This is a Facility Manager Handbook for Cannon Air Force Base that provides comprehensive guidance for facility managers regarding their responsibilities, procedures, and requirements. The handbook outlines specific duties including submitting service requests, conducting facility inspections, managing key control, implementing force protection measures, handling emergencies, and maintaining environmental compliance.
The document details work completion processes, safety protocols, and facility utilization guidelines. Key areas covered include work classification priorities (from Priority 1 Emergency Work through Priority 4B Scheduled Enhancement), fire prevention responsibilities, hazardous materials handling, energy conservation requirements, and coordination with Civil Engineering services. The handbook includes specific procedures for situations like active shooter response, shelter-in-place protocols, storm/natural disaster preparation, and pest management. It also covers service contracts for grounds maintenance, refuse collection, and custodial services. The document provides relevant contact numbers and includes sample templates for facility manager appointment letters and facility abuse documentation.
View the file
Other files for this federal contract opportunity
Show all 50
Cannon AFB - Melrose Air Force Support Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA485521R0002
Attachment 21
Cannon AFB
Facility Manager Handbook
TABLE OF CONTENTS
I FACILITY MANAGEMENT
Facility Manager Purpose
Training
Primary Responsibilities
Terminology
Facility Abuse
II WORK COMPLETION
Work Classification
Submit Service Requests
Emergencies Outside Normal Duty Hours
Service Requests for Projects
Work Request Working Group
Work Request Review Board
Methods of Accomplishment
Work Flow Chart
III FACILITY SAFETY & UTILIZATION
Facility Inspection
Key Control and Locks
Anti-terrorism/Force Protection
Active Shooter Lockdown
Real Property
Fire Prevention
Space Heaters
Generators
Shelter In Place
Storm/Hurricane/Typhoon
Snow Removal
Pest Management
Mechanical Rooms
Energy Conservation
IV ENVIRONMENTAL
Hazardous Waste
Universal Waste
Asbestos
Lead-Based Paint
Paint Disposal
Mold
Spills
Recycling
Storage Tanks
V U-FIX-IT
VI SERVICE CONTRACTS
Grounds Maintenance
Refuse
Custodial
VII MISCELLANEOUS
Continuity Book
Important Contact Numbers
ATTACHMENTS
Sample Facility Manager Appointment Letter
Sample Facility Abuse Letter
REFERENCES
I FACILITY MANAGEMENT
Facility Manager Purpose
The facility manager (FM) is the assigning unit’s key player for matters regarding the care, maintenance, repair, safety, and security of facilities across the installation and off-base sites. Furthermore, the FM acts as a liaison between the unit and the 27th Special Operations Civil Engineer Squadron (27th CES) for facility issues. Establishing this relationship is important to understand and balance work requirements against funds, available resources, manpower, and base priorities to ensure work is completed.
*Though the majority of FM duties fall within CE AFIs, non-CE AFIs (DODI O- 2000.16V1-AFI 10-245, Antiterrorism (AT) Program Implementation, AFI 91-203 Air Force Consolidated Occupational Safety Instruction, AFI 23-204 Organizational Fuel Tanks, etc.) and publications internal and external to CE programs may define additional roles and responsibilities. The FM must ensure any facility related actions are coordinated with them to ensure additional impacts are mitigated, occupants and other mission partners are notified, and any applicable documentation is processed.
Training
In accordance with (IAW) AFI 32-1001 Operations Management, an organizational commander must appoint an individual in writing to perform FM duties. The 27th CES on AFI 32-1001 states that FM’s are designated by, and act on behalf of, the unit commander. The intent of this threshold is to better ensure the assigned FM has sufficient experience to handle the various requirements of the additional duty, ability to deal with their own customers and chain of command in explaining CE decisions and priorities (especially for rejected work), and a degree of communication and process skills to work with CE as a forward observer and first line of contact with maintenance issues.
Once appointed, the FM must attend initial training locally. After initial training is completed, refresher local training or revalidation must be completed annually as processes and/or policies can change.
For reference materials, policy information, and FM documents/templates visit the 27th CES FM SharePoint site https://org2.eis.af.mil/sites/13708/facman/Shared%20Documents/Forms/AllItems.aspx
Note: Training must be accomplished within 30 days of assuming FM duties
Primary Responsibilities
POC for matters requiring CE support
Submit service requests to CE Requirements section for repair, replacement, enhancement, minor and major construction work (IAW) AFI 32-1001, CE Work Management Playbook and local policies/directives
Secure assigned facility(ies) while maintaining an effective key control program (if facility found unsecure by SFS after hours, FM will be contacted to rectify the issue)
Ensure all Force Protection Conditions (FPCON) checklist items have been completed as FPCON changes occur
Implement Random Anti-terrorism Measures (RAM)
Ensure all emergency management natural disaster checklist items have been completed as weather conditions change
Develop unit emergency response procedures implementing instructions, e.g., shelter-in-place, and active shooter lockdown operations
Conduct facility spot inspections
Maintain the surrounding area within 50ft of facility
Maintain continuity book (binder or electronically-See Miscellaneous section )
Perform minor repairs (limited painting, light bulb replacement for lights 10ft and under, placement of rodent traps, ceiling tile replacement, etc.)
Submit requests for space allocation or reviews
Add inspection and cleaning of tracks for rolling doors such as hangar doors
Identify generator requirements and coordinate testing (as applicable)
Inform occupants of load shed plan and actions to implement (if applicable)
Terminology
Listed below are common terms you as a FM will need to be familiar with:
Requirements Section-The focal point for receiving, reviewing, processing, tracking and final disposition of all service requests.
Service Request (SR)-Used to request work requiring CE support i.e. repair, construction, removal
Work Task (WT)-Once a SR has been reviewed and approved it is transferred to the appropriate CE section for estimate and/or scheduling.
U-Fix-It Program–Allows facility occupants to accomplish minor repairs to facilities and FMs to check out specific materiel, tools, and/or equipment.
Real Property Installed Equipment (RPIE)-Government owned or leased assets/fixtures permanently attached or integrated into government owned or leased property.
Preventive Maintenance-Proactive approach to maintenance. Performance of function checks, oil changes, component lubrication, belt/filter replacement, etc. on a continuous schedule to prevent failure and prolong infrastructure/equipment lifecycles.
Facility Project-Work originally submitted as an SR which requires detailed planning and/or large in scope. Project is completed with CE in-house forces.
Opportunity-Due to the nature of the request it is deemed the work is beyond the capability of CE in-house accomplishment and must be considered for contract completion. The CE Engineering Flight handles/processes contract projects. Note: Contracts can be obtained by the requesting organization, however, work accomplished on Real Property must receive CE approval prior to submitting requirement to Contracting.
Work Request Working Group (WRWG)-Body of personnel who perform actions in evaluating work requirements and recommendations for possible presentation to the Work Request Review Board (WRRB). Evaluations consist of estimates relating to manpower, funding, labor-hours, and materiel. The WRWG includes personnel both internal and external to the 27th CES, with each individual contributing specific inputs relevant to their areas of responsibility. Through their collective expertise the overall goal is to determine the optimal course of action to be taken for each requirement.
Work Request Review Board (WRRB)-Meeting chaired by the 27th CES Operations Flight Commander which determines approval/disapproval and/or execution methods for work requirements (which were deemed detailed, complex, and/or large in scope) based on recommendations from the WRWG. Not all requirements reviewed by the WRWG are destined for a WRRB decision, but all WRRB decisions do require WRWG input.
Facility Abuse
Facility abuse is defined as damage or loss due to misconduct or negligence in the use, care, or safeguarding of real property facilities or systems. FMs and facility occupants have the responsibility of preventing facility abuse. If CE craftsmen respond to repair damages to a facility or a piece of real property and determine repairs are beyond normal wear and tear, the requesting unit’s commander will be notified with a letter alleging facility abuse (See Attachment Sample Facility Abuse Letter). Once notified a Report of Survey should be initiated by the requesting unit. In order to safeguard the occupants and facility, CE will only perform emergency repair to the damaged area. When the issue has been processed and resolved, a total repair will be completed. Facility abuse repairs may require reimbursement by the individual(s) responsible, if pecuniary liability is determined. If the FM discovers damage during spot inspections, add comments indicating possible facility abuse in the Note Section when submitting the SR.
II WORK COMPLETION
Work Classification
The majority of CE work falls into three categories maintenance, repair and enhancement. Constrained resources (manpower and money) have driven leadership emphasis on what CE should be doing by establishing a model that classifies and prioritizes work that drives optimization, and preserves our ability to sustain installations.
Our migration towards an enterprise wide asset management approach, is focusing our limited direct work hours in the most optimal means possible. The new methodology accomplishes this goal by requiring our most critical caretaker work, preventive maintenance and plant operations, is accomplished right after emergency response.
Work priorities contain two priority sub-elements, priority of work type as well as priority of corrective maintenance risk. CE performs three major types of work:
PM and Plant Ops, CM, and enhancement. Work Priority determines the order which work is scheduled and CE uses the following categories:
• Priority 1 Emergency Work - Emergency work represents immediate maintenance, safety, or mission risk and will be mitigated before all other work and within 24 hours. Objective is to eliminate the emergency hazard and/or perform a temporary fix until sufficient materials or resources are available to finalize the repair. All follow‐on work is prioritized as corrective maintenance
• Priority 2A Preventive Maintenance (PM)-Actions directed at maintenance and prevention of infrastructure and equipment failure or breakdowns
• Priority 2B Contingency Construction Projects-Contingency Construction Projects (CCP) are large sustainment or enhancement work, which focuses on ensuring military and civilians are trained and qualified to perform their assigned duties
• Priority 3A Scheduled Sustainment Work-High risk. Work which corrects life, health and safety deficiencies. This identifies the task as having the potential for high risk and left unattended could develop into a potentially worse situation. Also, follow up work to an Emergency (Work Priority 1) which has been downgraded.
• Priority 3B Scheduled Sustainment Work-Medium risk. Based on the scope of work And should be responded to in an expedited manner to prevent failure.
• Priority 3C Scheduled Sustainment Work–Low risk. Work that is low priority and low risk maintenance.
• Priority 4A Scheduled Enhancement – Low risk. Work that does not contribute to sustainment or continuity of mission operations AND is determined by base priorities.
• Priority 4B Scheduled Enhancement – Low risk. Work that does not contribute to sustainment or continuity of mission operations and potentially funded by other units.
Submit Service Requests
Requests for CE to perform any type of work i.e. repair, new construction, contract by requestor, and enhancements begins with creating a service request.
Additionally, service requests are required whenever new or replacement equipment is planned to be installed, before actual purchase.
Provide clear and concise location and description of the desired work, to include effect on mission, equipment and personnel as well as any supporting documentation (i.e. safety/fire write-ups, diagrams, sketches, and photos). Service requests will be sent back if not enough information was provided or if clarity is needed in order to properly process the request.
Example of clear descriptions:
Exact location (floor, room number)
Asset affected (toilet, HVAC, lights, doors, etc.)
How many rooms, floors, offices are impacted
Faucet drip-slow, steady, or fast
HVAC-running/not running, blowing hot/cold/warm air
Clog in bathroom-Is it the sink, toilet, or drain and how many are clogged o For toilet clogs occupants must try to unclog with plunger before submitting a request
Typically a service request will follow a specific pattern for completion. The FM identifies an issue and submits the service request in TRIRIGA (or where not applicable, the mandated IT system). The Requirements section reviews the request to ensure all applicable information has been entered. Once confirmed, Requirements personnel will create a work task, assign the appropriate workgroup and priority level. The workgroup (shop) receives the task and the Shop foreman reviews and schedules CE craftsmen to go to the location and assess the task. If the fix is simple, it can be completed on the same day it is scheduled. However, if more time and/or materials are needed, the Shop Foreman will determine the requirements, order parts if necessary, and schedule to return at a later date.
Note: There are no longer mandatory time frames (e.g., Routine-30 days, urgent-7 days, etc.) to complete work like there were in previous CE work management systems. The work priorities described in this guide principally apply to in-house Operations Flight and serve as a tool to prioritize limited work hours to accomplish workload received. Emergency requests will be responded to and mitigated within 24 hours.
Many USAF facilities are considered historical/cultural resources that must be maintained IAW the base Integrated Cultural Resources Management Plan to comply with federal and state regulations. Repairs and/or renovations must not negatively impact the integrity of these facilities. For questions on facility status under this classification, contact the Cultural Resources Program Manager at 784- 4985.
Emergencies outside Normal Duty Hours
The Requirements section telephone lines are transferred to the Fire Department Alarm Room after hours. Once description of the issue and contact info is provided, Alarm room personnel will contact the CE Standby Duty Officer (SDO) who dispatches standby personnel if an emergency. Otherwise, the issue will be handled the next duty day.
Listed below are typical emergencies in which standby personnel will be immediately dispatched.
Base power outages Generator starts/fails to start No heat in entire building if it's 24 hour work center
No heat in entire building if there is a threat of below freezing temperatures outside No HVAC in a critical building (SIPR/NIPR, Command Post, E-Lab, PMEL, etc...)
No heat or air conditioning in any occupied dorm room Bees/Wasps inside a building Poisonous snakes in building Broken water line in building Stopped up sewer in building (Not toilet) Impaired or out of service Fire Suppression system Water Main break Sewer Main stopped up/break Anything related to natural gas lines including regulators Damage to fire hydrants Fire alarm in alarm status, not trouble status Power (or other utility) out to mission critical facility Gate drop arm/pop up barriers (only if impeding traffic flow) Lodging facility with no power
Service Requests for Projects
As previously mentioned, service requests are required for any type of work requiring CE support. This includes requests which are large in scope, planning, materiel, multi-shop, and/or man hours. These type of requests may be renovations, enhancement work, new construction, MILCON, etc. and will need further review (see Work Flow Chart on next page). Note: Large scale projects requests may take months to be completed due to cost, manning, and/or time.
Submit requests when an issue is first identified instead of when the need is required.
Work Request Working Group
The Work Review Working Group (WRWG) provides initial review and evaluation of complex requests. Based on the evaluation, the WRWG makes a recommendation if the request should go to the Work Request Review Board (WRRB). If the WRWG determines a WRRB decision is not needed for a request, it will be sent to the appropriate work center for planning, scheduling, and completion.
Work Request Review Board
The WRRB is a meeting chaired by the CE Operations Flight Commander and attended by agency representatives from the Fire Department, Safety, Bio Environmental, Real Property, CE Engineering, CE Superintendents and potentially other representatives (Community Planner) whose input is beneficial regarding the impact of the requested work. Determination of approval or disapproval is made based off recommendations from the WRWG, the agency representatives, as well as applicable AFIs or polices (Operating Instruction, MAJCOM, and/or local process), projected work plans (future demolition, facility moves, construction, etc.), and work priority. If approved, the method of accomplishment is determined.
Methods of Accomplishment
The top methods to accomplish detailed complex projects are In-House, Opportunity (Contract Project), and Contract by Requester.
In-House-CE craftsmen will perform and complete the project
Opportunity- The CE Engineering Flight plans and programs the project to be completed by contract
Contract by Requester- Allows the requesting unit to pay and contract out the project. *CE will still be involved in contract activity (i.e. marking lines, turning power off, road closures, monitoring work accomplishment, inspections, etc.) Also, FMs must provide CE appropriate documents for capital improvement projects.
Work Flow Chart
Facility Manager Submits Service Request
R &O approves as appropriate work and CE responsibility
/creates Work Task
Is Detailed Planning
Required?
Assigns Priority/Shop to the Work Task
No Yes
Shop foreman reviews & schedules assessment
WRWG makes recommendation
*If WRRB not needed sent to shop
Sent to Ops Planning for initial review
Sent to WRRB
Approved Disapproved
Customer notified, provided reason for disapproval
Accomplishment method determined
III FACILITY SAFETY & UTILIZATION
Facility Inspection
Conducting regular facility inspections is an important aspect of FM duties.
Inspections allow any issues to be identified early before they become more serious and protects not only the facility and infrastructure but occupants as well.
Inspections should be conducted at least once a month with each record kept in the continuity book. At a minimum the below areas should be inspected
EXTERIOR ACTIONS YES NO
1. Is landscaping within 50ft from facility alive/trimmed and clear of debris/trash
2. Is there garbage, cigarette butts, or other debris around the facility?
3. Are weeds removed from cracks in sidewalks and parking lots?
4. Are exterior facility signs neatly displayed, not painted over and not falling down?
See UFC 3‐120‐01 DESIGN: SIGN STANDARDS
5. Are all exterior lights attached to the building in good working order? Are covers clean and free of dead insects? Are lights off during the day?
Shop will schedule work to be done
(If applicable) Materiel Ordered/Received
Shop Schedules Shop Schedules
Shop foreman schedules
Craftsmen complete job
6. Are all exterior area lighting (street lights, parking lot lights) in good working order?
7. Are smoking areas approved, clearly labeled and clean/free of trash and debris?
8. Are cigarette butt cans painted brown, 50ft from building entrances and set on level ground or concrete?
9. Are reserved parking signs approved and properly mounted?
10. Are dumpster lids closed?
11. Are all bulk items near dumpsters removed?
12. Are wasp nests and ant mounds present? Are they being treated?
INTERIOR ACTIONS
1. Are wall surfaces clean with no soot or dust from HVAC ducts?
2. Are all wall surfaces free of mold?
3. Are walls decorated with appropriate pictures/posters to include personal areas (no sexual images, profanity, or derogatory language, image/poster or magazines)
4. Are all mounted directional or function signs framed or otherwise finished in a manner that compliments interior design? Signs should be standardized to the maximum extent possible (color, font, design, etc.)
https://www.wbdg.org/ffc/dod/unified‐facilities‐criteria‐ufc/ufc‐3‐120‐01
5. Are all building directories, maps, and office designation signs clearly displayed and correct?
6. Do electrical outlets /light switches/phone/internet panels have faceplates which are not broken?
7. Do water fountains work? Are they clean and in good condition?
8. Are floor surfaces (carpet or tile) loose or frayed?
9. Are all doors closing properly? Is door hardware in good condition?
10. Are substantive holes left in wall from removed mounting devices/fixtures present?
11. Are toilets or sinks leaking? Are drains stopped up/slow moving?
12. Are thermostats securely mounted to the wall?
13. Are ceiling tiles clean, undamaged, and not warped?
14. Are all lights that are wired to motion sensors or timers working properly to conserve electricity?
15. Are all lighting fixtures operational?
SAFETY ACTIONS
1. Are all switches, receptacles, and junction boxes covered (where accessible)?
2. Are breakers labeled (where accessible)?
3. Are breaker switches free from being taped in the on position (where accessible)?
4. Does emergency lighting/exit lighting light up when test button pressed?
5. Are surge protectors overloaded or daisy chained?
6. Are there any loose cables or wires hanging from the ceiling?
7. Are smoke detectors mounted properly (not hanging)?
8. Are fire extinguishers securely mounted to the wall (if applicable)? Are they showing green for pressure?
9. Have fire extinguisher been checked monthly (if applicable)?
10. Are space heaters present? If so, is there an authorization letter from CE?
11. If accessible, are mechanical rooms clean and empty (other than machinery inside)?
12. Are all exits and walking paths kept unblocked and are free from objects in the way?
13. Are blocked doors clearly labeled “Not An Exit” and have been identified to Fire Prevention Office?
14. Is flooring (carpet, tiles, and linoleum) in good condition, providing no tripping hazards?
15. Are aisles and passageways kept clear to avoid creating a tripping hazard?
16. Function check automatic external defibrillators. Inspect for damage/tears of pads and verify expiration dates. Contact MDG for replacement.
After inspections are complete, brief occupants on safe practices, initiate corrective actions, and submit service requests for repairs.
Key Control and Locks
A basic component of facility security is maintaining proper key control. FMs should establish a Key Control log on AF Form 2427 Lock and Key Control Register or a locally developed spreadsheet and periodically review the type of access occupants have i.e. door, office, and/or master key (entire facility). Master keys should be limited to FMs and Unit CCs.
Keys must be returned whenever personnel PCS, deploy, PCA, go TDY (for more than 30 days), separate, or end employment. Tracking personnel movements can be difficult, especially in large facilities however, FMs should work closely with the Commander Support Staff (CSS) to be notified when one of these situations applies. A suggested best practice is for FMs to be added to the unit out processing checklist to ensure personnel return keys.
A service request must be submitted for any new key requests. If requesting a master key, a signed letter by the unit commander must accompany the request. The locksmith will fabricate the keys and only the facility manager (or First Sergeant in emergency situations) can sign for them. If key control is being poorly managed, units may be charged for additional keys and/or re-keying.
Based on mission, a facility may require electronic doors and openers or special locks. All must be submitted via a service request in NexGen IT or where not available via AF Form 332. Automatic opening doors are authorized for public use facilities. The doors are maintained and repaired by CE through a service contract. Electronically operated openers (buzzers) are authorized in facilities where personnel cannot leave their controlled area within a locked room e.g. command post and fire alarm room.
Cipher locks (electronic and manual) are an equipment item and are not provided for convenience. If installation is approved, the lock is purchased by the requesting organization. All electronic cipher locks must include a tamper timeout function which delays code entry after an erroneous code is entered. All manual cipher locks will include a key override mechanism compatible with the base standard key lock and must be reviewed by Lock Shop personnel prior to purchase.
Organizations, not CE are responsible for code changes, maintenance, and repairs.
GSA lock systems on real property vaults and SCIF doors will be installed and repaired by CE but combination changes and minor maintenance will be completed by the using organization.
* Lock replacements can be requested however, if it is due to obvious abuse, negligence, or vandalism, follow the process under Facility Abuse.
Anti-terrorism/Force Protection
The FM is a part of the AT program, and must develop and maintain a solid working relationship with the unit/agency AT officer (ATO) or representative (ATR). Execution of AT duties include, but not limited to:
Implement FPCON measures
Ensuring FPCON signs are posted on entry doors and current
Implement RAMs when directed
Report suspicious activity/package to Security Forces
Active Shooter Lockdown
The base will declare Lockdown conditions in the event of an active shooter attack.
Lockdown is a security measure to confine and restrict personnel movement.
Personnel may not enter or exit an area until all clear is given. If outside the immediate incident area, immediate actions include securing the facility by locking all entrance doors and listening for the base warning/notification system for information. If inside the immediate incident area facility occupants should do one of the following options that provides the greatest chance for survival: escape, barricade, or fight. See chart below for detailed information on each.
Active shooter response is not the sole responsibility of the FM however, FMs should brief, email, or post on information boards lockdown procedures and response actions for facility occupants.
For more information on Active Shooter actions see AFTTP 3-4 Airman’s Manual or visit the Air Force Be Ready site at www.beready.af.mil.
Real Property
The Real Property (RP) office accounts for and assigns facilities, identifies Real Property Installed Equipment (RPIE), oversees space management surveys, transfers facilities between organizations, space function conversion (warehouse to office), manages facility authorizations and space allocation and utilization.
RP assets include land, buildings, structures, utility systems, and improvements permanently attached to and integrated into a facility. Essential to the function of a RP asset is RPIE, e.g. generators, HVAC units. RPIE does not include movable organizational or collateral/plant equipment (ice machines, intercom equipment, system furniture, window AC, appliances and mezzanines). For a complete list of items considered RPIE and non RPIE visit the CE Dash website RPIE Determination section at https://cs2.eis.af.mil/sites/10758/CITCATCODE/_layouts/15/start.aspx#/RPIE%20 Determinations/Forms/AllItems.aspx.
Space requests whether temporary or permanent must be vetted through the Real Property Officer for coordination and approval. This includes using other DOD or non-DOD facilities and/or land which may require a real estate instrument.
Fire Prevention
A fire hazard is defined as an existing condition which, if not corrected has the potential to result in an undesired ignition, fire, or rapid spread of fire, causing personal injury, loss of life, loss of materiel and/or the destruction of property.
FMs are responsible for maintaining fire safety conditions and carrying out fire prevention tasks associated with their facility.
Primary fire related responsibilities include, but are not limited to:
Promoting fire safety
Performing monthly inspections of fire extinguishers
Accompanying fire inspectors during scheduled inspections
Initiating corrective actions for fire hazards
Ensuring evacuation plans are posted in highly visible areas and/or safety boards
Function tests emergency exit lights
Reviews, updates, or modifies evacuation routes
Fire Extinguisher Inspection
Not all facilities have fire extinguishers. Due to recent updates to UFC 3-600-01 and NFPA101, which are the primary sources for general purpose fire extinguishers requirements, contact your local Fire Prevention Office to determine if your facility requires them or not. Should the requirements exist, the unit and facility manager have management roles including, but not limited to, procurement, inspection, and training.
For facilities with fire extinguishers, inspections should be conducted monthly throughout the entire facility. IAW AFI 91- 203, paragraph 6.2.4.7 check the following:
Permanently Mounted
Located in a designated place
Accessible
No obstruction to access or visibility
Serviceable
Operating Instructions on name plate are legible and facing outward
Tamper seal not broken or missing
No obvious physical damage
No corrosion, leakage or clogged nozzle
Pressure gauge in operable range
Fullness
Documents
Signed service tag with last inspection date
Fire Inspector Inspections
In preparation for a fire inspection, FMs should review the previous inspection to familiarize with any past issues or situations. The inspection is documented on AF Form 218, Facility Fire Prevention/Protection Record. Once an inspector arrives, accompany him or her during the process. Correct any minor issues immediately and initiate any other corrective actions once the inspection is over.
During the inspection if there are any Fire Safety Deficiencies (FSD) or fire hazards found, the inspector will annotate on AF Form 1487, Fire Prevention Visit Report. FSDs are hazards that pose a risk to life and mission continuity.
FSD I greatest risk to life and mission continuity
FSD II significant risk to mission continuity and/or existing property capability
FSD III least risk to life, mission continuity and/or existing property capability
Impaired or Out of Service Fire Suppression
Whenever a fire suppression system which has been classified in UFC 3-601-02, Chapter 2 is identified (by FM, CE Craftsman, or Fire Department personnel) as impaired or out of service a service request will be generated and given Priority 1- Emergency status. IAW UFC 3-601-02 paragraph 1-11.2, if the issue cannot be corrected the Fire Department and FM must be informed and advised of mandatory system outage signs to post. The Fire Department will advise the FM of immediate measures to ensure personnel safety and mission continuance. If an impairment exists for more than 72 hours, measures must be implemented to ensure safety.
This may include having personnel perform “Fire Watch” in 2-4 hour shifts until the issue is resolved. For more information see UFC 3-601-02, NFPA 101 Life Safety, or call the 27th CES Fire Department at 784-2578.
QUICK REACTION STEPS
Upon smelling gas, do the following:
DO NOT ACTIVATE THE FIRE ALARM SYSTEM
1.) Immediately evacuate the facility 2.) Call the Fire Department at 784-2578 (or 9-1-1) 3.) Do not re-enter the facility unless directed to by Fire Emergency Services personnel NOTE: If the fire is small, use a fire extinguisher (if equipped) to extinguish the fire if possible. However, don’t risk the safety of yourself or others.
Upon spotting smoke or seeing fire, do the following:
1.) Pull the manual fire notification pull station—notify occupants by yelling “FIRE, FIRE, FIRE evacuate the facility” 2.) Evacuate the facility 3.) Contact the Fire Department at 784-2578 (or 9-1-1) Notify them of where the fire/smoke is located and any other pertinent information
Note: If the fire is small, use a fire extinguisher to extinguish the fire if possible.
However, don’t risk the safety of yourself or others
If foam has been dumped in a hangar, do not try to evacuate through the foam.
Seek alternate exits.
Space Heaters
Portable space heaters are not permitted due to safety, energy conservation and electrical circuit capacity concerns. Waivers may be granted for individuals with documented special medical needs.
In order for a waiver to be granted, documentation from a medical professional stating the need for a space heater with the required temperature range the unit needs to be maintained at.
If approved the space heater must meet the following specifications:
Underwriters Laboratory (UL) listed or Factory Mutual approved
Units must have a built-in tilt switch and a screen over the heating elements
All space heaters must have an electrical rating of 110 or 120 volts with no more than 550 watts electrical heat rating
To ensure safety, keep heaters at least 36 inches away from combustible materials and do not plug into an extension cord or multi-outlet strip.
Note: If a facility’s heat will be inoperative for an extended period of time, space heaters may be approved until heat is restored. Unrestricted use of portable space heaters is not permitted. It directly counters energy saving/reduction goals.
Generators
Depending on specific missions, some facilities may be equipped with a backup generator. IAW AFI 32-1062, Electrical Systems, Power Plants, and Generators, it is the FM’s responsibility to verify building equipment is functioning properly after semi-annual generator testing. Once verified, AF Form 487 Generator Operating Log must be signed.
FMs will confirm with CE the type of generator (automatic start or manual) which supports their building(s) and IAW AFI 32-1062 must maintain and post next to the generator a list of personnel who have been trained to operate the generator, i.e., startup procedures.
For tenant units, a service request must be submitted to have a generator connected to real property. Also, a Memorandum of Agreement (MOA) between the tenant unit and 27th CES must be established for proper operation and maintenance which incurs reimbursable costs.
Shelter in Place
The FM and unit Emergency Management representative are key to a successful Shelter In-Place (SIP) program (in some cases FMs fill both roles). SIP involves taking immediate temporary protection in a structure and sealing the area from outside air contaminates. Duration is usually short (2-4 hours) and is used in unexpected emergencies such as a hazardous material spill incident or weather hazard (tornado). Emergency Management Personnel will identify proper SIP room locations, occupant capacity and air calculations.
FMs should ensure facility occupants know the SIP location. This can be done using posters, safety boards, email, shop safety briefings etc.
SIP kits must be maintained in their respective area. The kit should be inventoried after every SIP exercise or at least twice a year. In order to quickly cover vents and openings, it is recommended to precut and mark plastic.
NOTE: The unit is responsible for restocking SIP kit materials
When directed to SIP, make every effort to notify personnel within the facility (runner, Intercom, phone etc.). Close/lock office windows, close/lock doors, and post SIP warning signs on exterior doors on the way to the SIP room(s). Turn off ventilation system if trained and authorized. Place plastic over air vents and secure with duct tape (if it is safe to do so). Place plastic over SIP room windows/openings (if any) and seal edges with long strips of duct tape. Ensure tape securely overlaps all edges of the plastic. Lock door to SIP room and seal door edges with long strips of duct tape. See figure below
Contact the 27th CES Emergency Management Flight at 784-4178 or email https://org2.eis.af.mil/sites/13708/CEX/default.aspx for complete local SIP program guidance.
Storm/Hurricane/Typhoon
FMs are responsible for emergency preparation actions for their assigned facilities.
This includes protecting the facility from flooding prior to hurricanes/significant storms by sandbagging low-lying entrances, mechanical room doors, basement windows and other exterior openings adjacent to flood-prone areas. To prevent facility damage, metal window shutters should be closed and locked (if applicable to location). Also, to prevent items from becoming projectiles, mobile equipment must be moved inside and exterior equipment secured. Units are responsible for the filling, placement, and removal of sandbags prior to, during, and after emergency conditions.
Snow Removal
FMs are responsible for the surrounding area of the facility within 50 ft. of the entrance. This includes ensuring facility entrances are cleared of snow and/or ice during winter weather months. FMs will only use approved ice melt products and use shovels or small portable snow blowers to clear paths and sidewalks leading to the facility.
The 27th CES conducts snow control operations for the installation IAW local plan. The plan details the priority in which streets and parking lots will be cleared by the CE Snow Control team. If your facility is not on the list please call the Requirements section to coordinate with the Snow Control team.
Sidewalks, intersecting driveways/sidewalks, and spillover caused by plows are not the responsibility of the Snow Control team.
Note: Units are prohibited from using rock salt around a facility or Entry Control Point within 300 ft. of the airfield, as this is a safety/FOD hazard.
Pest Management
FMs should maintain and promote a sanitary environment in the workplace and around the facility and try to alleviate any minor insect or rodent problems by using pesticides and traps before contacting the Pest Management section. Review the Base Integrated Pest Management Plan as it details procedures for individual pest management actions and approved pesticides and herbicides.
Keep the following in mind
Small animals such as squirrels do not pose a threat unless inside a facility however, contact the Entomology section for larger animals like raccoons, foxes, and skunks
Dead animals occur naturally however, if you notice multiple dead animals this could be a sign of disease and Public Health along with the Pest Management section should be notified
Perform weed control within 50 ft. of the exterior of the facility (sidewalks, flower beds, rock beds, etc.)
Prevent insect and rodent infestation o Remove cob webs regularly o Empty indoor trash receptacles daily o Store and dispose of food properly o Don’t leave food out overnight o Ensure all doors and windows are closed o Eliminate standing water o Inspect facility for gaps/holes that would allow creatures to gain entry
For questions on pest management and best practices contact the 27th CES Ops Management section at 784-2001 or review the CE Dash website Self Help Pest and Vegetation document at https://cs2.eis.af.mil/sites/10159/Shared%20Documents/Air%20Force%20Self- Help%20Pest%20Mgmt.docx.
Mechanical Rooms
A mechanical room’s purpose is to house critical facility equipment. The room is not for personal and/or office storage items such as furniture, boxes, signs, books, etc.
Mechanical rooms should be checked each time a facility spot inspection is performed.
*AFI 32-2001 storage is prohibited in mechanical, communication, electrical, and boiler rooms
Energy Conservation
The Department of Defense is the single largest user of facility utilities in the Federal Government. It is the responsibility of all personnel to promote conservation and efficient use of energy and water. FMs must email, brief, or post energy saving tips to occupants which include:
End of day shutdown of non-essential equipment i.e. printer/copier, shredders, and computer monitors
Turn off lights when area/office is not in use
Notifying FM of broken timed systems such as automatic lights and sprinkler systems
Prohibited items in personal office/cubicle such as aquariums, coffee makers, electronic picture frames and televisions
Keeping windows closed during heating or cooling season
Turn off outside lights during daylight hours (exception during inclement weather)
Ensure bathroom faucets and toilets are not leaking
Check outside water spigots for leakage
Federal law encourages the use of energy star rated products to reduce energy usage in future replacement or installation of electrical appliances. For a complete listing of Energy Star qualified products, go to http://www.energystar.gov.
For more energy and water conservation ideas contact the Energy Management office at 604-5899.
IV ENVIRONMENTAL
The 27th CES Environmental section oversees and develops guidelines for environmental concerns. An emphasis on environmental awareness has become more robust over the years. It is important for all personnel to know the potential issues related to toxic substances and possible impact on operations and personnel.
Hazardous Waste
Hazardous Waste training is not mandatory for FMs, unless you handle hazardous waste or operate a hazardous waste accumulation point for the facility. The Cannon Air Force Base Hazardous Waste Management Plan (HWMP) contains all details required for compliance. It is important to be familiar with the HWMP and understand which facility waste streams must be managed. Proper authorization, labeling and storage is required, along with time or quantity limits at the point of waste generation.
*For questions on storage and disposal of Hazardous Waste materials contact the Hazardous Waste Section at 784-1114. For environmental questions contact your Unit Environmental Coordinator (UEC) and/or the Environmental Management section at 784-1114.
Universal Waste
Batteries, thermostats, and fluorescent lighting contain hazardous materials. These items must be stored and disposed of properly in an approved universal waste container. It is critically important that waste containers be marked with the date waste is first put into the container and that the container be securely closed except when adding additional waste to the container. For used fluorescent lamps, the original container is recommended as a storage container.
Asbestos
Old buildings (constructed prior to 1980) have a higher risk of containing asbestos or asbestos containing material (ACM). ACM is typically found in ceiling tiles, floor tiles, carpet, sheetrock, siding, and insulation. It can be harmless while undisturbed however, if broken, frayed, torn, or peeling occurs it can cause fibers to be airborne resulting in a health hazard. It is important to obtain information regarding known or presumed ACM in your facility and to periodically ensure it has remained undisturbed. IAW AFI 32-1052, Facility Asbestos Management and the Cannon AFB Asbestos Operating Plan, asbestos testing/abatement must be performed prior to any work (to include minor spot painting) that might result in asbestos fibers becoming airborne.
Lead-Based Paint
This type of paint is usually found in old buildings as well (constructed prior to 1980). At the time, it was used due to its durability, moisture resistance, and drying time. If you have a self-help paint project which also involves stripping paint, materials must be tested for lead prior to work beginning. If lead is found, removal must conducted through the appropriate abatement procedure to ensure personnel safety.
Paint Disposal
Aside from lead based paint, regular paint may present a concern if not disposed of properly. If a can of paint is completely used, allow the can to dry before throwing it away. If there is paint left over after use, coordinate with the centralized Hazardous Waste/Pharmacy section for paint to be redistributed.
Mold
Due to weather, humidity, water leaks, and poor ventilation, moisture could become a concern leading to the growth of mold. It is the FM’s responsibility to clean a surface at or below 10 ft. at the first sign of black residue. Per the Environmental Protection Agency (EPA) website www.epa.gov, mold can be removed on nonporous surfaces using a solution of detergent and water. Bleach and water is not recommended, especially not on porous surfaces (wood and drywall). If residue is irremovable, on a porous surface, or above 10 ft. submit a service request.
Spills
Inform personnel on the importance of reporting any hazardous leaks or spills such as oil, fuel, sewage, or chemicals. If a spill of hazardous substances occurs, call the Fire Department immediately, and evacuate the facility. DO NOT contact outside agencies, as CE Environmental determines which spills require outside agencies and will coordinate base support requirements.
Recycling
Typical recyclable materials include office paper, newspaper, magazines, glass bottles, aluminum cans, plastic bottles, and cardboard. Non-recyclable items are window glass, Styrofoam, paper towels, carbon paper, plastic bags, food, and carpet. Alkaline batteries are not hazardous or recyclable and may be disposed of as regular trash. Brief or post information throughout the facility detailing location of recycle bins, prohibited items, and base Recycling Center contact information.
For questions on recycling or where to take items contact Environmental Management at 784-1114.
Storage Tanks
It is important for FMs to be familiar with the location of underground ground storage tanks (UST) and above ground storage tanks (AST) that support the facility and/or operations. In some cases the FM may also serve as the storage tank custodian in which the following duties will need to be executed IAW AFI 32- 7044 Storage Tank Environmental Compliance and AFI 23-204 Organizational Fuel Tank: monthly tank inspection, ensuring no spillage during the fill process, checking for water in the tank, maintaining tank records, providing notice of product changes, reporting suspected releases, maintenance and use of spill kits, and coordinating tank activation or deactivation. FMs should work closely with the UEC for training, records, and reporting. Contact the Environmental Management Tank Program Manager at 784-1114 for questions and compliance regulations.
V U-FIX-IT
The U-Fix-It program is managed by the CE Materiel Control Section located in bldg. 356. The program allows facility occupants to perform simple tasks such as minor repairs, replacements and ground maintenance which do not require special tools, materiel, or training. Additionally, a limited number of tools can be loaned out, but only FMs can sign for them.
The program serves as a way to accomplish minor maintenance projects which would be categorized as low priority for CE support.
Common approved tasks are as follows:
Spot painting
Light bulb and ceiling tile replacement (only within 10ft from floor)
Nut, bolt, or screw replacement
Light switch/electrical cover replacement
Toilet seat replacement
Tools/Materials available for checkout:
Rakes
Hammer
Wet/dry vacuum
Paint brushes
Paint
NOTE: Facility occupants are prohibited from performing any electrical work
VI SERVICE CONTRACTS
The CE Service Contracts section handles various contracts around the installation.
Services include grease traps, oil water separator, painting, port-a-johns (for base functions) etc. The contracts which affect FMs the most are Grounds Maintenance, Integrated Solid Waste, and Custodial. These contracts are subject to the Air Force Common Output Level Standards (AFCOLS) criteria which CE comply/enforce.
CE performs inspections of contractor work however, days and times are selected randomly.
Feedback from FMs is essential as it assists CE in certifying acceptable standards are being performed on a consistent basis.
Below is quick summary of the Top 3 Service Contracts
Grounds Maintenance
Under AFCOLS, only grass cutting around facilities is allowed. Other services such as hedge/bush/tree trimming and flower beds are limited to certain facilities.
If your facilities aren’t authorized to have those services then it is the FM/organization responsibility.
Refuse
The refuse dumpsters are placed strategically around the installation and are serviced on a specific schedule. Recyclable items, wood pallets and furniture (chairs, couches, tables, cabinets and desks) are not to be placed in the dumpster. They should be taken to the appropriate recycling location. Placing prohibited items in the dumpster will cause a delay in removal. NOTE: Dumpster lids should always be closed.
Custodial
Basic cleaning services (cleaning restrooms, selected vacuuming, and mopping) and restroom consumable item restocking are provided to maintain minimum essential standards for health and safety.
*The only person authorized to direct a contractor to perform a service is the Contract Administrator or the Contract Officer Representative
If there is an issue with contract performance, frequency, or questions contact the Service Contract office at 784-2519.
VII MISCELLANEOUS
Continuity Book
Maintaining a continuous history of a facility’s maintenance, service requests, and inspection results is imperative. FMs should regularly update the continuity binder for this purpose, and to facilitate an ease of transition during FM changeovers.
The continuity book at a minimum must be formatted (electronically or hardcopy) as follows:
Tab A FM appointment letter
Tab B FM training slides (provided after initial training)
Tab C Key Log
Tab D Log of service requests and/or facility projects submitted
Tab E FM Periodic Spot Checks
Tab F Various Fire Prevention/Safety paperwork (Fire inspection, write-ups-maintain for one year upon completion of write-up)
Tab G Known asbestos or lead health hazards
Tab H Emergency Management and Force Protection (checklists and FPCON signs)
Important Contact Numbers
GeoBase (Maps) 904-5349
Service Contracts 784-2519
Fire Protection 784-2578
Environmental Management 784-1114
Real Property Officer 784-6961
Energy Management 604-5899
MDG Bio Environmental 784-4063
Emergency Management 784-4178
Command Post 784-2253
SFS/ Base Defense Operation Center 784-4111
Wing Safety 784-4471
U-Fix-It Store 784-2075
ATTACHMENTS
Sample Facility Manager Appointment Letter
Sample Facility Abuse Letter
46Page 2
REFERENCES
AFI 10-2501, Air Force Emergency Management
AFI 23-204, Organizational Fuel Tanks
AFI 32-1001, Operations Management
AFI 32-1053, Integrated Pest Management
AFI 32-1052, Facility Asbestos Management
AFI 32-1062, Electrical Systems, Power Plants, and Generators
AFI 32-1064, Electrical…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .