Bldg_4715_Asbestos_Survey_Report_Final.pdf
PDF 5 MB Posted
- Attached to
- Central Steam Distribution Replacement Phase 2 Federal contract opportunity
- Solicitation number
- 80MSFC18B0003
About this file
Bldg 4715 Asbestos Survey Report Final
View the file
Other files for this federal contract opportunity
Show all 40
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Asbestos Survey for Asbestos-Containing Materials
Prepared for:
Marshall Space Flight Center, AL
Building 4715 Marshall Space Flight Center
GSE - 017
April 30, 2009
Prepared by
Great Southern Engineering, Inc.
3795 Gordon Terry Parkway
Trinity, Alabama 35673
TABLE OF CONTENTS
1. Introduction
2. Summary
2.1. Suspect ACMs
2.2. Recommendations
3. Survey Scope
4. Limitations
5. Survey and Sample Collection Procedure
6. Previous Survey / Plans Review
7. Suspect ACM Materials Not Sampled
8. Survey Sampling Results
9. Appendices
Task Order GSE 017 Page 1 of 25
GENERAL ASBESTOS SURVEY OF
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
1. Introduction
In accordance with GSE Task Order No.GSE-017 dated August 15, 2008, Great Southern Engineering, Inc. (GSE) has performed an asbestos survey of Building 4715 located at George C.
Marshall Space Flight Center, Marshall Space Flight Center, Alabama. The 2,329 square feet building was identified to have been originally constructed in 1943. A total of 14 samples were collected from the building.
The objective of the Asbestos Survey is to determine the location and quantity of asbestos-containing materials at the Property building.
GSE’s Scope of Work included:
Visual inspection and identification of suspect asbestos-containing materials (ACMs) in the Property building and collected a representative number of samples for analysis.
As part of this asbestos survey, GSE personnel collected samples of all suspect friable and suspect damaged non-friable building materials at the Property. The remaining suspect non-friable materials were not be sampled as part of this asbestos survey
Estimated quantities and locations of ACM.
Assessed the condition of the ACM identified.
Assigned a hazard rating to each type of ACM.
This report has been prepared for the use of George C. Marshall Space Flight Center. Our investigation was performed using the degree of care and skill ordinarily exercised under similar circumstances by professional consultants practicing in this or similar localities. No other warranty or guarantee, expressed or implied, is made as to the conclusions included in this report.
Task Order GSE 017 Page 2 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
The GSE, Inc. did not perform destructive sampling procedures at the site; therefore, regardless of the thoroughness of this survey, it is possible that suspected asbestos-containing materials (ACMs) might exist in the building beneath the floors, behind walls, within pipe chases, or in other inaccessible locations. If, during renovation or demolition activities, materials not addressed in this survey are discovered, these materials should be sampled and analyzed for asbestos content prior to disturbance.
Surveyed by:
John A Jackson
University of Alabama Safe State Program Accredited Inspector/Management Planner
Accreditation #AIN0908531941
Written by:
Manju Ramasamudra
University of Alabama Safe State Program Accredited Inspector/Management Planner
Accreditation #APL0308R5089
Task Order GSE 017 Page 3 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
2. Summary
GSE performed an Asbestos Survey and Hazard Assessment at Building 4715 in Marshall Space Flight Center, Alabama on January 20, 2009 and April 1, 2009. Sample collection was completed by licensed personnel – John A Jackson. The following report summarizes the independent conclusions representing GSE’ best professional judgment based on information and data available to us during the course of this survey. Factual information regarding operations, conditions, and tests data provided by the client, owner or their representative has been assumed to be correct and complete. Additionally, the conclusions presented are based on the conditions that existed on the date(s) of the assessment.
The 2,329 square feet building was identified to have been originally constructed in 1943. A total of 14 samples were collected from the building. No homogeneous materials were identified as asbestos-containing materials.
Task Order GSE 017 Page 4 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
2.1. Suspect ACMs
The following information is included for informational purposes:
A. The following suspect asbestos-containing materials were not sampled as part of this scope of work:
Suspect fibrous electrical cable covering (danger of electrocution) were not sampled.
These materials are not subject to regulation under NESHAP for demolition and renovation as long as they are in good condition and are not subject to sanding, grinding, cutting, or abrading.
Since ordinary demolition activities do not include sanding, grinding, cutting, and abrading, these materials may remain in place during building demolition, as long as they remain in good condition and are not friable.
If the material is in poor condition and is friable at the time of demolition or renovation, or if it will be subjected to sanding, grinding, cutting, or abrading, it should first be removed by a licensed asbestos removal contractor and disposed of as asbestos-containing waste.
When removing asphalt-roofing products, the material should be removed using a method that does not subject the material to sanding, cutting, grinding, or abrading (hand tools).
Asbestos-containing roofing may be disposed of as construction debris.
2.2. Recommendations
The following additional actions are recommended:
No further actions are recommended at this time.
Task Order GSE 017 Page 5 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
3. Survey Scope
This survey was conducted for the purpose of identifying asbestos-containing materials (ACM) throughout the building and to conduct a hazard assessment on existing ACM. The survey was non-destructive in nature and limited only to those areas that were readily accessible.
Specific areas to which access was limited by occupant request, unavailability of keys, or by site conditions included the following:
Behind the walls
Beneath the floors
Any suspect ACM not sampled as part of the assessment and if any additional suspect materials were to be identified behind walls and beneath the floors should be sampled prior to repair, renovation, or demolition activities.
Task Order GSE 017 Page 6 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
4. Limitations
GSE did not attempt to disassemble mechanical equipment, open pipe chases or assess materials within wall voids. Regardless of the thoroughness of a survey, the possibility exists that some areas containing asbestos were not identified, inaccessible or different from those at specific locations. The findings and opinions presented are relative to the dates of our site work and should not be relied upon to represent conditions at substantially later dates due to changes in the condition ACM may change over time, renovations and repairs.
This report is for the exclusive use of the client and its agents and use by any unauthorized parties in whole or in part, except as directed by legal jurisdiction, is at the sole risk of the user.
If this assessment includes reliance on work products and/or documents prepared by others, GSE has no responsibility for the accuracy of information contained therein.
Although this assessment has attempted to identify the presence or absence of ACM, potential sources of ACM may have escaped detection due to: (1) the scope of this assessment, (2) the inaccuracy of records, interviews, work products or documents made available to GSE for this report, (3) the presence of undetected or unreported renovations and repairs, (4) inaccessible areas, and/or (5) deliberate concealment of detrimental information.
Estimates presented in this report are based upon observations during the survey and owner-provided information. These reasonable estimates may be affected by unanticipated conditions potentially present in inaccessible or un-surveyed areas. GSE does not warrant or guarantee the quantity estimates. The use of such estimates shall be at the user's own risk and shall constitute a release and agreement to defend and indemnify GSE from and against any liability. If questions arise during the planning for renovation, demolition, or other construction activities, GSE should be notified to permit review of the data and present recommendations.
Interior of the following rooms were inaccessible during our Asbestos Survey on January 20, 2009 and April 1, 2009: None.
Task Order GSE 017 Page 7 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
5. Survey and Sample Collection Procedure
Based on United States Environmental Protection Agency (USEPA) guidance documents, GSE considered all material applications identified during the visual assessment were suspect ACM and sampled as described below.
Bulk samples were collected of any materials, which were suspected of containing asbestos with the exception of fire doors. Fire doors were not sampled because the damage caused by sampling would render these materials friable and may also void the fire rating. Since these materials were not sampled, they should be assumed to be asbestos containing, unless sampled and proven otherwise. Sampling of these assumed ACMs should be performed prior to any renovation or other activity that may cause a material disturbance.
Samples of the remaining suspect ACM were taken in accordance with USEPA recommendations.
The number and location of samples collected was based on the type of material, the manner of application, and the homogeneity of the ACM (similarity of color, texture, and type). Each sample was collected and placed into an individual sample container. The sample location was noted on the field survey form and assigned an individual identification number. This number was affixed to the sample container as the sample was collected. The survey form was also used to note the material type and general condition of the material. During the inspection, each suspect material's accessibility, location, and friability were recorded. This information was used to assess the potential hazard of the ACM and to prioritize response action recommendations.
The USEPA defines asbestos-containing materials (ACM) as those that contain greater than one percent asbestos. Friable materials are defined as those that can be crumbled or reduced to powder by hand pressure.
GSE utilized the “positive-stop” method of sample analysis. In this method, analysis is stopped on a group of samples once the first positive (e.g., greater than 1% asbestos) sample is analyzed.
According to the USEPA, if one sample of a homogenous material is identified to be asbestos containing, the entire material must be considered asbestos containing. By using the positive-stop method, GSE reduces the Client’s laboratory analysis cost by not analyzing the additional samples.
Samples collected were carried and submitted under Chain-of-Custody to Steve Moody Micro Services LLC, Farmers Branch, Texas for analysis of asbestos using USEPA Method 40 CFR, Chapter 1, Part 763, Subpart F, Appendix A, also known as Polarized Light Microscopy (PLM).
Steve Moody Micro Services LLC is certified by the National Voluntary Laboratory Accreditation Program (NVLAP) and licensed by the Department of State Health Services.
Task Order GSE 017 Page 8 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
6. Previous Survey / Plans Review
GSE was not provided with any previously conducted asbestos surveys of the Property. As-built/renovation-site plans and construction drawings were reviewed at the Facilities Department Drawing Room. Review of these documents did not identify building material specifications requiring the use of ACM. However, this does not preclude or prevent the potential use of ACM.
Task Order GSE 017 Page 9 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
7. Suspect ACM Materials Not Sampled
During the course of the property visit, GSE performed a preliminary review of interior, accessible areas of the subject building for the presence of suspect asbestos-containing materials (ACMs). This asbestos survey was conducted for overview purposes only; additional suspect materials may exist in concealed locations (behind walls and above ceilings, beneath the floors, within machinery, etc.). Also, not all suspect materials may have been sampled due to the condition or the location of the suspect materials. Destructive sampling of suspect ACMs was not performed. GSE will not be responsible for damaging materials or causing the materials to become friable. The USEPA defines asbestos-containing material as material containing greater than one percent asbestos. This review was not a pre-demolition/renovation survey or for regulatory submittal purposes.
Suspect and/or presumed ACMs were observed within the subject building during the property visit. These suspect and/or presumed ACMs that were not sampled as part of this asbestos survey are listed in the following table.
Sample Description Physical Condition
Friable Yes/No
Type of
ACM
Sample ID
4715Building Number
Roofing Material, Roof UPS1 NoM
Expansion Joint Material, on Floor UPS2 NoM
Caulking, On Exterior Wall Joints UPS4 NoM
Grout, On Exterior Wall Masonry UPS5 NoM
Wiring, Fibrous Electrical Cable Covering UPS6 NoM
Fire Doors, Fire Door Insulation UPS7 NoM
Mastic, Mirror Mastic UPS8 NoM
Task Order GSE 017 Page 10 of 25
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
8. Survey Sampling Results
The results of the Survey are presented in the tables on the following pages. The tables describe the entire suspect Asbestos-Containing Materials (ACMs) identified in the building and list respective sample numbers and laboratory results. Sample numbers presented in the tables correspond to the sample numbers on attached Laboratory Analysis Forms. Also presented in the tables is the estimated quantity and assessed friability for each suspect ACM. For each suspect material identified as ACM, the assessed hazard potential is presented along with GSE’ recommended response action. Hazard potential for each material application is based on the material condition and accessibility to the public and maintenance personnel.
Glossary of Items for the following Table
Type of Asbestos (1) CH = Chrysotile AM = Amosite CR = Crocidolite AN = Anthophyllite TR = Tremolite AC = Actinolite ND = No Asbestos Detected PC = Point Count Method
Type of ACM (2) M = Miscellaneous S = Surfacing TSI = Thermal Systems Insulation
Friability (3) F = Friable NF = Non Friable
Physical Condition (4) U = Good D = Damaged SD = Significantly Damaged
Potential for Disturbance (5) NPD = No Potential for Disturbance PD = Potential for Disturbance PSD = Potential for Significant Disturbance
Assessment Category (6) 1 = Damaged or significantly damaged TSI ACBM, 2 = Damaged friable surfacing ACBM 3 = Significantly damaged friable surfacing ACBM 4 = Damaged or significantly damaged friable miscellaneous ACBM 5 = ACBM with potential for damaged 6 = ACBM potential for significant damage 7 = Any remaining friable ACBM or friable suspected
ACBM
X = not applicable
Unit of Measurement SF = Square Feet
LF = Linear Feet
Sample Description
Sample Location
Sample Analyzed
Yes/No
Estimated Quantity of
ACM
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
4715Building Number
Homogeneous Area 1
Wallboard with Associated Texture
Yes M No U XRoom: 100 Grid: WF3-4
ND - Drywall Material ND - Texture
1 PD
Yes M No U XRoom: 100 Grid: WR2-3
ND - Drywall Material ND - Texture
2 PD
Yes M No U XRoom: 100 Grid: WE3-2
ND - Drywall Material ND - Texture
3 PD
Yes M No U XRoom: 100 Grid: WF3-1
ND - Drywall Material ND - Texture
4 PD
Yes M No U XRoom: 101 Grid: WR2-3
ND - Drywall Material ND - Texture
5 PD
Sample Location
Sample Analyzed
Yes/No
Estimated Quantity of
ACM
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
4715Building Number
Homogeneous Area 2
Pipe Insulation with White Mastic
Yes TSI Yes U XRoom: 100 Grid: C4-4
ND - Insulation ND - White Mastic
6 PD
Yes TSI Yes U XRoom: 100 Grid: C1-4
ND - Insulation ND - Paper/ Foil Wrap ND - White Mastic
7 PD
Yes TSI Yes U XRoom: 100 Grid: C2-4
ND - Insulation ND - Paper/ Foil Wrap ND - White Mastic
8 PD
Homogeneous Area 3
Sealant Red Yes M No U XRoom: 100 Grid: WE2-2
ND - Firestop10 PD
Yes M No U XRoom: 101 Grid: WR3-1
ND - Firestop11 PD
Yes M No U XRoom: 100 Grid: C2-4
ND - Firestop9 PD
Sample Location
Sample Analyzed
Yes/No
Estimated Quantity of
ACM
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
4715Building Number
Homogeneous Area 4
Window Glazing on Window Frames
Yes M No D XRoom: 100 Grid: Exterior
ND - Window Glazing
12 PD
Yes M No D XRoom: 100 Grid: Exterior
ND - Window Glazing
13 PD
Yes M No D XRoom: 100 Grid: Exterior
ND - Window Glazing
15 PD
1. CH = Chrysotile; AM = Amosite; CR = Crocidolite; AN = Anthophyllite; TR = Tremolite; AC = Actinolite; ND = No Asbestos Detected; or PC = Point Count Method
2. M = Miscellaneous; S = Surfacing; or TSI = Thermal Systems Insulation
3. F = Friable or NF = Non Friable
4. U = Good; D = Damaged; or SD = Significantly Damaged
5. NPD = No Potential for Disturbance; PD = Potential for Disturbance; or PSD = Potential for Significant Disturbance
6. 1 = Damaged or significantly damaged TSI ACBM, 2 = Damaged friable surfacing ACBM, 3 = Significantly damaged friable surfacing ACBM, 4 = Damaged or significantly damaged friable miscellaneous ACBM, 5 = ACBM with potential for damage, 6 = ACBM potential for significant damage, 7 = Any remaining friable ACBM or friable suspected ACBM, or X = not applicable
SF = Square Feet LF = Linear Feet
9. Appendices
Appendix A— Laboratory Results and Chain of Custody Appendix B— ACM Sample Location Drawings Appendix C— ACM Location Diagrams Appendix D— Photographs Appendix E— Certificates and Licenses
Appendix A
Laboratory Results
PLM Summary Report NVLAP Lab No. 102056
TDSHS License No. 30-0084
Client :
Project :
Project # :
Identification :
Test Method :
Great Southern Engineering
MSFC, Building 4715
GSE-017
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 1/28/2009, eleven (11) bulk material samples were submitted by John Jackson of Great Southern Engineering for asbestos analysis by PLM/DS. The
PLM Detail Report is attached; additional information may be found therein. The results are summarized below:
Steve Moody Micro Services, LLC
Lab Job No. :
Report Date :
09B-00856
01/20/2009
01/28/2009
2051 Valley View Lane
Farmers Branch, TX 75234 (Phone 972-241-8460)
01 Drywall System None Detected - Drywall Material
None Detected - Texture
02 Drywall System None Detected - Drywall Material
None Detected - Texture
03 Drywall System None Detected - Drywall Material
None Detected - Texture
04 Drywall System None Detected - Drywall Material
None Detected - Texture
05 Drywall System None Detected - Drywall Material
None Detected - Texture
06 Mastic (White) on Pipe Insulation None Detected - Insulation
None Detected - White Mastic
07 Mastic (White) on Pipe Insulation None Detected - Insulation
None Detected - Paper / Foil Wrap
None Detected - White Mastic
08 Mastic (White) on Pipe Insulation None Detected - Insulation
None Detected - Paper / Foil Wrap
None Detected - White Mastic
09 Sealant (Red) None Detected - Firestop
10 Sealant (Red) None Detected - Firestop
11 Sealant (Red) None Detected - Firestop
Robert W. MiracleAnalyst(s):
Lab Director : Steve Moody Approved Signatory :
Thank you for choosing Steve Moody Micro Services
These samples were analyzed by layers. Quantification, unless otherwise noted, is performed by calibrated visual estimate. Results may not be reproduced except in full. This test report relates only to the samples tested. These test results do not imply endorsement by NVLAP or any agency of the U.S. Government. Accredited by the
National Voluntary Laboratory Accreditation Program for Bulk Asbestos Fiber Analysis under Lab Code 102056.
Lab Manager : Bruce Crabb Approved Signatory :
Steve Moody Micro Services, LLC PLM Detail Report NVLAP Lab No. 102056
TDSHS License No. 30-0084
Project # : GSE-017
Sample Number Layer Components % Of
Sample
Analysis
Date
% of
Layer Analyst
Supplement to PLM Summary Report 2051 Valley View Lane
Farmers Branch, TX 75234
Client :
Project :
Great Southern Engineering
MSFC, Building 4715
Lab Job No. :
Report Date :
09B-00856
01/28/2009
Glass Wool Fibers01 Drywall Material (White) 30% 01/282% RM
Cellulose Fibers01 Drywall Material (White) 30% 01/281% RM
Gypsum / Binders01 Drywall Material (White) 30% 01/2897% RM
Cellulose Fibers01 DW Paper Facing (Tan) 15% 01/28100% RM
Calcite / Talc / Binders01 Texture (White) 55% 01/28100% RM
Glass Wool Fibers02 Drywall Material (White) 45% 01/282% RM
Cellulose Fibers02 Drywall Material (White) 45% 01/281% RM
Gypsum / Binders02 Drywall Material (White) 45% 01/2897% RM
Cellulose Fibers02 DW Paper Facing (Tan) 20% 01/28100% RM
Calcite / Talc / Binders02 Texture (White) 35% 01/28100% RM
Glass Wool Fibers03 Drywall Material (White) 45% 01/282% RM
Cellulose Fibers03 Drywall Material (White) 45% 01/281% RM
Gypsum / Binders03 Drywall Material (White) 45% 01/2897% RM
Cellulose Fibers03 DW Paper Facing (Tan) 20% 01/28100% RM
Calcite / Talc / Binders03 Texture (White) 35% 01/28100% RM
Glass Wool Fibers04 Drywall Material (White) 20% 01/282% RM
Cellulose Fibers04 Drywall Material (White) 20% 01/281% RM
Gypsum / Binders04 Drywall Material (White) 20% 01/2897% RM
Cellulose Fibers04 DW Paper Facing (Tan) 25% 01/28100% RM
Calcite / Talc / Binders04 Texture (White) 55% 01/28100% RM
Glass Wool Fibers05 Drywall Material (White) 20% 01/282% RM
Cellulose Fibers05 Drywall Material (White) 20% 01/281% RM
Gypsum / Binders05 Drywall Material (White) 20% 01/2897% RM
Cellulose Fibers05 DW Paper Facing (Tan) 25% 01/28100% RM
Calcite / Talc / Binders05 Texture (White) 55% 01/28100% RM
Mineral Wool Fibers06 Insulation (Yellow) 80% 01/2895% RM
Resin Binders06 Insulation (Yellow) 80% 01/285% RM
Pigment / Binders06 White Mastic (Off-White) 20% 01/28100% RM
Project # : GSE-017
Sample Number Layer Components % Of
Sample
Analysis
Date
% of
Layer Analyst
Supplement to PLM Summary Report 2051 Valley View Lane
Farmers Branch, TX 75234
Client :
Project :
Great Southern Engineering
MSFC, Building 4715
Lab Job No. :
Report Date :
09B-00856
01/28/2009
Mineral Wool Fibers07 Insulation (Yellow) 75% 01/2895% RM
Resin Binders07 Insulation (Yellow) 75% 01/285% RM
Cellulose Fibers07 Paper / Foil Wrap (Tan / Silver) 10% 01/2860% RM
Glass Wool Fibers07 Paper / Foil Wrap (Tan / Silver) 10% 01/2820% RM
Metal Foil07 Paper / Foil Wrap (Tan / Silver) 10% 01/2820% RM
Pigment / Binders07 White Mastic (Off-White) 15% 01/28100% RM
Mineral Wool Fibers08 Insulation (Yellow) 75% 01/2895% RM
Resin Binders08 Insulation (Yellow) 75% 01/285% RM
Cellulose Fibers08 Paper / Foil Wrap (Tan / Silver) 10% 01/2860% RM
Glass Wool Fibers08 Paper / Foil Wrap (Tan / Silver) 10% 01/2820% RM
Metal Foil08 Paper / Foil Wrap (Tan / Silver) 10% 01/2820% RM
Pigment / Binders08 White Mastic (Off-White) 15% 01/28100% RM
Glass Wool Fibers09 Firestop (Red) 100% 01/285% RM
Graphite09 Firestop (Red) 100% 01/2810% RM
Binders / Fillers09 Firestop (Red) 100% 01/2885% RM
Glass Wool Fibers10 Firestop (Red) 100% 01/285% RM
Graphite10 Firestop (Red) 100% 01/2810% RM
Binders / Fillers10 Firestop (Red) 100% 01/2885% RM
Glass Wool Fibers11 Firestop (Red) 100% 01/285% RM
Graphite11 Firestop (Red) 100% 01/2810% RM
Binders / Fillers11 Firestop (Red) 100% 01/2885% RM
PLM Summary Report NVLAP Lab No. 102056
TDSHS License No. 30-0084
Client :
Project :
Project # :
Identification :
Test Method :
Great Southern Engineering
MSFC, Building 1715
GSE-017
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 4/7/2009, three (3) bulk material samples were submitted by John Jackson of Great Southern Engineering for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Steve Moody Micro Services, LLC
Lab Job No. :
Report Date :
09B-03801
04/01/2009
04/08/2009
2051 Valley View Lane
Farmers Branch, TX 75234 (Phone 972-241-8460)
12 Window Glazing Exterior None Detected - Window Glazing
13 Window Glazing Exterior None Detected - Window Glazing
14 Window Glazing Exterior None Detected - Window Glazing
Jose OrtizAnalyst(s):
Lab Director : Steve Moody Approved Signatory :
Thank you for choosing Steve Moody Micro Services
These samples were analyzed by layers. Quantification, unless otherwise noted, is performed by calibrated visual estimate. Results may not be reproduced except in full. This test report relates only to the samples tested. These test results do not imply endorsement by NVLAP or any agency of the U.S. Government. Accredited by the
National Voluntary Laboratory Accreditation Program for Bulk Asbestos Fiber Analysis under Lab Code 102056.
Lab Manager : Bruce Crabb Approved Signatory :
Project # : GSE-017
Sample Number Layer Components % Of
Sample
Analysis
Date
% of
Layer Analyst
Supplement to PLM Summary Report 2051 Valley View Lane
Farmers Branch, TX 75234
Client :
Project :
Great Southern Engineering
MSFC, Building 1715
Lab Job No. :
Report Date :
09B-03801
04/08/2009
Calcite12 Window Glazing (Light Grey) 100% 04/0860% JO
Binders / Fillers12 Window Glazing (Light Grey) 100% 04/0840% JO
Calcite13 Window Glazing (Light Grey) 100% 04/0860% JO
Binders / Fillers13 Window Glazing (Light Grey) 100% 04/0840% JO
Calcite14 Window Glazing (Light Grey) 100% 04/0860% JO
Binders / Fillers14 Window Glazing (Light Grey) 100% 04/0840% JO
Appendix B
ACM Sample Location Drawings
First Floor Building 4715
Marshall Space Flight Center Marshall Space Flight Center, AL
Task Order #GSE-017
Appendix C
ACM Location Diagrams
NOT APPLICABLE
Appendix D
Photographs
Building 4715, George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama
PHOTO 1. View of the building PHOTO 2. Window Glazing
PHOTO 3. Interior view of the building PHOTO 4. Wallboard system
PHOTO 5. Pipe insulation with white mastic PHOTO 6. Red sealant on walls
Appendix E
License and Certifications
| 1. Introduction |
| 2. Summary |
| 2.1. Suspect ACMs |
| 2.2. Recommendations |
| 3. Survey Scope |
| 4. Limitations |
| 5. Survey and Sample Collection Procedure |
| 6. Previous Survey / Plans Review |
| 7. Suspect ACM Materials Not Sampled |
| 8. Survey Sampling Results |
| 9. Appendices |
| Appendix A Laboratory Results |
| Appendix B ACM Sample Location Drawings |
| Appendix C ACM Location Diagrams |
| Appendix D Photographs |
| Appendix E License and Certifications |