This document is a Job Plan Template for a document management system implementation project by Konica Minolta. The template outlines a phased approach for deploying GlobalSearch, a document storage and workflow management software solution, with a detailed eight-week implementation timeline. The document appears to be a project methodology document rather than a full contract, focusing on the technical implementation and project rollout process.
The job plan covers a comprehensive implementation strategy involving several key phases: project kickoff, analysis and discovery, system installation, system configuration, training, user acceptance testing, and go-live support. Specific technical details include installation of GlobalSearch on one server, configuration of up to 18 capture workflows, setup of two-layer approval processes, and administrator and end-user training. The implementation includes configuring document storage archives, import capabilities, indexing methods, and workflow approvals. Konica Minolta will provide technical support and assistance to ensure end-users become comfortable with the product, with ongoing technical support after the go-live phase.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Job Plan
| Phase |
| Week 1 |
| Week 2 |
| Week 3 |
| Week 4 |
| Week 5 |
| Week 6 |
Week 7 Week 8+
Project Kickoff
Analysis & Discovery
System Installation
System Configuration
Training and User Acceptance Testing
Go Live and Ongoing Support
Live
Week 1: Project Kick-off Call
The Project Kickoff call is performed prior to project start date. This call should include Business Users and IT Staff. The purpose of the call is to:
· Ensure customer readiness prior to the project.
· Verify customer has the proper hardware in place for the project.
· Discuss customer expectations.
· Discuss project deployment and rollout.
Weeks 2-3: Analysis and Discovery
Discussion with Customer on the desired configuration. This discussion should involve any affected business users, questions you should be prepared to answer include:
· How are you currently storing documents?
· What are you storing?
· How are they stored and indexed, i.e.: file number, name, vendor, etc.
· How are they being received?
Week 4: Installation
· GlobalSearch Installation.
· Installation of GlobalSearch on one (1) server.
· Customer is responsible for basic setup and configuration of server infrastructure prior to Konica Minolta engagement. Minimum hardware requirements can be found at http://info.square-9.com/hardware-requirements.
· For customers with an existing SQL instance, Konica Minolta will need access to the server for creation of 6 user databases. If Konica Minolta will not have access to the SQL instance, databases need to be configured prior to the engagement and a SQL user with DB Ownership on the databases is required.
· If customer wishes to leverage email notifications, customer will need an SMTP mail gateway available and configured. Konica Minolta will not setup or configure the gateway. User/ Password/ Address details should be conveyed prior to the engagement. A SMTP gateway supporting non-SSL traffic is required for notifications.
Week 4-6: System Configuration
· Search
· Configure the archives for document storage:
· Capture
· Configure up to 18 capture workflows.
· Import to archive from static network folder location.
· Configure rapid adapt for customer Template creation.
· Indexing will be done with Key free or manual indexing.
· Workflow
· Configure up to three two-layer approval process ( archives and document types to be determined)
· Approvers to be manually selected from drop down lists
Weeks 6-8: Training and go live
· Proof of Concept Delivery. Konica Minolta will demonstrate the end to end solution with primary business users and document any necessary changes.
· Administrator and End User Training
· Week 8+: Go-Live Support – Konica Minolta assists end users in becoming familiar with and using the product, ensuring they are comfortable with the product prior to the project ending. Once Go Live has been completed, the technical support team will provide ongoing technical support.