This document contains a past performance questionnaire for a federal construction contract opportunity with the National Park Service. The opportunity is to stabilize the Alcatraz Wharf at the Golden Gate National Recreation Area in San Francisco, California. Work will include repairing historic steel-cased concrete piles, beams, and slabs that are in fair to poor condition, as well as installing two new seismic resisting elements to strengthen the wharf to Risk Category III standards. The single-phase project will repair concrete and undertake seismic improvements. References will evaluate the contractor's past performance on quality, schedule, cost control, management, regulatory compliance, and small business subcontracting using a rating system. The completed questionnaire should be returned to the National Park Service's Denver Service Center by the specified due date.

View the file

Other files

File Type Posted
B09_amd_5_attach_23_2021_08_18___Supplemental_Information_Repairs_and_Seismic_Upgrades_to_Alcatraz_Wharf_0005.pdf PDF
Sol_140P2021R0143_Amd_0005.pdf PDF
SECTION_01_27_00___DEFINITION_OF_CONTRACT_LINE_ITEMS_0005.pdf PDF
20220509_-_ContractPriceSchedule_0005.xlsx XLSX spreadsheet
B09_amd_5_attach_24_GOGA_AlcatrazWharfPier_NMFSLetter_20210916_FINAL_LEJ_0005.pdf PDF
Sol_140P2021R0143_Amd_0004.pdf PDF
Sol_140P2021R0143_Amd_0003.pdf PDF
B09_Amd_2_sign_in_2_0002.pdf PDF
Sol_140P2021R0143_Amd_0002.pdf PDF
B09_Amd_1_Site_visit_sign_in_0001.pdf PDF
Sol_140P2021R0143_Amd_0001.pdf PDF
B09_Amd_1_Site_Visit_Tri_Fold_ALCA_Wharf_0001.pdf PDF
B08_Attach_9_Subcontracting_Plan.doc DOC document
B08_Attach_2_ALCA_Const_Dwgs_20220318.pdf PDF
B08_attach_1_ALCA_Specifications.pdf PDF
B08_attach_11_NHPA_Section_106.pdf PDF
B08_Attach_10_ALCA_USACE_Permit.pdf PDF
Sol_140P2021R0143.pdf PDF
B08_Attach_15_PLUMBING_INSPECTION.pdf PDF
B08_Attach_5_Certification.pdf PDF
B08_Solicit_140P2021R0143.pdf PDF
B08_Attach_4_Memo.pdf PDF
B08_Attach_13_Geotechnical_Investigation_Report_Alcatraz_Wharf.pdf PDF
B08_Attach_12_2001_EIS_GOGA.pdf PDF
B08_Attach_3_WD.pdf PDF
B08_Attach_14_CH-2119_Alcatraz_Wharf_Report.pdf PDF
B08_Attach_8_General_References.doc DOC document
B08_Attach_6_Project_Experience_Questionnaire.docx DOCX document
B08_Attach_16_Signed_Acting_Deputy_Supt_D_Schifsky_12-27-21_ALCA_Wharf_NEPA_Consistency_Memo.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS: Offeror to complete Sections A and B and transmit questionnaire to reference.

Reference to complete Sections C and D and transmit back to Contracting Officer listed in section E.

A. CONTRACTOR INFORMATION

Company Name
Company
Street Address
Address
City
City
State
State
Zip Code
XXXXX
DUNS Number
XXXXXXX
Point of Contact
Name, Email, Phone

B. CONTRACT INFORMATION

Project Title
Title
Contract Number
XXXXXXXXXX
Contract Type
Firm Fixed Price / Time & Materials / Cost Reimbursable / Other
Awarded Contract Price
$X,XXX,XXX
Current / Final Price
$X,XXX,XXX
Contract Award Date
XX/XX/XXXX
Contract Completion Date
XX/XX/XXXX
Period of Performance
XX/XX/XXX – XX/XX/XXX
Project Location
Park or Street address, City, State
Client / Owner
Company
Brief description of the contract & work effort:
Scope of work description

C. REFERENCE:

Name
First, Last
Position / Title
Title
Organization
Agency or Company
Phone Number
XXX-XXX-XXXX
Email Address
Email
Signature
Signature
Date
XX/XX/XXXX

D. EVALUATION

Rating
Definition
Exceptional
Performance met contractual requirements and exceeded many to the owner’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance met contractual requirements and exceeded some to the owner’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance met contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance did not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Evaluation Area
Rating

Quality

Quality of workmanship (including subcontractors)?
Choose an item.
Quality of and adherence to quality control plan?
Choose an item.
Quality of informational and technical submittals?
Choose an item.
Overall Quality Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Schedule (& Time Management)

Met project schedule milestones?
Choose an item.
Responded to owner requests in a timely manner?
Choose an item.
Informational and technical submittals submitted timely?
Choose an item.
Promptly addressed scheduling issues?
Choose an item.
Overall Schedule (& Time Management) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Cost Control

Addressed differing & unforeseen site conditions so as to minimize additional costs?
Choose an item.
Provided fair and reasonable pricing for contract modifications?
Choose an item.
Submitted accurate and complete invoices?
Choose an item.
Promptly paid subcontractors and suppliers?
Choose an item.
Overall Cost Control Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Management

General oversight by project manager and superintendent?
Choose an item.
Coordination with and control of subcontractors?
Choose an item.
Avoidance of accidents & safety violations?
Choose an item.
Addressed location factors (especially remote locations)?
Choose an item.
Maintained good working relationship with owner representatives?
Choose an item.
Demonstrated flexibility, innovativeness and cooperation in resolving potential problems?
Choose an item.
Overall Management Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Small Business Subcontracting (& Labor Standards)

Met regulatory and contractual labor standards?
Choose an item.
Successfully contracted with small and socio-economically disadvantaged businesses?
Choose an item.
Quality and adherence to applicable subcontracting plans?
Choose an item.
Overall Small Business Subcontracting (& Labor Standards) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Regulatory Compliance

Met building and life safety codes?
Choose an item.
Overall Regulatory Compliance Rating
Choose an item.
Overall Recommendation:
Given what I know today about the contractor's ability to perform in accordance with the contract’s most significant requirements, I would recommend them for similar contracts:
Choose an item.
Overall Comments:

E. RETURN:

Return by
Time / Date
Name
Brian Tollensdorf
Title
Contract Specialist
Organization
National Park Service – Denver Service Center
Email
Brian_Tollensdorf@nps.gov

File details come from the government source that posted it. Updated .