Roadway Plan (3) 4/24/2026 Kisinger Campo &

Associates Corp.

11 Roadway Plan (4) 4/24/2026 Kisinger Campo &

Associates Corp.

12 Roadway Plan (5)

00850-3

13 Roadway Plan (6) 4/24/2026 Kisinger Campo &

Associates Corp.

14 Roadway Plan (7) 4/24/2026 Kisinger Campo &

Associates Corp.

15 Stormwater Pollution Prevention Plan (1) 4/24/2026 Kisinger Campo &

Associates Corp.

16 Stormwater Pollution Prevention Plan (2)

SUPPLEMENTAL ATTACHMENTS:

The following list of supplemental attachments is applicable to the foregoing.

ATTACHMENT

NO.

SUPPLEMENTAL ATTACHMENT

ISSUE

DATE

ISSUER

SA-01

RCES Underground Construction Rules in the

Vicinity of CFTOD Electrical Utilities (REV 7)

2/04/2025 RCES

SA-02 2025 CFTOD Insurance Requirements 2/27/2025 CFTOD

SA-03

CFTOD Storm Preparation Procedures (Rev

04.26) 4/27/2026

CFTOD

SA-04 LYNX Bus Stops – HPB And BVD 9/10/2026 CFTOD

SPECIFICATIONS:

The following list of specifications is applicable to the foregoing.

SECTION NO. SECTION TITLE

ISSUE

DATE

STATUS

DIVISION 00 – CONTRACT & BIDDING DOCUMENTS

00850 List of Drawings and Specifications 9/9/2026

DIVISION 01 – GENERAL REQUIREMENTS

01009 Project Specific Safety Plan Requirements 9/9/2026

01010 Summary of Work 9/9/2026

01018 Owner Furnished Products 9/9/2026 AS NEEDED

01019 Owner Purchased Products 9/9/2026 AS NEEDED

01019A Owner Direct Purchase Routing Procedures 9/9/2026 AS NEEDED

01019B Contractor’s Vendor Invoice Affirmation Letter 9/9/2026 AS NEEDED

01019C Owner’s Vendor Invoice Affirmation Letter 9/9/2026 AS NEEDED

01020 Electronic Document Processing Service 9/9/2026

01021 Allowances 9/9/2026 AS NEEDED

01041 Project Coordination 9/9/2026

01045 Cutting and Patching 9/9/2026

01050 Field Engineering 9/9/2026

00850-4

01100 Alternates 9/9/2026 AS NEEDED

01202 Progress Meetings 9/9/2026

01310 Construction Schedule 9/9/2026

01315 Contract Time, Sequencing and Timing of Work 9/9/2026

01325 Scheduling of Work 9/9/2026

01330 Submittal Procedures 9/9/2026

01340 Shop Drawings, Product Data and Samples 9/9/2026

01370 Schedule of Values 9/9/2026

01410 Regulatory Requirements 9/9/2026

01420 References 9/9/2026

01430 Soils Investigation 9/9/2026 AS NEEDED

01440 Quality Assurance and Quality Control 9/9/2026

01455 Testing and Inspection Services 9/9/2026

01500 Temporary Construction Facilities 9/9/2026

01560 Erosion Control and Dewatering 9/9/2026 AS NEEDED

01560A SFWMD Dewatering Permit Notification 9/9/2026 AS NEEDED

01560B Turbidity Monitoring Plan Requirements 9/9/2026 AS NEEDED

01630 Substitutions and Product Options 9/9/2026

01640 Product Handling and Protection 9/9/2026

01700 Project Closeout 9/9/2026

01710 Cleaning 9/9/2026

01720 Project Record Documents 9/9/2026

01730 Execution 9/9/2026

DIVISION 02 & 03 – SECTION 1 – ROADWAY SPECIFICATIONS

FDOT Specification Reference and

Modifications 4/27/2026

CFTOD 334 Specification for Asphalt Pavement 4/27/2026

CFTOD 528

Specification for Portland Cement Concrete

Sidewalk and Driveway

4/27/2026

END OF SECTION 00850

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT Section 01009

2027 Milling & Resurfacing Project Project Specific Safety Plan Requirements

01009-1

SECTION 01009

PROJECT SPECIFIC SAFETY PLAN REQUIREMENTS

PART 1 – GENERAL

1.01 INTRODUCTION

A Project Specific Safety Plan (PSSP) is a communication tool between contractors and the Owner. Used correctly, the PSSP ensures that relevant project/site-specific safety information is identified, monitored and communicated to all involved with the project.

1.02 PURPOSE

The PSSP will allow all those involved with the project to easily identify the existing and potential hazards associated with the scope of work and what methods the contractor shall utilize to mitigate the hazards to an acceptable level.

This should not be an overly complex document. It should be easily referenced by all those working on the project. The document should be able to be used as part of the daily pre task planning and for onsite safety meetings (toolbox talks).

The PSSP should not be a version of the company safety plan. It is Project / Site / Task specific. The PSSP shall include the applicable information commensurate with the size, complexity and risk level of the project.

The PSSP shall make it clear that everyone on the project has the right to report hazards and unsafe practices without fear of reprisal.

Contractor shall submit a PSSP to the Owner for review prior to project commencement with appropriate time for review. The Owner reserves the right to ask the Contractor to resubmit the PSSP if safety critical items related to the project are missing or incomplete.

The submittal of the PSSP does not relieve the Contractor from any other submittals required by the Contract

Documents, including but not limited to:

• Construction & Demolition Safety Plan

• Crane Critical Lift Plan

• Hazardous Materials Disposal Plan

• Maintenance of Traffic (MOT) Plan / Temporary Traffic Control (TTC) Plan

• Hurricane / Weather Contingency Plan

1.03 FORMAT

The Owner will not dictate the exact format of the PSSP. However, there are four critical components of the

PSSP:

• Responsibilities / Contacts

• Scope of work

• Job Safety Analysis (JSA)

• Pre-Task / Daily Safety Planning

01009-2

A. RESPONSIBILITIES / CONTACTS

This section shall simply and clearly define the duties and responsibilities of the Contractor’s personnel regarding the work to be completed and safety and health program implementation. It should also include means to contact those listed (i.e. phone, email, etc.)

• Contractor’s President/Owner (of company)

• Contractor’s Project Manager

• Contractor’s Safety Manager (if applicable)

• Contractor’s Field Supervision/ Superintendent

• All of Contractor’s Subcontractors and Sub-Subcontractors (if any)

B. SCOPE OF WORK

The Scope of Work shall include translating the contract scope of work into a specific detailed work plan. It shall identify location(s), means and methods of accomplishing the plan, anticipated sequence of events, equipment to be used, etc. Please note that this includes all work to be performed by the Contractor and Subcontractors of every tier.

The scope shall also identify the following:

• Maximum height and depth of work activities

• Industrial hygiene issues

• Exposure to high hazard areas including but not limited to:

o Water Ways o Diving o Crane Lifts o Energized Electrical Systems o Confined Spaces o Maintenance Of Traffic (“MOT”) / Temporary Traffic Control (“TTC”) o Guest Areas

C. JOB SAFETY ANALYSIS (JSA)

The JSA is a task/operation-driven document to ensure that the job task or operation receives proper safety planning prior to beginning work. In actuality, the JSA is a written work plan that incorporates safety procedures into the work practices The JSA should be prepared far enough in advance of the task or activity to ensure that changes or revisions will not affect the scheduled execution of the task or activity. A JSA is to be developed by the Contractor or Subcontractors for any high-hazard or high-risk activity as identified by the Owner in its sole and absolute discretion, the Contractor or all

Subcontractors of every tier.

The specific format of the JSA is to be determined by the Contractor, however, it must include the following information:

• A breakdown of the job into successive steps involved with the work activity.

• Identification of the hazards and the potential incidents associated with each work activity.

• Identification of methods to reduce or eliminate the hazards and potential incidents.

01009-3

D. PRE-TASK PLANNING

Pre-task Planning is an activity that occurs at the start of each day, prior to beginning any work shift during which work is to be performed by the Contractor or any Sub-contractor of any tier, as well as any time the daily cope of the work changes. It helps everyone involved in performing, supervising and overseeing the work to align the objectives to be accomplished before the day of work begins. A Pre-task Planning form is required to be completed and a meeting is required to be held with the crew by the supervisor prior to the start of each work shift. At a minimum, the supervisor will include the following in the Pre-task Planning:

• Identify the specific actions and work methods required to perform the work.

• Identify the specific hazards associated with the performance of the work and the measures necessary to eliminate or minimize the workers’ exposure to the hazard.

• Provide the necessary training needed to safely perform the work.

• Identify and provide the necessary tools, equipment, and PPE required to protect the workers from the hazards.

• Review any items that may be applicable to their work activity previously identified on the JSA.

The Pre-Task Plan will be documented and kept in the work location for the duration of the shift or activity. As acknowledgment of its contents, the Pre-Task Plan must be signed by all members of the work crew and its supervisor, and others identified by, and in the sole and absolute discretion of, the Owner.

Pre-Task Planning is not something that is to be submitted with the PSSP however it must be maintained on the jobsite throughout the project duration for review by the Owner and, at the request of the Owner, must be provided to the Owner as part of the Contract Close- out documentation.

END OF SECTION 01009

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT Section 01010

2027 Milling & Resurfacing Project Summary of Work

01010-1

SECTION 01010

SUMMARY OF WORK

PART 1 – WORK COVERED BY CONTRACT DOCUMENTS

1.01 General

A. The Scope of Work for the 2027 Milling & Resurfacing Project is described by the Project Manual entitled 2027 Milling & Resurfacing Project. Specific elements of the Scope of Work are generally summarized below but this Summary of the Work is not intended to be complete descriptions of the

Work. Any quantities or measurements, if included in the summaries, are approximate and are not to be used in estimating the Work.

B. It is the intent of the Owner that the Contractor will perform all of the Work of any kind and nature shown on the drawings and/or described in the specifications, which is within the Contractor's Scope of Work unless specifically excluded or indicated as Owner-furnished and/or installed. Any Work not specifically indicated on the drawings and/or described in the specifications but required to fulfill the intent of a "complete job" for the Contractor's Scope of Work will be considered to be included in the Contract.

1.02 General Summary

The scope of work for the 2027 Milling & Resurfacing Project includes but is not limited to: Maintenance of Traffic/Temporary Traffic Control/Lane Closures; Erosion & Sedimentation Control; Existing Paver and

Concrete Header Curb Demolition; Milling & Resurfacing; Signage & Pavement Markings and Patterned

Pavement Installation.

1.03 Detailed Scope of Work

A. Mobilization and General Conditions:

1. The Contractor shall provide a minimum dedicated full-time staff for the duration of the

Contract Time including but not limited to the following staff positions:

a. Part time dedicated project manager.

b. Full time dedicated general superintendent.

c. Foreman and crew dedicated to Maintenance of Traffic (MOT)/Temporary Traffic

Control (TTC) and SWPPP only.

d. Power broom on site at all times.

e. Water truck will be required periodically.

B. Permitting:

1. Work must meet all requirements of the Land Development Regulations in effect at the time of the effective Contract date.

C. Maintenance of Traffic (MOT) / Temporary Traffic Control (TTC):

1. The Contractor shall follow the Traffic Control Plans (TCPs) provided for the Project.

Contractor is required to adhere to FDOT Standard Plans (Standard Design Index) 102-600 series and associated indexes for items not detailed in the TCPs. Contractor is required to submit for approval proposed MOT/TTC details when certain activities (i.e., structure component deliveries, excavations adjacent to traffic, overhead installations, etc.) require detailed operations to control traffic flow. Contractor shall include all such activities within

01010-2 their bid and expect to attend regular MOT/TTC Coordination meetings to discuss proposed operations. Should the Contractor request to deviate from the TCPs or request an alternate/additional detour or subphase, the Contractor shall hire a professional engineer licensed to do business in the State of Florida to provide a certified Maintenance of Traffic

(MOT) / Temporary Traffic Control (TTC) individual plan prior to applying for the required permits from CFTOD Planning & Engineering. The MOT/TTC plans shall be in compliance with the Manual for Uniform Traffic Control Devices and applicable FDOT

Standards. The Contractor shall maintain his traffic control devices for the entire duration of the project until the Owner certifies that the Punch List is complete.

2. The Contractor shall provide a qualified traffic control crew to provide continuous maintenance of all traffic control systems at its expense, whenever traffic conditions warrant such control and whenever directed to provide such maintenance or adjustments by the CFTOD Construction Project Manager. This requirement shall also apply to all events requiring a vehicle to back up on a lane maintained for traffic or any other situation considered by the CFTOD Construction Project Manager to be dangerous.

3. The Contractor shall provide a qualified traffic control crew at its expense to inspect all traffic control systems in the presence of the Owner at the beginning and end of each work shift for a minimum of one hour after the start of the shift and a minimum of one hour before the end of the shift. The Contractor’s crew shall make immediate corrections or adjustments to the MOT/TTC systems as required to conform them to the approved

MOT/TTC plans or as directed by the CFTOD Construction Project Manager.

4. All MOT/TTC devices shall be like new. They shall be freshly painted and free of scratches, dents, dirt, and debris, and stains. The Contractor shall replace any MOT/TTC device that becomes damaged with a new device.

5. The Contractor shall construct and remove all temporary pavement as indicated within the drawings or otherwise deemed as necessary by the Owner.

D. Lay Down Yard/Employee Parking Construction:

1. The designated lay down yard and employee parking area is anticipated to be in the vicinity of the Project Site. The exact location of the laydown area shall be coordinated with and approved by the CFTOD Construction Manager, prior to mobilization. The Contractor shall contain all trade parking, inclusive of the Contractor itself, to designated contractor parking areas. Staging and construction laydown is very limited within project limits. Contractor is responsible to maintain cleanliness of their assigned/approved area(s). No POV shall be parked within project limits.

2. Contractor Employees shall be transported from assigned parking areas to work areas by means provided by Contractor.

E. Erosion and Sedimentation Control:

1. The Contractor shall design, furnish, install and maintain, at its expense, all necessary erosion control and wetland protection systems, such as silt fences, temporary retention basins, silt screens, synthetic hay bales, floating turbidity barriers, inlet protection systems, filter fabric, sandbags, sheet piling or other approved devices per the Land Development

Regulations and Owner as required to prevent erosion and to protect the storm water systems and receiving waters. The Contractor shall be responsible for repairing and/or replacing any and all damage to the erosion protection devices. The Contractor shall maintain all erosion control systems until the Owner certifies that the punch list is complete.

2. The Contractor shall prepare the Storm Water Pollution Prevention Plan utilizing the forms included in the Specification Section 01560. The Contractor shall submit a completed

SWPPP to CFTOD Planning and Engineering for review and the Contractor shall make all modifications and refinements to the plan requested by CFTOD Planning and Engineering.

01010-3

Contractor shall be advised CFTOD Planning and Engineering has 30 days to review

SWPPP submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly. Once all of the modifications have been made to the satisfaction of CFTOD Planning and Engineering, then the

Contractor shall sign and certify the SWPPP as the operator and implement the structural erosion control devices.

3. The Contractor shall prepare and submit the NOI (when required) to CFTOD

Planning and Engineering for review. Only after CFTOD Planning and Engineering has reviewed and approved the draft NOI, shall the Contractor submit the NOI to

FDEP and pay all filing fees and secure a permit authorization letter from the EPA and fully comply with all record keeping requirements.

4. The Contractor shall prepare and submit a Turbidity Control Plan if working within an active waterbody or within 15 feet of the top of slope (a.k.a the low maintenance zone) of an active waterbody (including lakes, canals, etc.). The Contractor shall be required to create a Turbidity Control Plan providing detailed information regarding means and methods and best management practices to prevent, contain and treat turbidity as may be encountered and generated during the course of work. This can also include items such as sheet pile/cofferdam information, bypass pumping, etc. that may be required to manage flow during course of work. Contractor shall be advised CFTOD Planning and Engineering has 30 days to review Turbidity Control Plan submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly.

5. The Contractor shall provide a qualified and dedicated erosion and sedimentation control team to inspect and maintain the erosion control and wetland protection systems on a daily basis. The Contractor acknowledges that daily inspection and maintenance requirement is more stringent than the periodic inspections required by the FDEP. The Owner requires more stringent daily inspection and maintenance by a dedicated crew. The Contractor shall remove all erosion and sediment control systems at the conclusion of its Work when authorized to do so by the Owner and upon approval by CFTOD Planning and Engineering.

6. The Contractor will be required to maintain at all times, a clear, orderly construction site and ensure the implementation of good housekeeping practices as described in these

Contract Documents within the Storm Water Pollution Prevention Plans (SWPPP).

7. The Contractor shall submit any chemical products/treatment methods for turbidity to the

Owner and CFTOD Planning and Engineering for approval prior to use. Contractor shall be aware certain products may not be allowed due to risks of environmental degradation.

8. The Contractor shall maintain a power broom on site at all times throughout the Contract

Time and sweep the roadways on a daily basis whenever its construction traffic cause dirt or debris to be deposited on the roads or whenever directed to sweep the roads by the

Owner.

9. The Contractor shall provide and maintain a water truck at all time during the Contract

Time to provide dust control when conditions warrant or as directed by the Owner.

10. The water quality within the various bodies of water located on the Owner’s property is regularly monitored and compliance with environmental standards is rigidly enforced. The

Contractor is advised that should any of the Owner’s ponds, lakes or canals, (or those of adjacent landowner’s) become contaminated due to the Contractor’s actions or inaction, the cost to flocculate, or clean by any means as may be required, shall be paid for by the

Contractor.

F. Survey and Lay-Out:

1. The Contractor shall perform all survey and lay out as required to complete the work within the specified tolerances.

2. Refer to the Drawings for information regarding bench mark datum and coordinate system.

3. The Contractor shall preserve and protect all existing survey monuments within the limits of construction.

01010-4

4. The Contractor shall provide the following specific survey tasks:

a. All surveying, engineering and layout required for the Work including but not limited to: (i) roadway layout and stationing; (ii) guardrail layout, etc.

b. All “rough” and “finish” grade stakes as required to perform the Work. Any re-staking required due to his or any other contractor damaging, or removing original stakes shall be performed by the Contractor and will not be the responsibility of the Owner.

c. Coordination with the Owner’s survey consultant for verification of the

Contractor’s survey including, but not limited to, Contractor’s field notes and temporary horizontal and vertical control points.

5. It is the responsibility of the Contractor to generate survey control, layout, and as-built information as required in the contract documents. At no time will the project CAD design files be given to the Contractor.

G. Clearing:

1. The Contractor shall provide all clearing and grubbing as needed in performance of the work. Tree pruning, as required, is to be performed/supervised by an approved certified arborist as deemed necessary by the Owner.

2. No burning will be allowed on site. The Contractor shall remove all cleared vegetation

(grasses, plants, bushes, shrubs, trees, etc) from the site and dispose of it legally off site.

Existing grasses/sod removed (strippings), as required for construction, shall be disposed of off-site at the contractor’s expense and not utilized for embankment, backfill, or prepared soil layer of any kind unless approved by the Owner.

3. The Contractor shall remove all irrigation systems within the limits of the Work as required for the construction of the improvements. The Contractor will be required to retain the services of a CFTOD approved irrigation company to make any repairs and adjustments due to the Contractor’s construction activities as directed by the CFTOD Construction

Project Manager.

4. The following contractors have worked within the boundaries of Central Florida Tourism

Oversight District (CFTOD) property in the past. By providing this list, CFTOD does not make or imply any qualifications or statements as to the performance or standing of these firms and the bidder is at their own risk while contracting or working with them:

a. BrightView LLC

b. Commercial Landscape and Irrigation Inc.

c. Cepra Landscape LLC

d. Down To Earth Landscape and Irrigation LLC

e. Newberg Irrigation Inc.

H. Utilities:

1. The Contractor, with guidance from the Owner shall coordinate all utility construction efforts with the utility owners – Reedy Creek Energy Services (RCES) RCES requires coordination for inspections of their new and existing utilities. RCES will also require 72-hour notice and planning when working around their existing utilities. Other utility owners may include, but are not limited to, Smart City Telecom (data and communications fiber optic and wire), CFTOD (traffic fiber optic), and WDW Telecom (Disney fiber optic), Spectrum, Duke, Summit Broadband, TECO, & AT&T.

2. The Contractor shall identify and protect all existing utilities within the limits of the work.

3. Except as otherwise explicitly indicated on Drawings or called for in the Specifications, do not cut, alter, remove or otherwise disturb any existing improvement or construction or disturb any existing utilities without the approval of the CFTOD Construction Project

Manager.

01010-5

4. The Contractor shall immediately restore to service and repair any damage caused by it to any existing utilities which are not scheduled for removal, discontinuance or abandonment, or which have not been released by the Owner and jurisdictional agencies for removal, discontinuance or abandonment, even if so scheduled.

5. Temporary Supports for existing Utilities: The Contractor shall provide all necessary temporary supports required to protect any and all existing utilities prior to commencing

Work. Any damage to existing in-service utilities during construction will be repaired at the Contractor’s expense. Temporary supports shall be reviewed by representatives of

RCES or appropriate utility company prior to installation by the Contractor.

6. The Contractor shall strictly adhere to utility notice and excavation permit provisions specified in Section 2.13 of Section 01010 of the project manual. The RCES Utility Locate

Office will locate primary utility services. It will not locate secondary services. Secondary services include roadway lighting systems, irrigation systems, and electrical power systems for the existing lift station. All such services shall be maintained and/or relocated without interruption to existing services. The Contractor shall hire a private utility locate service to identify and locate all secondary utilities within the limits of the Work

7. Locating services provided by the RCES Locating Services Office10T13T, Sunshine 811 and by any private secondary locating technician are confined to surface markings and flagging only. The Contractor shall hand dig and soft dig as required to determine the depths of all utilities. All such hand digging and soft digging shall be included in the Lump

Sum Contract amount.

8. In the case of a conflict between the RCES specifications and the CFTOD specifications, generally the CFTOD specifications shall supersede the RCES specifications. The final determination shall be made by the CFTOD Construction Project Manager. This is not withstanding provisions contained elsewhere in the general conditions.

9. Any temporary or permanent utility (potable water, reclaimed water, sanitary water, gas, chilled water, etc.) connection to existing facilities will require advance coordination between Contractor, Owner, and RCES in all cases.

10. Contractor is strictly prohibited from adjusting, closing, or opening any mechanical valves on RCES, CFTOD or Resort utility systems. Utilization/adjustment of valves for any reason requires advance coordination between Contractor, Owner, Resort Owner, and

RCES in all cases. The utility Owner(s) must be present to supervise/perform any and all valve operations.

I. Construction:

1. The Contractor shall construct all areas as shown on the drawings.

2. The Contractor shall prevent any vehicle and material tracking within and outside the limits of work due to paving equipment tracking tack or asphalt debris.

Contractors shall use methods such as sanding to avoid tracking tack at high friction area (intersections & U-turns). All sand, millings, and tack debris shall be cleaned prior to open lanes traffic.

J. Sod:

1. Contractors shall replace all sod, with like kind, if damaged by its operations.

K. Irrigation:

1. The Contractor shall repair and restore to new condition any and all grades, landscaping, sod, utilities, or sleeves that are damaged during the contract scope of work. The Contractor shall coordinate its activities with the Separate Contractors to ensure all sleeves are installed in a timely manner consistent with the schedule provided by the Separate

Contractors.

01010-6

2. The Contractor shall be responsible to maintain the irrigation system in such a manner to prevent plant stress due to lack of water. Planted material that becomes stressed beyond recovery, shall be replaced by the Contractor at no additional charge. If temporary irrigation systems are required to meet the Milestone Schedule, the Contractor shall provide such temporary systems.

3. If needed, Contractor shall coordinate all planting work with irrigation work and shall be responsible for all hand watering as required to supplement irrigation watering and rainfall.

The Contractor shall be responsible for supplemental hand watering in all planting areas, regardless of the status of the irrigation.

PART 2 – GENERAL INSTRUCTIONS & STANDARDS FOR THE CONSTRUCTION WORK

2.01 General Requirements

A. The Contractor shall provide all services and necessary items of expense, including but not limited to, labor, material, trucking, transportation, equipment, hoisting, scaffolding, power, supervision, appliances, layout and all other services and items of expense required for the complete performance of all Work in accordance with the Contract Documents.

B. Cost Loaded Schedule

1. The Contractor shall cost load their monthly progress CPM schedule submittals, in order to provide projected monthly cash flows to the Owner.

C. Proposed Staffing Plan

1. Contractor shall submit with its Bid Proposal a staffing plan which clearly illustrates the key elements of the organizational structure proposed to accomplish the management, field work, and administrative services required. The Contractor shall identify the key person to be placed in responsible charge of the work. The CFTOD Construction Project Manager and key personnel within each discipline shall be identified and past experience of each, as it relates to this Project, shall be discussed. Other items to be included in the discussion of the staffing plan are:

a. Work force capabilities of the firm.

b. Work force commitment for the Project.

c. Key staff resumes.

2.02 Job Site Access / Use of Job Site

A. A haul route will have to be provided by the Contractor for CFTOD Planning and Engineering review and approval. The Contractor shall utilize lined trucks to haul muck or saturated soils off site

(if required) and shall utilize only those hauling routes prescribed or approved by the Owner for hauling to and from the site. For each and every occurrence that the Contractor or its

Subcontractor(s) utilize a haul route that is not prescribed by, or otherwise expressly approved by, the Owner shall deduct from the Contract Sum, the sum of $500.00 a day.

B. Vehicular traffic to the Job Site is limited to vehicles required to deliver labor and materials. On-site parking for vehicles shall be limited to those areas designated by the Owner and shall be limited to company work vehicles actively working on site. Vehicles not actively supporting Job Site operations are not permitted to remain on site. The designated lay down yard and employee parking area is anticipated to be in the vicinity of the Project Site. When it is designated, the Contractor shall create an engineered plan for review by the Owner that demonstrates how it will safely access the work zone and storage areas and how it will egress from the work zone and storage area.

01010-7

C. The Contractor is responsible for the routing of all construction personnel and traffic required in the performance of the Work and shall ensure compliance with any special instructions pertaining to such routing as established by the CFTOD Construction Project Manager.

D. Lunch and break areas are confined to the immediate job site area, within the limits of construction.

E. The Contractor shall confine its use of the job site to those activities directly relating to the performance of the Work. No other use of the job site will be permitted without the express written approval of the CFTOD Construction Project Manager.

F. The Contractor shall provide all necessary flagmen, barricades, and MOT/TTC devices necessary for safe and proper traffic control. The Contractor is advised that it is responsible for all construction personnel and traffic routing logistics required in the performance of its work.

G. The Contractor shall provide all necessary temporary water retention basins, turbidity control, and silt fence, etc., for construction site water run-off control. The Contractor is advised that should any of the adjoining Central Florida Tourism Oversight District and Walt Disney World ponds, lakes, wetlands, or canals become contaminated due to the Contractor’s actions or inactions, the cost to flocculate, clean, or restore by any other means, these ponds, lakes, wetlands, or canals shall be paid for by the Contractor. Any fines and / or penalties assessed for contamination of these water bodies, due to the Contractor’s actions or inactions, shall be paid for by the Contractor.

2.03 Coordination

A. The Contractor shall coordinate with the CFTOD Construction Project Manager to allow for all materials testing. The Owner shall pay for costs associated with the initial testing but the Contractor shall be liable for costs associated with retesting as a result of initial test failure due to deficiencies in the Contractor's work efforts.

B. The Contractor shall coordinate its work with the CFTOD Construction Project Manager and with the Owner’s Separate Contractors. The Contractor shall sequence its Work, as required by the

CFTOD Construction Project Manager, with the work of the Owner’s Separate Contractors at no additional cost to the Owner.

C. The Contractor is required to coordinate with the delivery of any and all Owner Furnish, Owner or

Contractor installed items.

D. The Contractor shall coordinate with the CFTOD Construction Project Manager for site access/control for The District Fire Department.

E. The Owner, reserve the right of access to any part of the job site, at any time, for the purpose of observation, or to install other work, either with its own forces of with other contractors.

2.04 Worker Conduct and Clothing

A. The Contractor is responsible at all times for the proper conduct of its personnel and that of its subcontractors and suppliers. The Contractor shall restrict its personnel to the job site and immediate vicinity thereof and shall endeavor to prevent discordant relationships between its personnel and that of any adjacent property owner or resident.

B. The Contractor shall enforce strict discipline and good order among employees and other workers related to the performance of the Work. Under no circumstances will behavior offensive to building occupants or the general public be tolerated, and Contractor shall immediately remove and further ban from the job site any persons failing to comply with this standard.

01010-8

C. The Contractor shall ensure its personnel are properly dressed with O.S.H.A. approved clothing and safety gear, including but not limited to, hard hats, work shoes, shirts and long pants, as appropriate for the performance of the Work. Shorts, sleeveless shirts (tank tops) or clothing bearing offensive marks or wording are not permitted to be worn on the job site. The Owner shall solely determine whether any such clothing is or is not permissible.

2.05 Surveying

A. Refer to Specification Section 01050 – Field Engineering, contained in the Project Manual, for specifications governing field engineering and surveying.

B. The Contractor shall inspect the site, observe the existing conditions and grades, and make reasonable measurements to verify existing conditions prior to its bid.

C. The Contractor shall verify forms prior to pouring, or placing, critical components of structures.

D. It is the responsibility of the Contractor to generate survey control, layout, and as-built information as required in the contract documents. At no time will the project CAD design files be given to the Contractor.

E. The Contractor verify the location of all existing utilities or obscured existing improvements or construction indicated on Drawings to be proximate to or affected by the Work prior to commencement of excavation or demolition in any given area.

2.06 Testing and Inspection

A. Refer to Specification Section 01455 – Testing & Inspection Services, contained in the Project

Manual, for specifications governing soils and materials testing and inspection. The Owner reserves the right to re-test and approve or disapprove the results of the Testing and Inspection.

B. The project specifications utilize Florida Department of Transportation specifications governing acceptance of materials used in the performance of the Work. Because the Owner has no affiliation with the Florida Department of Transportation’s materials testing laboratories where such materials are deemed acceptable, the Owner has developed an alternative Materials Acceptance Criteria

Matrix governing the manner in which materials will be accepted on the project. Contractor shall refer to attached Division 2 through Division 3 Specifications prepared by Kisinger Campo &

2.07 Surface Water Management and Environmental Controls

A. The Contractor shall provide and maintain all necessary erosion control in accordance with paragraph 1.3.5 above, the plans, and Specification Section 01560, entitled Erosion Control and

Dewatering, contained in the Project Manual.

B. The Contractor shall submit for approval any and all Erosion and Sedimentation control measures necessary/required to remedy waterway conditions negatively impacted by or resulting from contractor operations. Contractor will implement such approved measures at no additional cost to the owner.

2.08 Temporary Fencing

A. Geogrid Fencing and Silt Barriers:

01010-9

1. When required by the Contract Documents, geogrid fencing and silt barriers shall be provided and maintained along the boundaries of all designated tree preservation and protected wetland areas. The Contractor shall not disturb the trees or vegetation within such areas unless directed otherwise by the Owner.

2. Geogrid fencing shall be provided and maintained along jurisdictional wetland buffers excluding those wetlands (if any) to be removed under this Contract. Silt barrier shall be provided and maintained along areas designated on Drawings.

3. The Contractor shall inspect all geogrid fences and silt barriers daily and shall immediately make necessary repairs to any damaged or improperly functioning geogrid fences and/or silt barriers.

2.09 Permits and Permit Fees

A. All Permits required for any part of the Contractor’s Work (except those permits obtained directly by the Owner, as further enumerated below) shall be procured and paid for by the Contractor. This shall apply also to those permits required to be obtained by the Contractor in the name of the Owner for the Owner’s own temporary construction office facilities, if any. The costs for the required permits (except those permits obtained directly by the Owner) are included in the Contract Sum.

Before applying for any permit, the Contractor shall present a draft application to the Owner for review.

B. The Contractor shall obtain, secure and pay for the following permits:

1. SWPPP Permit

2. CFTOD Haul Permit and any required Right of Way Permit

3. RCES Dig permit

C. The Owner shall provide to the Contractor the following:

1. N/A

D. The Contractor shall submit to the Owner a copy of ALL permits required to be obtained by this

Contractor, which are required for the performance of this Work.

2.10 Job Site Cleanliness, Construction Operations Upon and Affecting the Use of the Project Site

A. Refer to Specification Section 01710 – Cleaning, contained in the Project Manual, for specifications governing cleaning and job site cleanliness.

B. The Contractor shall cause no dirt or debris to be deposited on any public or private roadways and must clean up same in an expeditious manner if such dirt or debris occurs due to this Contractor's operation. If the Contractor fails to perform, clean-up will be performed by others and all costs for same will be deducted from monies due or owing the Contractor.

C. The Contractor shall clean the tires of all vehicles as they exit the job site and enter onto the public roadway or private driveways. The Contractor shall provide rotary power broom equipment on site for daily sweeping as needed and as requested by the Owner.

D. The Contractor shall use "whisperized" construction equipment. Noise levels shall be within those levels acceptable by the authorities having jurisdiction.

E. Material deliveries shall generally be made during normal working hours. Where special deliveries must be made at other times Contractor shall request approval of same. If such request is approved

Contractor shall arrange for the proper labor force to receive and unload materials promptly.

01010-10

F. The Contractor shall be responsible to consolidate and secure all equipment and materials at the job site. The Owner will not provide any security for material and equipment stored on site for contractors working at the Project site.

G. On site storage of fuel will not be permitted without prior written approval of the Owner and approval from all appropriate local, state, and federal agencies having jurisdiction.

H. Any and all damage to property resulting directly or indirectly by the Contractor's operations, or those of its subcontractors, shall be repaired or replaced by the Contractor at no additional cost to the Owner and to the satisfaction of the Owner.

I. Daily clean-up of the construction areas will be strictly enforced. Excess materials or accumulation of debris shall not encumber the site.

J. If, in the judgment of the Owner, the construction area is deemed to be unclean and/or encumbered by the accumulation of excess materials; and, in the event the Contractor fails to correct the situation, the Owner reserves the right to take any action it deems necessary to correct the situation and shall back charge the Contractor for the full cost of the corrective action.

K. The Contractor shall provide a final clean prior to turnover.

L. All construction activities that may have any effect on any adjacent landowner’s operating systems or facilities must first have the final approval of the Owner before they are initiated. The activity description, schedule time and duration, and areas affected must be submitted to the Owner at least

72 hours in advance to obtain this approval.

M. Work activities that affect the environment of guest operations (noise, visual intrusion, safety, odor, dust and dirt, etc.) may be restricted to other than normal operating hours.

N. Any maintenance to construction equipment on-site, which may be considered by the Owner to have the potential to contaminate the existing earth, will not be permitted.

O. Maintenance and dust abatement of all areas of Work provided by the Contractor shall be performed in a manner acceptable to the Owner.

P. The Contractor will be responsible for safely barricading open excavations that may present hazards.

Q. The Contractor shall hire Mid Florida Materials to provide rubbish removal, reuse container rental/removal or other services related to the disposal of waste material from the job site. Contact

Noah (Tel: 407.607.9359) or Lisa (Tel: 407.607.9345), a minimum of 24 hr. in advance of waste pick-up. No other firm, entity or agency is authorized to provide solid waste service within the

District unless permitted in writing by the District. Such service includes Class I, Class III and

Construction and Demolition Debris service. Any firm, entity or agency found to be providing such service within the District without written permission from the District shall be required to remove any solid waste containers associated with this service within 48 hours of notification. Failure to do so will result in the impoundment of said containers by the District. Release of said impounded containers to the owner will require payment of a storage fee of $100/container each day.

R. The Contractor shall legally dispose of all excess soils generated by the Work.

S. On-site security is the responsibility of Contractor. Observe security requirements established by

Central Florida Tourism Oversight District and adjacent landowners. Coordination and all questions with regard to security shall be directed to the CFTOD Construction Project Manager.

01010-11

T. The Contractor shall prevent any vehicle and material tracking within and outside the limits of work due to paving equipment tracking tack or asphalt debris. Contractors shall use methods such as sanding to avoid tracking tack at high friction area (intersections & U-turns).

All sand, millings, and tack debris shall be cleaned prior to open lanes traffic.

2.11 Existing and Adjacent Roadways and Utilities

A. The Contractor will maintain access to roadways at all times. The Contractor shall create no open cuts or other obstacles on roadways or walkways without explicit approval of the CFTOD

Construction Project Manager. Authorized cuts must be bridged to permit vehicular and pedestrian traffic to continue without delay or hindrances. Any work that must be performed which may result in delays to public traffic or re-routing of traffic must be coordinated with the CFTOD Construction

Project Manager.

B. Wherever possible, the Contractor shall arrange work so there will be no service interruptions of any existing systems. Whenever service interruptions are necessary, the Contractor shall secure the advance approval of the CFTOD Construction Project Manager and jurisdictional agencies as to the time and date such interruptions will be permitted. The Contractor shall return all services back into operation as soon as possible, including working on an overtime basis, if deemed necessary by the

CFTOD Construction Project Manager, at no additional cost to the Owner.

C. All existing conditions off the immediate Project site that are disturbed due to Contractor’s activities must be restored by the Contractor to pre-construction conditions.

D. The Contractor shall restore all existing grade, existing sod, and existing irrigation it disturbs.

Restore all affected areas to existing conditions or better.

E. RCES, CFTOD, WDW and other Utility Owners all have existing infrastructure within the project limits. The Contractor shall preserve and protect all such infrastructure during the performance of its Work. The Contactor shall sequence its Work in cooperation with the utility companies and as required to work around the existing infrastructure without damaging it until it is relocated. Once relocated, the Contractor shall preserve and protect the relocated infrastructure throughout the remaining duration of the work. Contact information is provided on the drawings.

2.12 Temporary Facilities

A. The Contractor shall provide generators for temporary construction power.

B. The Contractor shall provide temporary portable toilets for use by its tradesmen, and shall be located out of view from the traveling public at locations approved by the CFTOD Construction Project

Manager.

2.13 Notification to Utility Companies and Excavation Permit

A. Utility Locate Tickets:

1. In accordance with Florida “Underground Damage Prevention and Safety Act” (Chapter

556, Florida Statutes) as administered by Sunshine 811 of Florida. Any entity or individual responsible for any project involving excavating, grading, penetration, or disturbance of the earth’s surface, inclusive of jack and boring, pile-driving, directional drilling, trenching and pipe bursting, within the District shall not commence such work within the District

01010-12 until that entity/individual has submitted a Locate Ticket request to Sunshine 811 and received clearance from the affected utilities. Refer to 32Thttp://www.sunshine811.com/ 32T.

2. There are two types of utility locate requests:

a. Standard Locate requests:

i. Used when no portion of the excavation will be underwater

ii. Request must be submitted a minimum of three (3) full business days before excavation. If the excavation site is in an area that is underwater, the request must be submitted ten (10) full business days before excavation.