About this file
This document is an Award Criteria Figure Formula for a county contract, detailing a complex mathematical method for evaluating and calculating bid adjustments across different facility types. The formula covers three distinct facility categories: General Facilities, Detention Facilities, and OSHPD (Office of Statewide Health Planning and Development) Facilities. For each facility type, the document provides calculation methods for normal working hours and other than normal working hours adjustment factors, with specific percentage weightings (40% for General Facilities, 15% for Detention and OSHPD Facilities).
The Award Criteria Figure (ACF) is determined by adding specific multiplied lines that represent different facility and work hour scenarios. The percentages and calculations are intended for bid purposes only, with the county explicitly noting they are not obligated to issue job orders in the stated percentages. The instructions emphasize carrying out all calculations to the 4th decimal place, suggesting a high degree of mathematical precision in the bid evaluation process. This formula appears designed to provide a standardized, quantitative method for comparing and scoring construction or service bids across different facility types and work schedules.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Award Criteria Figure Formula
Award Criteria Figure Formula percentages are for Bid purposes only. The County is not obligated to issue Job Orders in the stated percentages.
Carry out all Lines to the 4th decimal place.
Line 1. General Facilities
Normal Working Hours Adjustment Factor
1.
Line 2. Multiply Line 1 by 40% = (0.40 x Line 1) 2.
Line 3. General Facilities
Other than Normal Working Hours Adjustment Factor
3.
Line 4. Multiply Line 3 by 10% = (0.10 x Line 3) 4.
Line 5. Detention Facilities
5.
Line 6. Multiply Line 5 by 15% = (0.15 x Line 5) 6.
Line 7. Detention Facilities
7.
Line 8. Multiply Line 7 by 10% = (0.10 x Line 7) 8.
Line 9. OSHPD Facilities
9.
Line 10. Multiply Line 9 by 15% = (0.15 x Line 9) 10.
Line 11 OSHPD Facilities
11.
Line 12 Multiply Line 11 by 10% = (0.10 x Line 11) 12.
Line 13. Add Lines 2, 4, 6, 8, 10 and 12
(This is the Award Criteria Figure)
ACF =
File details come from the government source that posted it. Updated .