Att12d_CSF_Questions_and_Answers_5-19-22.pdf
PDF 426 KB Posted
- Solicitation number
- 140P2022R0100
About this file
This document contains questions and answers related to solicitation number 140P2022R0079 issued by the National Park Service for the construction of support facilities for a transcanyon waterline project at Grand Canyon National Park. The solicitation seeks bids for the construction of a pre-engineered metal building, operations building, campground, and other site improvements. Key details include specifications for materials like aggregate, asphalt, pipe insulation and tile. Clarification is provided on requirements for tree removal, borrow sites, construction water access and rates, permits, site access and laydown areas. The response deadline was extended to May 23, 2022.
View the file
Other files
Show 40 more
Latest 50 of 93 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GRCA 250176 - Construction of Support Facilities for Transcanyon Waterline Project, Grand Canyon National Park
Solicitation 140P2022R0079 - Questions and Answers
1. Page 50 of 56, Factor 3 – Key Personnel Experience states, “Submit resumes, 1 page for key personnel.” Just to clarify, is that 1 page per resume?
Answer: Yes 1 page per resume.
2. Page 51 of 56, Factor 6 – Past Performance says Past Performance Information Retrieval System
(PPIRS) evaluation reports can be submitted in lieu of Past Performance Questionnaires (PPQ).
Can we submit PPQs that have been previously submitted for other proposals in lieu of asking references to fill out a new PPQ?
Answer: Yes, you can use previous Past Performance Questionnaires.
3. Does the park have any flexibility on the schedule for this project? We understand that the park wants this to be done at the earliest and the specs have the period of performance from this July but the some of the materials, specifically the PEMB has a long lead time of around 30 weeks which would push the building out. How is the park dealing with the material cost escalation and variability?
Answer: Contractor's should forward their approach and schedule based on current market conditions and lead time of equipment and material.
4. ABC - Plans call for ADOT Class 3. Per ADOT Spec Section 303, the ADOT Class 3 is misc.
specification that points to the project’s special provisions for spec requirements. Please confirm specific requirements for ABC - options might be MAG-spec ABC, non-spec ABC, ADOT Class 2, or whatever is locally available.
Answer: ABC material sieve spec is included in 32 15 40 paragraph 2.1.C. An ADOT or MAG-spec ABC will be acceptable.
5. Crushed aggregate surface and ABC surface - In lieu of ABC, would raw Millings/RAP (recycled asphalt pavements) be an acceptable alternate to help save on cost and provide a better driving surface?
Answer: Crushed aggregate- Park would prefer a compactable material, millings/chip rock will remain loose, while cheap they will be easily displaced and harder to maintain. RAP/asphalt millings are good as long as there are binding fines present that will allow the surface to hold compaction and retain a bit of moisture.
6. Rock Removal & Excess Material - Does NPS have a designated haul location for rock and excess materials? Dry or wet dump?
Answer: Rock and excess material staging, the dump/landfill can be used. We can identify an area for material staging as requested,
7. Field Office - Will NPS be proving electrical and data connection for the job office trailer?
Where exactly are those connections?
Answer: Not supplied by the Park, however, Hughes Net and Starlink satellite contracts can be purchased. Verizon and AT&T have towers in the park with strong signal so a cellular hot spot should be available as well, and may be the quickest solution to use.
8. New Roadway Connection to US64 - Is US64 an NPS road or ADOT highway at the connection point? What are permitting requirements and fees (if any) as well as anticipated traffic control requirements on US64 (signs, message boards, etc.)?
Answer: US64 is under NPS jurisdiction and no permits are required with ADOT. Contractor shall submit traffic control plan per paragraph 1.4A.
9. Job Laydown Areas - Other than the onsite staging areas identified on the plans, are there other stockpiling, staging, and contractor parking areas within the job vicinity to help avoid congestion and safety concerns within the project limits?
Answer: Park will work with DSC and Contractor to identify initial staging and laydown areas until trees can be cleared etc. It all depends on the season and the space need. Short term uses will be easier to accommodate than for the duration of work. The park landfill area south of the project area is the most likely spot for short and long term staging/ storage until the project areas are complete enough to bring those activities within the limits of construction.
10. Existing Utilities - Are there any existing utilities within the excavation limits that we need to be aware of? Will public utility locating (bluestake) cover identification of all existing utilities or does a 3rd-party private utility firm need to be included to help locate private utilities?
Answer: All known utilities to the engineer are shown on the drawings. A 3rd party utility locate will be required in addition to bluestake.
11. Please provide a spec for pipe insulation
Answer: Pipe insulation is in section 40 42 00
12. Are horizontal aluminum blinds to be included in base bid? Referenced in the spec book but not shown on plans.
Answer: Aluminum blinds are required on all exterior windows per section 12 21 13, para 3.5.
13. Are window stools part of base bid? Shown as dashed in plans but noted in specs.
Answer: Stools are shown for spatial representation only and are not in the scope of work.
14. How are we to handle future material pricing escalation?
Answer: FAR Clause 52.216-4 Economic Price Adjustment clause will be added to the solicitation.
15. Please specify product/material for Ceramic Tile (CT). Specs indicate "as specified in Drawing Finish Schedule" but a product selection is not shown in the provided Finish Schedule.
Answer: Section 09 30 00, replace para 2.1.A.1.a with the following:
1. Base:
a. American Olean
b. Crossville
c. Daltile
16. Specs indicate a Type A single tier 18" x 18" x 72" locker, plans show a double tier, please confirm which type of locker should be provided and installed?
Answer: Section 10 51 13, replace paragraph 3.4.A.1 with “Double tier locker 18”x18”x36” each”
17. Specs indicate a locker bench, but plans do show a locker bench on the floor plan. Please confirm if a locker bench is to be provided and installed. If so, please provide dimensions for pricing purposes.
Answer: Bench is shown on the drawings in the shower dry area.
18. Please confirm model # for Undercounter dishwasher is GE GDT226SSLS, GE GDT226SSLSS is the only model # that is found.
Answer: Proposed model number is acceptable
19. Please confirm commercial reach in refrigerator is Arctic Air AR49 and not Artic Air AR49
Answer: Proposed model number is acceptable
20. Please confirm built-in cooktop model # is GE PP7030EJESS and not GE PP7030EJES
Answer: Provide model number specified (slate).
21. Is design and sizing of anchor bolts to be included with PEMB design? 5/S500 includes an Adhesive Anchor Bolt Schedule defining anchor bolt diameter and embedment length.
Specifications indicate to "Size anchor bolts and base plates assuming 3000 PSI concrete "
Answer: Anchor bolt layout and diameter shall be designed by the PEMB manufacturer as indicated on drawing 06-S101.
22. Can Floor mount toilets be substituted for the wall mounted models?
Answer: Janitorial staff prefer wall mount always over floor mount for ease of floor and toilet cleaning. Please remain with the specification for wall mounted WC’s as stated in section 22 20 00 2.2 A. 1. g. 1
23. Is there a Hot water recirculation system as required by code?
Answer: Per IPC 607.2, recirculation pump is only required if longest length of hot water pipe exceeds 50ft. Our longest length is approximately 41 LF of Hot Water Pipe.
24. Is there a water softener system to protect the water heater and other fixtures?
Answer: Domestic water will serve water heater and fixtures throughout building as shown.
25. Is water meter supplied by GC utility?
Answer: There is a water meter at the Lapp Loop Location
26. Is a borrow/import material site available within the Park or is the contractor to import material from an outside source
Answer: There are no borrow areas in the Park for contractors. Imported materials should follow specification section Earthwork 1.4 A. 3. a.
27. Please confirm that the existing site can be used for rock crushing operations if needed and that crushing operations do not have to occur at another location within the park where hauling would have to be figured both ways.
Answer: It can be done on within the limits of construction.
28. Please confirm the construction water source(s) location and type of connection for this project.
Please confirm if there is a charge for water usage.
Answer: We allow USFS to get water at Lapp Loop. Park is required per DO 35B to recover utility costs and requires us to charge for water, current rate is $0.18/gal. Contractor can bring in a water tank/tower as long as it fits within the construction limits.
29. Please confirm specifically what permits the contractor is responsible for including cost for in the bid.
Answer: Contractor is responsible for identifying permits in accordance with 01 31 00, para 1.9.
Note that reference to “Division 15” is not clear as this is not the specification format. GRCA is the AHJ. SWPPP permit is required from the county or state as listed in the 013100.
30. Please confirm if vaccinations are required to work in the park premises.
Answer: Offerors are required to adhere to the solicitation clauses.
31. Can a bid date extension of 2 weeks be accommodated for this project?
Answer: The proposal due date is extended to Monday, May 23, 2022 at 1500 MT.
32. Please confirm that the schedule (factor 4) to be required along with the proposal is to have the
NTP as January 15,2022 and not the period of performance starting in July 2022.
Answer: For bidding purposes, the Period of Performance is July 1, 2022 to June 30, 2023. The actual Notice to Proceed will be issued after Award and after all of the Division I submittals are in and accepted, typically 30 days after award. From that date, the contractor will have 365 days.
33. Are there any data connections for the job office trailer?
Answer: Not supplied by the Park, however, Hughes Net and Starlink satellite contracts can be purchased. Verizon and AT&T have towers in the park with strong signal so a cellular hot spot should be available as well, and may be the quickest solution to use.
Amendment 02 – Issued 5/4/22
34. What are the live load requirements for the mezzanine?
Answer: Elevated Mezz Live Load: 65 psf
35. Please confirm the elevator will be self supporting and not supported by the PEMB structure.
Answer: The elevator jack will be supported off the mat foundation at the elevator pit. Contractor shall include any structural provisions required for construction.
36. Would providing the G-90 which triples the galvanizing protection than the G-30 be an option?
This would not require additional acrylic coating.
Answer: The reference to this question is unclear, please provide drawing and specification number for context.
37. Do they want blue for data, white for voice? Since all cable will be C6a, should we just use blue cable for both?
Answer: Per Section 27 10 00 (Paragraph 2.12) provide white cable for voice and blue cable for data.
38. Do we need to provide any cable to the construction trailers and the Contractor Residential area on 06-E103?
Answer: HDR: Per drawings 06-E101 through 06-E104 and 06-E505:
• Empty conduits with pullstrings from the helibase to the three construction trailer locations. No communications cables are installed, but conduits are available for use.
• No empty conduits for comms cabling to the RV sites.
• Power to all locations will be installed by APS per their design. Trenching and conduits will be installed by the contractor, and the actual power cables provided and installed by
APS.
39. Are we required to have a RCDD for this project?
Answer: Per Section 27 10 00 (Paragraph 1.4.A.3) fabrication and/or layout drawings must be sealed and approved by an RCDD.
40. Will there be any paging speakers? We didn't see any on the drawings.
Answer: Not included in contract.
41. Will they need any cameras?
Answer: Not included in contract.
42. Per 06-E105, we only see one wireless access point in the hangar. Is this the only one needed?
Answer: Only one wireless access point is required in the hangar.
43. Do we need to include patch cables from the patch panel to the switches? If so, what lengths?
Should we provide any extra for growth? Please see page 22, 5.3 Patch Cables (Panel) of B08_Attachment_5_Structured_Cable_Plant_Standard.
Answer: Per Section 27 10 00 (Paragraph 2.10) provide patch cords equal to 1.1 times the number of cables terminated in the communication rooms. Lengths shall be as required to reach from patch panels to switches.
44. Do we need to include patch cables from the IMO to the workstation? If so, what lengths?
Should we provide any extra for growth? Please see page 22, 5.2 Patch Cables (Workstation) of B08_Attachment_5_Structured_Cable_Plant_Standard.
Answer: Per Section 27 10 00 (Paragraph 2.11) provide patch cords equal to 1.1 times the number of jacks installed. Lengths shall be as required to reach from jacks to workstations.
45. Please confirm if we are to use 50 Micron fiber and LC connectors.
Answer: Per Section 27 10 00, provide multi-mode (50 micron cable) with LC connectors.
Provide LC-SC fiber jumpers where necessary to connect to legacy SC-connector systems.
46. Do we need to match existing building manufacturers in the new building for cabling equipment?
Answer: Matching existing cabling equipment manufacturers is not required.
47. Please provide clarification on the IT Room rack or cabinet. Per 06-E106, it mentions a wall mounted network equipment rack for IT Room 206. We would recommend a 7ft floor mount relay rack.
Answer: Section 27 10 00 (Paragraph 2.2.A) requests a wall-mounted open frame equipment rack. Contractor may provide a floor-mounted rack at their option.
48. Should we provide ladder rack on three walls of the IT Room?
Answer: Ladder rack is not required, but may be provided at Contractor’s option.
49. Is there space in the fiber LIU in the existing Helibase bldg and the Firehouse to add 12 strand of fiber? If so what is the manufacturer so we can add the appropriate hardware if needed.
Answer: Spare capacity of the existing LIU units is unknown. Provide new 1U-size LIU/fiber patch panel for termination of new fiber optic cables.
50. The RFP lists contractor’s key personnel as Superintendent, On-site QC Manager, and On-site Safety Manager. Are all three positions required to be full-time, on-site personnel at all times during the project? Is it allowable for one person to fill multiple onsite roles for this project?
Answer: An individual can fill multiple roles.
51. Please confirm tree removal is not a part of scope per Delta #1/Sheet X100 at Heli base area. Per site walk, it was referenced that GC was to remove the trees at the Heli base. Line item #6 in bid schedule also makes reference to removal of trees that are not part of GC scope per plan set.
Answer: Trees are to be removed. See PROJECT SPECIFICATIONS Section 31 10 00 SITE CLEARING and Attachment 9 of the solicitation.
52. Please confirm Government will remove trees for Access Road prior to construction per 2/X102.
It was referenced several times on the site walk that the GC was to remove trees. Per the prior solicitation this is the case, but Delta #1 shows otherwise.
Answer: Trees are to be removed. See PROJECT SPECIFICATIONS Section 31 10 00 SITE CLEARING and Attachment 9 of the solicitation.
53. Please confirm elevation of existing utility pole per 20/X100
Answer: This elevation is to be confirmed by contractor and relayed to CO
54. Are we to assume fill is suitable for pricing purposes? (Geo-Tech Report Section 5.1/page 8)
Answer: Assume it is. If not, an equitable adjustment will be made
55. Are we to assume subgrade is stable for pricing purposes? (Geo-Tech Report Section 5.2/page 8)
Answer: Assume it is. If not, an equitable adjustment will be made
56. Tree Removals - Does NPS have a designated haul location for removed trees to help save on cost? Are there NPS or F.S. fees associated with removing trees and, if so, what are the fees?
Answer: No. the NPS only has a location to sort and load out.
57. Tree Removals - Does NPS have a designated haul location for tree stumps to help save on cost?
Dry or wet dump?
Answer: No. the NPS only has a location to sort and load out.
58. Tree Removals - Despite what’s identified on the plans, will NPS be flexible on the tree removals that are ‘required’ to be removed for construction purposes? For example, trenched utilities likely require drill and shoot and large excavation equipment due to the rock. Trees will likely need to be removed to allow for adequate access of large equipment, open trenching, trench spoils, and materials.
Answer: Yes, on a case by case basis.
59. Construction Water - Will construction water be provided by NPS and is so, where exactly and what is the output (Gal/Min)? Any fees? Is there room for an adjacent water tower?
Answer: Park is required per D 35B to recover utility costs and requires NPS to charge for water, current rate is $0.18/gal. Contractor can bring in a water tank/tower as long as it fits within the construction limits. There is an NPS meter
60. Contractor Workers - Are there onsite camp locations or other areas that will accommodate workers? Hotels and trailer campgrounds in the greater area are VERY expensive.
Answer: Contractor work crews may dry camp in RVs within the limits the construction site.
61. Can the below verbiage as part of Attachment 09 Clarifications be modified to show a 250-mile radius? The specs show a specific type of elevator with limited installers who are in Phoenix and the existing 200 mi radius is not sufficient.
Answer: 250 mi radius is allowed.
62. Are there any necessary permits that need to be obtained? Division 15, Spec 1.5 Permits, indicates to "obtain necessary permits from municipal authority having jurisdiction". Are there any associated costs with this type of permit?
Answer: Contractor is responsible for identifying permits in accordance with 01 31 00, para
1.9. Note that reference to “Division 15” is not clear as this is not the specification format. The SWPPP permit is from the county or state as listed in the 013100. Any APS work requires permits per APS. The park is the AHJ and does not require any permits.
63. There is a bid item on the bid schedule #6 for Heli base Tree Removal. This item is not listed in section 012700- Definition of Contract Line Items. Please refer to civil demolition drawings sheet 06-X100 thru 06-X102. It appears per the red crossouts and not in contract Note (Delta 1) that tree removal will be by others and not part of this contract. Specification 3.4 on sheet 024100-5 confirms this scope is by others. Please confirm that bid item #6 should be removed and that tree removal is not a part of this contract per the documents provided.
Answer: Tree removal is part of the contract. See B08_Attachment_9_Clarifications
64. Will NPS be removing the stumps along with the trees?
Answer: Tree removal, including most stumps, is part of the contract. See B08_Attachment_9_Clarifications as part of solicitation.
65. Will a Sand and Oil Interceptor be required for the drain in the Hanger Bay? If so, will a separate sewer line be run to the interceptor location outside the building? How large will the Interceptor need to be, and will it have to be traffic rated?
Answer: A sand and oil interceptor is not required.
66. Is it possible to utilize PG 64-2a mix in lieu of PG70-10? Using a local mix will reduce cost.
Answer: The question’s reference to PG 64-2a is not clear. Make the following changes by addendum to Section 32 12 16, paragraph 3.1.C: Remove references to PG 70-10 and add the following: In accordance with City of Flagstaff revisions to MAG, the asphalt to be mixed with the mineral aggregate shall be paving grade asphalt conforming to AASHTO Designation MP1, Standard Specification for Performance Grade Asphalt Binder and shall be 58-28 unless otherwise specified in the special provisions. AC 20 conforming to Section 711 may be used if PG 58-28 is not available.
67. Will the new concrete helipad have in slab heating?
Answer: Concrete helipads are not heated.
68. Please confirm collateral loads for this project for the PEMB structure.
Answer: Refer to note G3 on sheet 06-005 for design criteria including dead loads.
69. Please refer to addendum 1 question and answer #6. It is understood that excess rock and dirt can be permanently disposed of a the NPS dump/landfill within the park if needed. Please confirm.
Answer: Rock and excess material staging, the dump/landfill can be used. We can identify an area for material staging as requested
70. Please confirm if the contractor is to include the actual water meters for the domestic water services for the proposed campground. Please confirm if the contractor is to include the 6” water meter for the fire line for the helibase. Just confirming that all these meters will not be provided by others.
Answer: Contractor is responsible for supplying water meters.
71. Please confirm if there are any special coatings required for the new proposed sewer manholes for this project.
Answer: Section 33 05 16 Precast Concrete Manhole Structures shall be added to the specifications (attached).
72. Please confirm if imported cinder sand is acceptable for use as bedding and shading of utilities.
Answer: Granular bedding material shall be ASTM 2321 Class 1b per spec 31 23 33.
73. Please confirm if imported cinder based structural fill is acceptable for use as offsite borrow for general fill for this project.
Answer: Structural and non-structural fill shall be in accordance with 31 23 00, paragraph 2.1.A.
74. Please confirm is a regular temporary fence would be acceptable in lieu of the 4’ orange fence per the plans
Answer: Temporary fencing at least 4 ft height and in good condition will be acceptable.
75. Please confirm if the lockers in the hanger and the bathroom lockers are the same. If not, can you please provide specifications?
Answer: The lockers in the hanger and bathroom are the same as specified in section 10 51 13.
76. Please confirm if Schluter is required between wall tile and floor tile
Answer: No trim on floor.
77. Please confirm of Schluter is required at outside wall corners and wainscot cap
Answer: Yes, trim as described in 09 30 00, paragraphs 2.3 L and M.
78. We wanted to know if there are any procedures or requirements currently in place having to do with helicopter safety. For example, positioning of cranes, etc.
Answer: The new operations building will be constructed adjacent and active helibase as shown on the drawings. Contractor to coordinate all construction activities with the helibase management.
79. Can we get .dwg files to assist in our take-off.
Answer: These are not available for distribution during the solicitation period.
80. Please refer to addendum 1 question and answer #28. Please confirm that the charge for construction water is $.18/Gal and not $.18/1000 gallons. Is the water at Lapp Loop potable water? Please confirm if reclaimed water is available from the treatment plant or another place in the park for this project for earthwork operations and dust control as allowed on previous projects for free. If this is available, please confirm if it is free or if there is a charge.
Answer: Yes, it is .18/gal (one gallon). There is a meter now we use for another customer. The park will install one for contractor use (meter). Lapp Loop water is potable. There is reclaimed water but not in significant quantities, park can work the with contractor for specific needs. The fill location would be within the WWTP compound at the reclaimed water pump house.
Both wet and dry can be taken to either the dump and/or the landfill. Again, depending on the quantities etc the park will work with the contractor as to which site will be used. The dump and the landfill are in the same general area. (1/4 mi between the two).
81. Will a hazardous materials report for the demolition involved be provided for the project?
Answer: A hazardous materials report is not available.
82. How far is it from the existing telecom pedestal to the building and how many new landlines are needed for the project?
Answer: Pedestal is shown on drawing 06-E101. The Contractor needs to install conduits and pull the wires shown on the drawings.
83. On page 51 of the solicitation under SMALL BUSINESS PARTICIPATION it states "All offerors (both other than small businesses and small businesses) shall submit Small Business Participation documentation that address and on page 52 of the solicitation under 3.
CONTENTS: SMALL BUSINESS PARTICIPATION it states; small business offerors are not required to submit a subcontracting plan. Can you please clarify if this is or is not a requirement for a Small Business?
Answer: The purpose of the Small Business Participation Plan is to assure the large businesses is able to meet the goals.
84. Please provide the sizes or style for the tiling in the restrooms.
Answer: The tile sizes graphically represented on drawing 06-A012 are 12”x24” and 12”x12”.
85. Please advise if powder coating can be used in lieu of the painting for the fencing.
Answer: Powder coating will be acceptable and shall match the color of existing fence.
86. Please provide specifications section 33 05 16 for the Precast Concrete Manhole Structures.
Answer: Attached section 33 05 16
87. Are there permit requirements for crane usage onsite?
Answer: There are no NPS permit requirements for cranes. Contractor shall coordinate crane setup and operation with helibase operations.
88. If we were to add electronic tabbed dividers to our SOQ, are those counted in the page count?
Answer: No