This solicitation seeks proposals for the stabilization of Alcatraz Wharf at Golden Gate National Recreation Area. Work will include repairing the historic steel-cased concrete piles, beams, and slabs that are in fair to poor condition. Two new seismic resisting elements will also be installed to upgrade the wharf's seismic rating. Concrete repairs and seismic upgrades will be completed in a single construction phase. Responses are due by the date specified in the solicitation. The National Park Service will award a firm fixed price contract for the work.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GOLDEN GATE NATIONAL RECREATION AREA
ALCATRAZ ISLAND
STABILIZE ALCATRAZ WHARF
GOGA
PMIS NO. 215726
DIVISION 1 SPECIFICATIONS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
FEBRUARY 4, 2022
GOGA - 215726 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 57 19.12 Noise & Acoustics Management 01 57 23 Under-An-Acre Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 81 13 Sustainable Design Requirements
GOGA - 215726 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Soils Investigation Report.
11. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Fixed Wharf and Finger Pier, Alcatraz Island, Golden Gate National Recreation Area, San Francisco, California.
B. The Alcatraz Fixed Wharf and Finger Pier are historic structures and contributors to the National Historic Landmark (NHL) district. All work must be in compliance with the Secretary of the Interior’s Standards for the Treatment of Historic Properties. All materials and elements of the building must be protected during construction. See Section 01 35 91 - “Historic Preservation Treatment Procedures.”
C. As a result of its status as a contributor to an NHL district, all Work must be conducted by the Contractor in a manner that prioritizes protection of the existing historic structures and site from damage during construction. The Work will require using means and methods carefully selected to be least damaging to the historic building and site. Means and methods are constrained to those that will afford the building protection against damage of any kind. All work must comply with the Secretary of the Interior’s Standards for the Treatment of Historic Properties. Refer to Section 01 35 91 - “Historic Preservation Treatment Procedures.”
D. The Work consists of the following:
1. The repair of damage in Fixed Wharf slabs, beams, and piles as indicated on the drawings and in these specifications. A Type 1 repair involves using cast-in-place concrete or
GOGA - 215726 01 11 00 - 2
shotcrete to repair the concrete member. A Type 2 repair requires rebar repairs in addition to cast-in-place and/or shotcrete repairs to the concrete member. Seismic retrofit efforts will also be undertaken. The work will include the replacement of mechanical piping under the Fixed Wharf. The work includes the following:
a. Type 1 Beam Repair efforts utilizing cast-in-place and/or shotcrete repair methods for Fixed Wharf beams.
b. Type 2 Beam Repair efforts utilizing cast-in-place and/or shotcrete repair methods and rebar repairs for Fixed Wharf beams.
c. Type 1 Slab Repair to concrete on Fixed Wharf slabs.
d. Type 2 Slab Repair to concrete and rebar on Fixed Wharf slabs.
e. Pile Repair to concrete and repair on Fixed Wharf piles. Pile Repair also includes the installation of two pile replacements.
f. Addition of two seismic dolphins.
g. Installation of a seismic joints.
2. The replacement/installation of piles and movable landing in the Finger Pier. The work includes the following:
a. Replacement of the movable landing with a landing composed of similar materials.
b. Replacement of 8 timber piles on the Finger Pier.
c. Reconstruction of the cross bracing on the Finger Pier.
d. Installation of a steel fender pile along Gridline 5.
e. Installation of 4 hybrid piles along Gridline 5.
E. The Finger Pier project will be treated as add alternate #1 to the Fixed Wharf project.
F. The repair to 50 piles on the Fixed Wharf will be treated as add alternate #2 to the Fixed Wharf project.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. There may be overlapping projects with the Fixed Wharf and Finger Pier project. Ensure coordination with other project activities including fixed wharf barge run mobilization and demobilization activities with the Contracting Officer.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to areas of construction and designated staging areas.
2. Limit site disturbance, including earthwork and clearing of vegetation, 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond
GOGA - 215726 01 11 00 - 3
constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
B. Storage of Materials: Confine storage of materials to staging locations designated on Drawings.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Concessionaire Requirements and Coordination
1. The Park Concessionaire has a leasehold on portions of the Wharf where the work will be performed. A certificate of proof of insurance shall be provided for use of the Wharf within the leasehold area.
2. Coordinate schedule of work and completion dates with Park Concessionaire as directed by the Contracting Officer.
F. Construction Camp: Establishment of a camp within the park will not be permitted.
G. Hauling Restrictions: Comply with all legal local, state, and federal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads and deck of Fixed Wharf may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1. Protect roads and the Fixed Wharf deck from construction-related damage; refer to Section 01 73 40 - “Execution.” For road usage requirements.
2. Roads on the island have hairpin turns that preclude the use of some construction equipment.
GOGA - 215726 01 11 00 - 4
3. Do not block the shuttle route on the Fixed Wharf deck or the main road during hours of public visitation.
4. All vehicles on the main road must have a “spotter” on foot to interface with the interpretive staff and public, and to assist in the prevention of accidents. The main road speed limit is 5 miles per hour.
H. Worker Orientations: All workers must attend an orientation meeting with Park interpretative staff to review the unique requirements of working on Alcatraz Island, interfacing with the public, and safeguarding natural and cultural resources. All contractor staff shall attend Bird Sensitivity Training led by Park Wildlife biologist. Worker orientation shall occur prior to notice to proceed for all new workers.
I. Provide 30 days’ notice before moving into a work area to allow Park to adjust interpretation for public.
1.5 PUBLIC USE OF SITE
A. The island will be open to the public during construction. Conduct all operations to ensure the least inconvenience to the public and park staff. Public areas of the Wharf and Finger Pier must remain open to the public at all times during visitor hours. Closures of portions of the Wharf and Finger Pier for construction will be permitted on a case by case basis upon written approval of Contracting Officer.
1.6 OCCUPANCY REQUIREMENTS
A. Existing Structures
1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
B. New Structures
1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of the Fixed Wharf or Finger Pier, provided such occupancy does not interfere with completion of the Work.
Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.
b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.
c. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of the Fixed Wharf and Finger Pier.
GOGA - 215726 01 11 00 - 5
1.7 WORKER TRANSPORTATION TO ALCATRAZ ISLAND
A. Contractor is responsible for transporting their construction crew to the Island. The requirements and availability of worker transport services are outlined below.
B. Park Concessionaire, Alcatraz City Cruises (ACC), operates multiple regularly scheduled public ferries and a single “staff ferry” on a daily basis. The Contractor may use these ferries for transport to and from Alcatraz at no cost. Only materials that can be hand carried onto and offloaded from the ferry without multiple trips will be allowed on ferries. See Section 01 73 40
- “Execution” for material and equipment transportation.
1. Park Concessionaire is not required to transport workers to Alcatraz Island.
2. Park Concessionaire can transport workers from Alcatraz Island to San Francisco on regularly scheduled passenger ferries.
3. Notify and coordinate with Park Concessionaire when work crew size will vary from an established norm in order to facilitate adequate room on passenger ferries.
4. Contractor must provide a list of crew members’ names to the Contracting Officer at least two days before the first day of work.
5. Crew members will be required to check in at the Ticket Booth.
6. Photo identification is required for passage on any ferry/barge/water taxi. Contractor shall supply crew members with photo badges that include crew member’s photo, Contractor’s name, project name, project number, and dates the badge is valid through.
7. No flammables or hazardous materials are allowed on staff or public ferries. All equipment must be drained of fuel prior to transport.
C. See Paragraph 1.8 for information about water taxis.
1.8 TRANSPORT OF MATERIALS AND EQUIPMENT TO ALCATRAZ ISLAND
A. Contractor parking at Pier 33 is not permitted. Parking areas near the Pier can be found on the Alcatraz City Cruises website. Contractors can drive in and unload supplies and equipment at Pier 33 early, move the vehicle to a nearby parking lot, and walk back to the Pier to load the boat.
B. Contractor is responsible for arranging transport and delivery of materials and equipment to and from the island.
C. Alcatraz City Cruises (ACC) is the Concessionaire for Alcatraz Island and is the only approved vendor for landing on the floating dock and Fixed Wharf. Use of all barge services must be coordinated with the Contracting Officer and ACC and a certificate of liability insurance and/or a landing plan review may be required.
D. The requirements and availability of barge services are outlined below:
1. Weststar Marine Services operates a material barge service using a 20 ton crane to off-load and take on material. Weststar Marine Services also operates a water taxi service that is used outside of ACC operating hours, or if ACC cannot supply a vessel.
GOGA - 215726 01 11 00 - 6
2. Alcatraz Island Services operates a material barge service with a 2,000 pound crane limit.
All cargo loads must be arranged at least 48 hours in advance.
3. Manson Construction and CS Marine are used for heavy lift in cases where heavy equipment is needed on the Island and it will not fit through the Sally Port. Restrictions apply during bird breeding season.
4. The Golden Gate National Parks Conservancy operates a monthly Weststar Marine Services barge to meet the operational needs of both the Conservancy and the NPS. Any barge activities that are arranged by the Contractor shall not interfere or conflict with this monthly barge. The Conservancy barge schedule is set in October/November of each year for the following calendar year.
a. The Conservancy will allow Contractor limited use of the monthly barge as follows:
1) Availability will be determined by the Conservancy based on availability of space, time and equipment/personnel limitations.
2) Use of Conservancy barge will be subject to “per lift” fees.
3) Coordinate use of Conservancy barge directly with the Golden Gate National
Parks Conservancy a minimum of one week prior to barge run.
5. The Contractor may organize and coordinate their own barge service and other vendors may be available. Barge service outside the service listed above must be arranged and paid for by the Contractor and coordinated with Park Concessionaire’s regular ferry schedule.
6. Other services may be available.
E. Contacts:
1. Alcatraz City Cruises: Aaron Warren 415.559.3126
2. Weststar Marine Services Dispatch: 415.495.3191
3. Alcatraz Island Services: Aaron Warren 415.559.3126
4. Manson Construction: Ryan King 510.232.6319
5. CS Marine: 707.562.4100
6. Parks Conservancy Operations: Patrick McAllister 415.561.4923
F. Coordinate construction efforts with the Contracting Officer such that there is minimal impact to the work of the National Park Service personnel and the visiting public.
1.9 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
GOGA - 215726 01 11 00 - 7
1.10 WORK RESTRICTIONS
A. Regular Work Hours: Work shall be generally performed during the hours of 5:00 a.m. to 9:30p.m., Sunday through Saturday, except when otherwise indicated.
1. Work may be performed between 9:30 pm and 5:00 am with 72 hours notice given and Contracting Officer approval. When work occurs during these hours use minimum lighting to safely conduct operations. Lighting should be fully shielded and cast downward. Light should be directed to stay within project area and avoid light escape to adjacent areas and habitats.
2. Visitor Hours High Season: 9:00 a.m. to 9:30 p.m.
3. Visitor Hours Low Season: 9:00 a.m. to 7:45 p.m.
4. Non-visitor Hours High Season: 9:30 p.m. to 9:00 a.m.
5. Non-visitor Hours Low Season: 7:45 p.m. to 9:00 a.m.
6. Noisy work is permitted in accordance with section 01 57 19.12 Noise and Acoustics Management. Noisy work may be permitted if noise reduction measures mitigate the effect on the visitor experience are provided by contractor and approved by Contracting Officer.
Notify the Contracting Officer of noisy work 72 hours in advance. Noisy work is not permitted during special events outside visitor hours. Contracting Officer will provide one week advanced notice of special events that prohibit noisy work.
B. The following activities shall occur outside Visitor Hours:
1. Driving the casings for the seismic dolphin piles.
2. Driving piles at the Finger Pier and movable landing.
3. Lifting loads over the Fixed Wharf. For instance, lifting the piles or casings into place.
C. Existing Utilities
1. No potable water is available on the island for construction activities. Contractor to arrange with Park Concessionaire for transport of water to the island.
2. Storage and delivery of potable water is extremely limited; Contractor is responsible for providing adequate means for storage and delivery of water.
3. Contractor is responsible for collection and disposal of any waste water. Contractor to arrange with Alcatraz Island Services for transport of waste water from the island.
4. No electricity is available on the island for construction activities. Contractor is responsible for providing own electricity and to arrange fuel supply and handling with Alcatraz Island Services.
5. The island does not have a public telephone land line and has limited cellular reception.
Contractor is responsible for providing their own phone and data access.
6. Contractor shall be responsible for locating and preventing damage to utilities. If damage occurs, repair utility at no additional expense to the Government.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
GOGA - 215726 01 11 00 - 8
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions. Electrical utility outages shall not occur during visitor hours. Interruptions to sewage pipes should not disrupt service, coordinate with Contracting Officer.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Do not interrupt diesel fuel line.
E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes. Smoking is allowed only in a designated area on the Fixed Wharf.
1.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. Comply with all requirements of the Alcatraz Island Historic Preservation and Safety Construction Environmental Impact Statement dated October 2001 and the mitigation measures included therein. Details of compliance shall be presented in the Historic Preservation Treatment Plan, refer to Section 01 35 91 – “Historic Preservation Treatment”.
C. Alcatraz Island has severe weather exposure and frequent high winds.
1.12 SOILS INVESTIGATION REPORT
A. A soils investigation report entitled Geotechnical Investigation Alcatraz Wharf Seismic Retrofit, October 19, 2018, has been prepared by Langan Engineering and Environmental Services, Inc.
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.13 HAZARDOUS MATERIAL REPORT
A. An asbestos survey report entitled Asbestos Survey Report Alcatraz Island Concrete Wharf, San Francisco, CA, September 3, 2021, has been prepared by Craig W. Heidig, CAC.
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
GOGA - 215726 01 11 00 - 9
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
END OF SECTION 01 11 00
GOGA - 215726 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general
GOGA - 215726 01 26 01 - 2
conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
GOGA - 215726 01 26 01 - 3
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) – Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) – Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
GOGA - 215726 01 26 01 - 4
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
GOGA - 215726 01 26 01 - 5
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project.
Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………12% Profit…………………..6%
GOGA - 215726 01 26 01 - 6
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
END OF SECTION 01 26 01
GOGA - 215726 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
1.2 DEFINITIONS
A. “Unit Price”: a price per unit of measurement for materials and services necessary to perform the Work defined below and in the Contract Documents, include all necessary material, cost for delivery, protection, engineering & testing, access, installation, insurance, supervision, overhead, and profit.
B. Type 1 work involves repairing concrete members (beams, slabs, and piles) with cast-in-place concrete or shotcrete. Type 1 work does not include repair to rebar.
C. Type 2 work involves repairing concrete members (beams, slabs, and piles) with cast-in-place concrete or shotcrete. Type 2 work includes repair to rebar.
1.3 PROCEDURES
A. Payment for unit price work will be made only for the actual quantities of work installed.
B. For each unit price the approved Schedule of Values will establish defined subtasks and an associated percentage completion of the unit price work in order to receive partial payment of unit price items.
C. The Contracting Officer reserves the right to reject Contractor’s measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government’s expense, by an independent surveyor mutually acceptable to the Government and Contractor.
D. The Line Item descriptions of work below are in outline form and are intended only to present an overview of the of the work included under each item. Each item includes the cost associated with mobilization and general conditions.
PART 2 - PRODUCTS
GOGA - 215726 01 27 00 - 2
PART 3 - EXECUTION
Stabilize Alcatraz Wharf Project includes:
Base Bid: Contract line items 01 through 09 Add alternate #1, Finger Pier Project: Contract line item options 10 through 15 Add alternate #2: Contract line item option 16.
3.1 CONTRACT LINE ITEM NO. 01 TYPE 1 BEAM REPAIR:
A. Type 1 Beam Repair consists of furnishing transportation, labor, materials, and equipment to perform concrete beam repairs. Repairs will utilize cast-in-place concrete or shotcrete for beams.
All edge beams shall be repaired with cast-in-place concrete. The work includes but is not limited to installation of safety barriers, inspection of work, demolition and removal of damaged concrete, surface preparation of rebar, preparation of concrete surfaces, scaffolding, placing concrete, curing concrete, removal of scaffolding, repair of any defects, and clean up.
B. Measurement will be made on a linear foot basis. The base contract quantity is 316 linear feet.
C. Payment will be made at the contract unit price per linear foot.
3.2 CONTRACT LINE ITEM NO. 02 TYPE 2 BEAM REPAIR:
A. Type 2 Beam Repair consists of furnishing transportation, labor, materials, and equipment to perform concrete beam repairs including rebar repairs. Repairs will utilize cast-in-place concrete or shotcrete for beams. All edge beams shall be repaired with cast-in-place concrete. The work includes but is not limited to installation of safety barriers, inspection of work, demolition and removal of damaged concrete, surface preparation of rebar, repair to rebar, installation of new rebar, preparation of concrete surfaces, scaffolding, placing concrete, curing concrete, removal of scaffolding, repair of any defects, and clean up.
B. Measurement will be made on a linear foot basis. The base contract quantity is 1,889 linear feet.
C. Payment will be made at the contract unit price per linear foot.
3.3 CONTRACT LINE ITEM NO. 03 TYPE 1 SLAB REPAIR:
A. Type 1 Slab Repair consists of furnishing transportation, labor, materials, and equipment to perform concrete slab repairs. Concrete repairs will utilize shotcrete. The work includes but is not limited to installation of safety barriers, inspection of work, demolition and removal of damaged concrete, surface preparation of rebar, preparation of concrete surfaces, scaffolding, placing concrete, curing concrete, removal of scaffolding, repair of any defects, and clean up.
B. Measurement will be made on a square foot basis. The base contract quantity is 1,306 square feet.
C. Payment will be made at the contract unit price per square foot.
GOGA - 215726 01 27 00 - 3
3.4 CONTRACT LINE ITEM NO. 04 TYPE 2 SLAB REPAIR:
A. Type 2 Slab Repair consists of furnishing transportation, labor, materials, and equipment to perform concrete slab repairs including rebar repairs. Concrete repairs will utilize shotcrete. The work includes but is not limited to installation of safety barriers, inspection of work, demolition and removal of damaged concrete, surface preparation of rebar, repair to rebar, installation of new rebar, preparation of concrete surfaces, scaffolding, placing concrete, curing concrete, removal of scaffolding, repair of any defects, and clean up.
B. Measurement will be made on a square foot basis. The base contract quantity is 2,417 square feet.
C. Payment will be made at the contract unit price per square foot.
3.5 CONTRACT LINE ITEM NO. 05 PILE REPAIR:
A. Pile Repair consists of furnishing transportation, labor, materials, and equipment to perform the repairs to damaged piles and the replacement of three piles on the Fixed Wharf. The work includes but is not limited to installation of safety barriers, inspection of work, partial removal of existing steel shell, demolition and removal of damaged concrete, surface preparation of rebar, repair/installation of rebar, install pile jackets, preparation of concrete surfaces, placing concrete, grouting, removing scaffolding, repair of any defects, and clean up. A Type 2 Pile Repair includes the installation of rebar while a Type 1 Pile Repair does not.
B. Measurement will be made on a linear foot basis. The base contract quantity is 1,924 linear feet.
C. Payment will be made at the contract unit price per linear foot.
3.6 CONTRACT LINE ITEM NO. 06 SEISMIC DOLPHINS:
A. Seismic Dolphins consists of furnishing transportation, labor, materials, and equipment to perform the installation of two seismic dolphins. The first seismic dolphin will be located between horizontal Gridlines W and U and vertical Gridlines 7 and 9. The second seismic dolphin is located between horizontal Gridlines H and F and vertical Gridlines 5 and 8. The first seismic dolphin consists of four steel pipe piles while the second seismic dolphin consists of six steel pipe piles. The pipe piles are 30” in diameter. Seismic Dolphins also includes the installation of a concrete cap and connection of the cap to the existing concrete. The work includes but is not limited to the installation of safety barriers, inspection of work, demolition of slabs and tops of existing piles, disposal of removed materials, preparation of concrete surfaces, drilling rock sockets, driving of a pile casing, installation of an architectural slab, repair of any defect, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
GOGA - 215726 01 27 00 - 4
3.7 CONTRACT LINE ITEM NO. 07 SEISMIC JOINT:
A. Seismic Joint consists of furnishing transportation, labor, materials, and equipment to perform the installation of a seismic joint between Gridlines AA and BB. The seismic joint will be covered by a ¾” thick plate. To support this cover plate and frame the joint, concrete will be cast on either side and steel sections and anchors will be cast-in or post installed. The work includes but is not limited to the installation of safety barriers, inspection of work, slab demolition, slab removal, disposal of removed materials, pile installation, installation of a pilaster, epoxy doweling of rebar and anchors, installation of steel sections, repair of any defects, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.8 CONTRACT LINE ITEM NO. 08 UTILITY REPLACEMENT
A. Utility Replacement consists of furnishing transportation, labor, materials, and equipment to remove and replace all existing utility lines below the Fixed Wharf. The work includes but is not limited to installation of safety barriers, inspection of work, demolition and removal of existing utility lines, installation of new utility lines, installation of utility hangers and anchors, repair of any defects, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.9 CONTRACT LINE ITEM NO. 09 CONCRETE CURB REPAIR
A. Concrete Curb Repair consists of furnishing transportation, labor, materials and equipment to remove and replace damaged concrete curb.
B. Measurement will be made on a linear foot basis. The base contract quantity is 98 linear feet.
C. Payment will be made at the contract unit price per linear foot.
3.10 CONTRACT LINE ITEM OPTION NO. 10, ADD ALTERNATE #1, MOVABLE LANDING:
A. Movable Landing consists of furnishing transportation, labor, materials, and equipment to furnish and install the new movable landing. The moveable landing will be replaced with steel channels of similar size to existing steel channels. The movable landing shall be hot dip galvanized. Prior to installation shop drawings that have been signed and stamped by a licensed California Engineer shall be submitted to Contracting Officer for review. The lifting mechanism shall have its cables and sheaves replaced. The lifting winch shall be replaced and shall include limit switches. The work includes but is not limited to the installation of safety barriers, inspection of work, submittal of stamped shop drawings of movable gangway, demolition and removal of existing gangway, disposal of removed materials, installation of structural steel channels, installation of decking, repair of any defects, and clean up.
B. No separate measurement of quantities will be made.
GOGA - 215726 01 27 00 - 5
C. Payment will be made at the contract lump sum price.
3.11 CONTRACT LINE ITEM OPTION NO. 11, ADD ALTERNATE #1, REPLACEMENT OF
TIMBER PILES:
A. Replacement of Timber Piles consists of furnishing transportation, labor, materials, and equipment to furnish and install 8 new timber piles on the Finger Pier. The work includes but is not limited to the installation of safety barrier, inspection of work, removal of damaged piles indicated on drawings, disposal of removed materials, pile coating, pile driving, repair of any defects, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.12 CONTRACT LINE ITEM OPTION NO. 12, ADD ALTERNATE #1, RECONSTRUCT THE
CROSS BRACING AND OTHER PIER TIMBERWORK:
A. Reconstruct the Cross Bracing consists of furnishing transportation, labor, materials, and equipment to furnish and reconstruct 3 cross braces on the Finger Pier, resetting the waler between piles 35 and 36, and replacing the waler between piles 43 and 44. The work includes but is not limited to the installation of safety barrier, inspection of work, removal of damaged cross braces indicated on drawings, disposal of removed materials, pier timberwork, repair of any defects, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.13 CONTRACT LINE ITEM OPTION NO. 13, ADD ALTERNATE #1, STEEL FENDER PILE:
A. Steel Fender Pile consists of the furnishing transportation, labor, materials, and equipment to furnish and install a steel fender pile along Gridline 5. The steel fender pile will consist of a 10.75” diameter steel pipe pile enveloped in an HDPE sleeve. The work includes but is not limited to the installation of safety barriers, inspection of work, pile driving, pile coating, repair of defects, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.14 CONTRACT LINE ITEM OPTION NO. 14, ADD ALTERNATE #1, HYBRID PILES:
A. Hybrid Piles consists of the furnishing transportation, labor, materials, and equipment to furnish and install four hybrid piles along Gridline 5. A hybrid pile consists of a 10.75” diameter steel pipe pile enveloped in an HDPE sleeve with a timber stub attached to the top of the pipe pile and sleeve. The work includes but is not limited to the installation of safety barriers, inspection of
GOGA - 215726 01 27 00 - 6
work, removal of damaged piles, disposal of removed materials, pile driving, pile coating, repair of any defects, and clean up. Installation will include connection to existing pier.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.15 CONTRACT LINE ITEM OPTION NO. 15, ADD ALTERNATE #1, COATING PORTAL
FRAMES:
A. Coating Portal Frames consists of furnishing transportation, labor, materials, and equipment to clean and recoat the two portal frames at the movable landing. The work includes but is not limited to installation of safety barriers, inspection of work, surface preparation of portal frames, coating/painting of portal frames, repair of any defects, and clean up.
B. No separate measurement of quantities will be made.
C. Payment will be made at the contract lump sum price.
3.16 CONTRACT LINE ITEM OPTION NO. 16, ADD ALTERNATE #2, PILE REPAIR:
A. Pile Repair consists of furnishing transportation, labor, materials, and equipment to perform the repairs to damaged piles on the Fixed Wharf. The work includes but is not limited to installation of safety barriers, inspection of work, partial removal of existing steel shell, demolition and removal of damaged concrete, surface preparation of rebar, repair/installation of rebar, install pile jackets, preparation of concrete surfaces, placing concrete, grouting, removing scaffolding, repair of any defects, and clean up. A Type 2 Pile Repair includes the installation of rebar while a Type 1 Pile Repair does not.
B. Measurement will be made on a linear foot basis. The base contract quantity is 673 linear feet.
C. Payment will be made at the contract unit price per linear foot.
END OF SECTION 01 27 00
GOGA - 215726 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC Project Website.
7. Project meetings.
8. Environmental Coordination.
9. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction (Agency) – An agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.
B. Construction Permits – Contractor Provided – Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service (NPS).
C. Government Furnished Permits – Obtained by National Park Service (NPS), usually through the Architect/Engineer (A/E) or a consultant, during the design process and are usually concerned with impacts to resources protected by federal law.