This exhibit outlines inspection requirements for photovoltaic systems and batteries at Alcatraz Island. The inspection list details items to monitor and document for the solar panels in arrays A through D, including cell voltages, ohms readings, and component statuses. For the batteries, requirements include reporting on cleanliness, charging capacity, voltages, and operational condition for each bank. Inspections must also be performed for the battery inverters, battery room equipment such as dehumidifiers and monitoring systems, and documentation submitted per the contract terms. The related federal opportunity is a solicitation from the National Park Service seeking preventative maintenance services for these renewable energy assets at Alcatraz Island, as identified by solicitation number 140P8623Q0106.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT D – PV INSPECTION LIST
Provide reports per Section 9 of the contract.
1. Inspect all photovoltaic panels (Arrays A, B, C, and D). Report on cleanliness, condition of glass, operational status, and voltage and current per string. Items to be monitored and documented shall include at a minimum:
a. Intertier Connections
b. Lowest Cell Voltage
c. Highest Cell Voltage
d. Average Cell Voltage
e. Low Ohms
f. High Ohms
g. Average Ohms
h. Knife Switches
i. Current Sensors
j. Racks
k. Solar Sensor
l. PVA Conduit
m. PVB Conduit
n. PVC Conduit
o. PVD Conduit
p. All Disconnects
q. All Combiner Boxes
r. All Array Mounts
s. All Array Racks
2. Inspect all batteries. Report on cleanliness, condition of batteries, charging capacity, operational status, and voltage and current per bank.
3. Inspect Battery Inverters. Report on cleanliness, and operational status.
4. Inspect all equipment associated with Battery Room, items to be monitored and documented shall include at a minimum:
a. Dehumidifier
b. Temperature Sensors
c. Fire System
d. Bus Cables
e. Spill Kit
f. Eye Wash
g. Alber Battery Monitoring System for String A
h. Alber Battery Monitoring System for String B
i. Spare Cells
j. Overhead Fan