ADDENDUM #2.pdf
PDF 127 KB Posted
- Attached to
- Snowden Training Center Mechanical Upgrades
- Solicitation number
- ANC-C-25-0011
- Issued by
- Anchorage Municipality, Alaska
About this file
Addendum #2 is an official document issued by the Alaska Court System for the Snowden Training Center Mechanical Upgrades project (Project No. ANC-C-25-0011). This addendum, dated May 5, 2025, modifies the original Invitation to Bid by removing three (3) unit heaters in the warehouse section of the building from the procurement scope. The submittal date remains unchanged, with bids still due on May 14, 2025, at 12:00 PM. All other specifications and requirements from the original bid documents continue to be in effect.
The addendum does not introduce any changes to pricing, set-asides, or other contract terms beyond the removal of the specified unit heaters. It serves as a clarification to bidders, ensuring they are aware of the updated project scope while maintaining all other original bid parameters. The document is part of the standard procurement process for the Alaska Court System's mechanical upgrade project at the Snowden Training Center, following the organization's procurement guidelines and maintaining transparency in the bidding process.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #2
Snowden Training Center Mechanical Upgrades Project No. ANC-C-25-0011
Date: May 5, 2025
To All Plan Holders:
The following changes, additions, clarifications, and/or deletions are hereby made a part of the Contract Documents for the above noted project, fully and completely as if the same were fully contained therein. All other terms, conditions, and specifications of the original Invitation to Bid remain unchanged.
This amendment must be acknowledged in the space provided on the Bid Schedule.
The Submittal Date and Time is UNCHANGED. Submittal Date is: May 14, 2025 at 12:00 PM
The modifications directed by this Addendum #2 are described on this page.
Addendum #2
The three (3) unit heaters in the warehouse section of the building are being removed from the ITB. All other specifications and requirements remain unchanged.
End of Addendum #2