Addendum_3_RFB DOS 2025-03.pdf
PDF 89 KB Posted
- Attached to
- IPOC BUILDING UPS REPLACEMENT State and local contract opportunity
- Solicitation number
- RFB DOS 2025-03
- Issued by
- Merrimack County, New Hampshire
About this file
This is Addendum 3 to RFB DOS 2025-03 for the IPOC Building UPS Replacement project in Merrimack County, New Hampshire. The addendum addresses two questions related to the project execution. The document confirms that all work can be completed during normal business hours.
The addendum clarifies that electrical compliance must meet both National Electrical Code (NEC) and New Hampshire state law requirements. The vendor is responsible for all permitting and inspection requirements, including any associated scheduling and costs.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Addendum_3_RFB DOS 2025-03.pdf | ||
| RFB DOS 2025-03.pdf | ||
| Addendum_1_RFB DOS 2025-03.pdf | ||
| Addendum_2_RFB DOS 2025-03.pdf | ||
| Addendum_2_RFB DOS 2025-03.pdf | ||
| RFB DOS 2025-03.pdf | ||
| Addendum_1_RFB DOS 2025-03.pdf | ||
| addendum-2-rfb-dos-2025-03.pdf | ||
| addendum-1-rfb-dos-2025-03.pdf | ||
| rfb-dos-2025-03.pdf | ||
| RFB DOS 2025-03.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFB DOS 2025-03
ADDENDUM 3
Questions and Answers
RFB DOS 2025-03 Page 1
# Page No. Section No. QUESTION ANSWER 1 General Question Can all work be completed during normal business hours?
Yes
2 General Question Is an inspection required upon completion of the project?
If yes, who is responsible for the scheduling/cost of the inspection?
Electrical compliance in New Hampshire is governed by the National Electrical Code (NEC) and state laws. All work done must comply to both. Vendor is responsible for all permitting, and inspections.