Attachment9_Exhibit_G_ProposedSchedule.pdf
PDF 612 KB Posted
- Attached to
- Construction Management At Risk (CMAR) Terminal Restroom Modernization and Other Improvements Project
- Solicitation number
- 2026-RFP-080
- Issued by
- San Bernardino County, California
About this file
This is a proposed project schedule for a Construction Management at Risk (CMAR) Terminal Restroom Modernization and Other Improvements Project at Ontario International Airport (ONT) in California. The comprehensive program encompasses two primary projects: Terminal Restroom Modernization (federally funded and eligible) and Hold-Room Enhancement (non-federally funded), along with additional non-federal projects. The Design Phase spans 270 days from January 5, 2026, through January 15, 2027, with the ONT Restroom Renovation component scheduled for 216 days from January 5, 2026, through November 2, 2026. The design work progresses through defined phases including Concept (35 days), 30% Design (44 days), 60% Design (54 days), 90% Design (60 days), and 100% Design/IFC (11 days), while the Hold-Room project follows a parallel track with Schematic Design (70 days), Design Development (50 days), Issued for Permit (50 days), and IFC (30 days). The CMAR phase is scheduled for 257 days from January 6, 2026, through December 30, 2026, including an RFP Phase (144 days), Preconstruction Services (113 days), and Guaranteed Maximum Price (GMP) phases for both restroom renovations (33 days) and hold-room enhancements (28 days).
The schedule reflects a coordinated approach to design collaboration and construction services, with overlapping task timelines to optimize project efficiency. The Restroom Modernization Project involves replacing and upgrading aging facilities in Terminals 2 and 4, including widened ADA-compliant disabled access stalls, energy-efficient LED lighting, water-efficient fixtures, and temporary restroom construction to maintain passenger service levels during renovation. The Hold-Room Enhancement Project includes new seating with integrated power outlets, modernized gate electrical and data infrastructure, new carpet, and reorganized furniture arrangements to improve passenger flow. The proposed schedule demonstrates a phased delivery model with clear milestones, design progression checkpoints, and construction phases that coordinate federal and non-federal funding streams for the comprehensive terminal improvements.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish 1 Design Phase 270 days Mon 1/5/26 Fri 1/15/27 2 ONT Restroom Renovation 216 days Mon 1/5/26 Mon 11/2/26 3 SOW 70 days Mon 1/5/26 Fri 4/10/26 8 Task 1: Concept 35 days Mon 4/13/26 Fri 5/29/26 16 Task 2: 30% Design 44 days Mon 5/18/26 Thu 7/16/26 25 Task 3: 60% Design 54 days Mon 6/15/26 Thu 8/27/26 34 Task 4: 90% Design 60 days Mon 7/27/26 Fri 10/16/26 46 Task 5: 100% Design / IFC 11 days Mon 10/19/26 Mon 11/2/26 49 Holdroom 200 days Mon 4/13/26 Fri 1/15/27 50 Task 1 - Schematic Design (30%) 70 days Mon 4/13/26 Fri 7/17/26 53 Task 2 - Design Development (60%) 50 days Mon 7/20/26 Fri 9/25/26 56 Task 3 - Issued for Permit (90%) 50 days Mon 9/28/26 Fri 12/4/26 59 Task 4 - IFC (100%) 30 days Mon 12/7/26 Fri 1/15/27 61 CMAR 257 days Tue 1/6/26 Wed 12/30/26 62 RFP Phase 144 days Tue 1/6/26 Fri 7/24/26 63 CMAR Preconstruction Services 113 days Mon 7/27/26 Wed 12/30/26 64 GMP Restrooms 33 days Mon 9/14/26 Wed 10/28/26 71 GMP Holdrooms 28 days Mon 11/23/26 Wed 12/30/26
Design Phase ONT Restroom Renovation
SOW
Task 1: Concept
Task 2: 30% Design Task 3: 60% Design
Task 4: 90% Design Task 5: 100% Design / IFC
Holdroom Task 1 - Schematic Design (30%)
Task 2 - Design Development (60%) Task 3 - Issued for Permit (90%)
Task 4 - IFC (100%)
CMAR
RFP Phase CMAR Preconstruction Services
GMP Restrooms GMP Holdrooms
Dec '25 Jan '26 Feb '26 Mar '26 Apr '26 May '26 Jun '26 Jul '26 Aug '26 Sep '26 Oct '26 Nov '26 Dec '26 Jan '27 Feb '27 Mar '27 Apr '27 May '27
CMAR Estimate
Design Team Estimate
Task - Meetings
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: CMAR Restroom & Hol Date: Fri 4/3/26