Attachment 8 - 246_01-FX409 ADD 1.pdf
PDF 1 MB Posted
- Attached to
- Y1DA--Iowa City | EHRM Infrastructure Upgrades
- Solicitation number
- 36C77622R0094
About this file
This document package includes construction drawings and notes for fire protection system upgrades at the Iowa City VA Medical Center. The drawings show existing and proposed sprinkler locations throughout the ninth floor of Building 1, with keynotes providing instructions for contractors. Notes indicate the drawings are conceptual and final design and installation will be the responsibility of the design-build fire protection contractor. The contractor must utilize existing piping where possible, protect existing sprinklers, and only use new sprinkler heads where existing ones are removed or relocated. The project involves infrastructure upgrades to electrical, mechanical and healthcare facilities.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOT ALL KEYNOTES APPLICABLE TO THIS DRAWING.
1. EXISTING AUTOMATIC SPRINKLER HEAD - TO REMAIN
2. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED.
3. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW
UPRIGHT SPRINKLER TO BE INSTALLED IN SAME LOCATION.
4. EXISTING AUTOMATIC SPRINKLER HEAD LOCATION - TO BE RELOCATED AS INDICATED WITH NEW
UPRIGHT AUTOMATIC SPRINKLER HEAD.
5. INSTALL NEW SEMI-RECESSED AUTOMATIC SPRINKLER HEAD.
6. INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD..
7. EXISTING LAY-IN TILE CEILING TO REMAIN, OR BE ADJUSTED BY GENERAL CONTRACTOR PER
ARCHITECTURAL DRAWING.
8. EXISTING LAY IN CEILING TO BE REMOVED BY GENERAL CONTRACTOR
9. EXISTING PLASTER CEILING TO BE REMOVED BY GENERAL CONTRACTOR.
10. ROOM SHALL HAVE NO CEILING.
11. NEW ROOM CONFIGURATION WILL REQUIRE FIELD ADJUSTMENT TO EXISTING SPRINKLER LAYOUT.
12. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW SEMI
RECESSED SPRINKLER HEAD TO BE INSTALLED IN SAME LOCATION.
13. SEE ARCHITECTURAL DRAWING FOR WORK IN ROOM(S) BELOW THIS AREA. ARCHITECTURAL AND
STRUCTURAL WORK MAY INCLUDE FIRE PROTECTION ADJUSTMENT DUE TO FIELD CONDITIONS.
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL, FOR GENERAL INFORMATION ONLY AND
SHALL NOT BE CONSTRUED AS FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE DESIGN BUILD FIRE
PROTECTION CONTRACTOR. THIS INCLUDES THE RELOCATION OF SPRINKLER MAINS, BRANCH
PIPING AND HEADS AS NECESSARY FOR THE NEW DESIGN. REFER TO SPECIFICATION FOR DESIGN
CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION DESIGN MANUAL, DATED JUNE 1, 2021.
C. CONTRACTOR TO PROTECT EXISTING HEADS FROM DAMAGE DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS, AND FEED MAINS, SERVING NEW
SPRINKLER LOCATIONS WITH MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET.
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN VERTICAL POSITION OF BRANCH 90 DEGREE FITTING FROM FACING
DOWNWARD TO UPWARD AND INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD TO MAINTAIN
FIRE SUPPRESSION PIPING ACTIVE DURING THE CONSTRUCTION. AT THE CONCLUSION OF THE
CONSTRUCTION, REVERSE THE 90 DEGREE FITTING TO ITS ORIGINAL CONFIGURATION, AND
PENDENT AUTOMATIC SPRINKLER HEADS WILL BE INSTALLED, WHERE REQUIRE.
F. AT LOCATIONS WHERE THE EXISTING AUTOMATIC SPRINKLERS ARE REMOVED, RELOCATED, OR
RE-INSTALLED, ONLY NEW AUTOMATIC SPRINKLER HEADS SHALL BE USED. NO AUTOMATIC
SPRINKLER HEADS SHALL BE RE-USED, IN ACCORDANCE WITH THE NFPA #13 REQUIREMENTS.
G. SEE ARCHITECTURAL DRAWINGS GENERAL NOTES AND KEY NOTING TO COORDINATE WORK.
H. VERIFY IN FIELD ALL EXISTING CONDITIONS ILLUSTRATED ON THESE DRAWINGS. CONSTRUCTION DRAWINGS HAVE BEEN DEVELOPED REFERENCING AS-BUILT DRAWINGS PROVIDED BY THE VA. AND FIELD VERIFICATION CONDUCTED THROUGH VISUAL INVESTIGATION. NO SELECTIVE DEMOLITION
OR EXPLORATORY INVESTIGATION WAS ABLE TO BE PERFORMED TO DISCOVER EXISTING
CONDITIONS HAS BEEN EXECUTED DURING THE CREATION OF THESE DRAWINGS. THIS ALSO
RESULTED IN LIMITED ACCESS TO HIDDEN WORK AREAS AND THEIR CONDITIONS DURING SITE
INVESTIGATION. ALL DIMENSIONS EXISTING COMPONENTS OF NEW AND EXISTING COLUMN
LOCATIONS MUST BE VERIFIED IN FIELD.
I. COORDINATE FINAL LOCATION OF AUTOMATIC SPRINKLER HEAD IN FIELD. ADJUST SO HEAD AND
FITTINGS ARE NOT DIRECTLY ABOVE DATA RACKS.
J. FIRE PROTECTION CONTRACTOR SHALL REVIEW WORK OF ALL TRADES TO VERIFY THE EXTENT OF
WORK IN ROOM AND COORDINATE.
K. REFER TO OVERALL ARCHITECTURAL FLOOR PLAN, OF THIS FLOOR, SHOWING EXTENT OR CABLE
AND CABLE TRAY MODIFICATIONS OF CEILING. COORDINATE FIRE PROTECTION WORK WITH
CEILING WORK. WHEREVER REQUIRED REMOVE EXISTING AUTOMATIC SPRINKLER HEAD
ASSEMBLY AND INSTALL A NEW A/S HEAD ASSEMBLY OF SAME TYPE IN REPAIRED CEILING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
8\
-1
6C
9D
V
IS
N
ID
IQ
(N or th D ak ot a
Io w
a) \3
6C
1R
EH
R M
Io w a
C ity
, I A\
0-
D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\A C
AD
\3
6C -1
8-
1-
-F X4
.d w g
5/
/2
3:
:5
PM
CONSTRUCTION BID
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
IOWA CITY, IA
636A8-21-700
Project Director
Revisions: Date:
www. bancroft-ae.com
BAE PROJECT NO. 18-121
3300 Dundee Rd. Suite D Northbrook, IL 60062
T: 847.952.9362
VA CONTRACT NO. 36C77621N281535% SCHEMATIC DESIGN SUBMISSION 07-15-21
75% DESIGN DEVELOPMENT SUBMISSION 08-19-21
95% CONSTRUCTION DOCUMENTS SUBMISSION 10-21-21
100% CONSTRUCTION DOCUMENTS SUBMISSION 11-09-21
CONSTRUCTION BID DOCUMENTS 04-08-2022
04/08/2022
FIRE PROTECTION - ENLARGED
PLAN - BUILDING 1 - NINTH FLOOR
JPK RRR 01-FX409
HAZARDOUS
NON-RATED SMOKE PARTITION
1 HOUR SMOKE PARTITION
2 HOUR SMOKE PARTITION
1 HOUR FIRE BARRIER
2 HOUR FIRE BARRIER
HEALTHCARE OCCUPANCY
ADDENDUM #1 05-27-2022
NOT ALL KEYNOTES APPLICABLE TO THIS DRAWING.
1. EXISTING AUTOMATIC SPRINKLER HEAD - TO REMAIN
2. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED.
3. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW
UPRIGHT SPRINKLER TO BE INSTALLED IN SAME LOCATION.
4. EXISTING AUTOMATIC SPRINKLER HEAD LOCATION - TO BE RELOCATED AS INDICATED WITH NEW
UPRIGHT AUTOMATIC SPRINKLER HEAD.
5. INSTALL NEW SEMI-RECESSED AUTOMATIC SPRINKLER HEAD.
6. INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD..
7. EXISTING LAY-IN TILE CEILING TO REMAIN, OR BE ADJUSTED BY GENERAL CONTRACTOR PER
ARCHITECTURAL DRAWING.
8. EXISTING LAY IN CEILING TO BE REMOVED BY GENERAL CONTRACTOR
9. EXISTING PLASTER CEILING TO BE REMOVED BY GENERAL CONTRACTOR.
10. ROOM SHALL HAVE NO CEILING.
11. NEW ROOM CONFIGURATION WILL REQUIRE FIELD ADJUSTMENT TO EXISTING SPRINKLER LAYOUT.
12. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW SEMI
RECESSED SPRINKLER HEAD TO BE INSTALLED IN SAME LOCATION.
13. SEE ARCHITECTURAL DRAWING FOR WORK IN ROOM(S) BELOW THIS AREA. ARCHITECTURAL AND
STRUCTURAL WORK MAY INCLUDE FIRE PROTECTION ADJUSTMENT DUE TO FIELD CONDITIONS.
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL, FOR GENERAL INFORMATION ONLY AND
SHALL NOT BE CONSTRUED AS FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE DESIGN BUILD FIRE
PROTECTION CONTRACTOR. THIS INCLUDES THE RELOCATION OF SPRINKLER MAINS, BRANCH
PIPING AND HEADS AS NECESSARY FOR THE NEW DESIGN. REFER TO SPECIFICATION FOR DESIGN
CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION DESIGN MANUAL, DATED JUNE 1, 2021.
C. CONTRACTOR TO PROTECT EXISTING HEADS FROM DAMAGE DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS, AND FEED MAINS, SERVING NEW
SPRINKLER LOCATIONS WITH MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET.
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN VERTICAL POSITION OF BRANCH 90 DEGREE FITTING FROM FACING
DOWNWARD TO UPWARD AND INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD TO MAINTAIN
FIRE SUPPRESSION PIPING ACTIVE DURING THE CONSTRUCTION. AT THE CONCLUSION OF THE
CONSTRUCTION, REVERSE THE 90 DEGREE FITTING TO ITS ORIGINAL CONFIGURATION, AND
PENDENT AUTOMATIC SPRINKLER HEADS WILL BE INSTALLED, WHERE REQUIRE.
F. AT LOCATIONS WHERE THE EXISTING AUTOMATIC SPRINKLERS ARE REMOVED, RELOCATED, OR
RE-INSTALLED, ONLY NEW AUTOMATIC SPRINKLER HEADS SHALL BE USED. NO AUTOMATIC
SPRINKLER HEADS SHALL BE RE-USED, IN ACCORDANCE WITH THE NFPA #13 REQUIREMENTS.
G. SEE ARCHITECTURAL DRAWINGS GENERAL NOTES AND KEY NOTING TO COORDINATE WORK.
H. VERIFY IN FIELD ALL EXISTING CONDITIONS ILLUSTRATED ON THESE DRAWINGS. CONSTRUCTION DRAWINGS HAVE BEEN DEVELOPED REFERENCING AS-BUILT DRAWINGS PROVIDED BY THE VA. AND FIELD VERIFICATION CONDUCTED THROUGH VISUAL INVESTIGATION. NO SELECTIVE DEMOLITION
OR EXPLORATORY INVESTIGATION WAS ABLE TO BE PERFORMED TO DISCOVER EXISTING
CONDITIONS HAS BEEN EXECUTED DURING THE CREATION OF THESE DRAWINGS. THIS ALSO
RESULTED IN LIMITED ACCESS TO HIDDEN WORK AREAS AND THEIR CONDITIONS DURING SITE
INVESTIGATION. ALL DIMENSIONS EXISTING COMPONENTS OF NEW AND EXISTING COLUMN
LOCATIONS MUST BE VERIFIED IN FIELD.
I. COORDINATE FINAL LOCATION OF AUTOMATIC SPRINKLER HEAD IN FIELD. ADJUST SO HEAD AND
FITTINGS ARE NOT DIRECTLY ABOVE DATA RACKS.
J. FIRE PROTECTION CONTRACTOR SHALL REVIEW WORK OF ALL TRADES TO VERIFY THE EXTENT OF
WORK IN ROOM AND COORDINATE.
K. REFER TO OVERALL ARCHITECTURAL FLOOR PLAN, OF THIS FLOOR, SHOWING EXTENT OR CABLE
AND CABLE TRAY MODIFICATIONS OF CEILING. COORDINATE FIRE PROTECTION WORK WITH
CEILING WORK. WHEREVER REQUIRED REMOVE EXISTING AUTOMATIC SPRINKLER HEAD
ASSEMBLY AND INSTALL A NEW A/S HEAD ASSEMBLY OF SAME TYPE IN REPAIRED CEILING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
8\
-1
6C
9D
V
IS
N
ID
IQ
(N or th D ak ot a
Io w
a) \3
6C
1R
EH
R M
Io w a
C ity
, I A\
0-
D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\A C
AD
\3
6C -1
8-
1-
-F X4
.d w g
5/
/2
3:
:5
PM
CONSTRUCTION BID
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
IOWA CITY, IA
636A8-21-700
Project Director
Revisions: Date:
www. bancroft-ae.com
BAE PROJECT NO. 18-121
3300 Dundee Rd. Suite D Northbrook, IL 60062
T: 847.952.9362
VA CONTRACT NO. 36C77621N281535% SCHEMATIC DESIGN SUBMISSION 07-15-21
75% DESIGN DEVELOPMENT SUBMISSION 08-19-21
95% CONSTRUCTION DOCUMENTS SUBMISSION 10-21-21
100% CONSTRUCTION DOCUMENTS SUBMISSION 11-09-21
CONSTRUCTION BID DOCUMENTS 04-08-2022
04/08/2022
FIRE PROTECTION - ENLARGED
PLAN - BUILDING 1 - NINTH FLOOR
JPK RRR 01-FX409
HAZARDOUS
NON-RATED SMOKE PARTITION
1 HOUR SMOKE PARTITION
2 HOUR SMOKE PARTITION
1 HOUR FIRE BARRIER
2 HOUR FIRE BARRIER
HEALTHCARE OCCUPANCY
ADDENDUM #1 05-27-2022
NOT ALL KEYNOTES APPLICABLE TO THIS DRAWING.
1. EXISTING AUTOMATIC SPRINKLER HEAD - TO REMAIN
2. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED.
3. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW
UPRIGHT SPRINKLER TO BE INSTALLED IN SAME LOCATION.
4. EXISTING AUTOMATIC SPRINKLER HEAD LOCATION - TO BE RELOCATED AS INDICATED WITH NEW
UPRIGHT AUTOMATIC SPRINKLER HEAD.
5. INSTALL NEW SEMI-RECESSED AUTOMATIC SPRINKLER HEAD.
6. INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD..
7. EXISTING LAY-IN TILE CEILING TO REMAIN, OR BE ADJUSTED BY GENERAL CONTRACTOR PER
ARCHITECTURAL DRAWING.
8. EXISTING LAY IN CEILING TO BE REMOVED BY GENERAL CONTRACTOR
9. EXISTING PLASTER CEILING TO BE REMOVED BY GENERAL CONTRACTOR.
10. ROOM SHALL HAVE NO CEILING.
11. NEW ROOM CONFIGURATION WILL REQUIRE FIELD ADJUSTMENT TO EXISTING SPRINKLER LAYOUT.
12. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW SEMI
RECESSED SPRINKLER HEAD TO BE INSTALLED IN SAME LOCATION.
13. SEE ARCHITECTURAL DRAWING FOR WORK IN ROOM(S) BELOW THIS AREA. ARCHITECTURAL AND
STRUCTURAL WORK MAY INCLUDE FIRE PROTECTION ADJUSTMENT DUE TO FIELD CONDITIONS.
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL, FOR GENERAL INFORMATION ONLY AND
SHALL NOT BE CONSTRUED AS FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE DESIGN BUILD FIRE
PROTECTION CONTRACTOR. THIS INCLUDES THE RELOCATION OF SPRINKLER MAINS, BRANCH
PIPING AND HEADS AS NECESSARY FOR THE NEW DESIGN. REFER TO SPECIFICATION FOR DESIGN
CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION DESIGN MANUAL, DATED JUNE 1, 2021.
C. CONTRACTOR TO PROTECT EXISTING HEADS FROM DAMAGE DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS, AND FEED MAINS, SERVING NEW
SPRINKLER LOCATIONS WITH MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET.
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN VERTICAL POSITION OF BRANCH 90 DEGREE FITTING FROM FACING
DOWNWARD TO UPWARD AND INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD TO MAINTAIN
FIRE SUPPRESSION PIPING ACTIVE DURING THE CONSTRUCTION. AT THE CONCLUSION OF THE
CONSTRUCTION, REVERSE THE 90 DEGREE FITTING TO ITS ORIGINAL CONFIGURATION, AND
PENDENT AUTOMATIC SPRINKLER HEADS WILL BE INSTALLED, WHERE REQUIRE.
F. AT LOCATIONS WHERE THE EXISTING AUTOMATIC SPRINKLERS ARE REMOVED, RELOCATED, OR
RE-INSTALLED, ONLY NEW AUTOMATIC SPRINKLER HEADS SHALL BE USED. NO AUTOMATIC
SPRINKLER HEADS SHALL BE RE-USED, IN ACCORDANCE WITH THE NFPA #13 REQUIREMENTS.
G. SEE ARCHITECTURAL DRAWINGS GENERAL NOTES AND KEY NOTING TO COORDINATE WORK.
H. VERIFY IN FIELD ALL EXISTING CONDITIONS ILLUSTRATED ON THESE DRAWINGS. CONSTRUCTION DRAWINGS HAVE BEEN DEVELOPED REFERENCING AS-BUILT DRAWINGS PROVIDED BY THE VA. AND FIELD VERIFICATION CONDUCTED THROUGH VISUAL INVESTIGATION. NO SELECTIVE DEMOLITION
OR EXPLORATORY INVESTIGATION WAS ABLE TO BE PERFORMED TO DISCOVER EXISTING
CONDITIONS HAS BEEN EXECUTED DURING THE CREATION OF THESE DRAWINGS. THIS ALSO
RESULTED IN LIMITED ACCESS TO HIDDEN WORK AREAS AND THEIR CONDITIONS DURING SITE
INVESTIGATION. ALL DIMENSIONS EXISTING COMPONENTS OF NEW AND EXISTING COLUMN
LOCATIONS MUST BE VERIFIED IN FIELD.
I. COORDINATE FINAL LOCATION OF AUTOMATIC SPRINKLER HEAD IN FIELD. ADJUST SO HEAD AND
FITTINGS ARE NOT DIRECTLY ABOVE DATA RACKS.
J. FIRE PROTECTION CONTRACTOR SHALL REVIEW WORK OF ALL TRADES TO VERIFY THE EXTENT OF
WORK IN ROOM AND COORDINATE.
K. REFER TO OVERALL ARCHITECTURAL FLOOR PLAN, OF THIS FLOOR, SHOWING EXTENT OR CABLE
AND CABLE TRAY MODIFICATIONS OF CEILING. COORDINATE FIRE PROTECTION WORK WITH
CEILING WORK. WHEREVER REQUIRED REMOVE EXISTING AUTOMATIC SPRINKLER HEAD
ASSEMBLY AND INSTALL A NEW A/S HEAD ASSEMBLY OF SAME TYPE IN REPAIRED CEILING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
8\
-1
6C
9D
V
IS
N
ID
IQ
(N or th D ak ot a
Io w
a) \3
6C
1R
EH
R M
Io w a
C ity
, I A\
0-
D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\A C
AD
\3
6C -1
8-
1-
-F X4
.d w g
5/
/2
3:
:5
PM
CONSTRUCTION BID
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
IOWA CITY, IA
636A8-21-700
Project Director
Revisions: Date:
www. bancroft-ae.com
BAE PROJECT NO. 18-121
3300 Dundee Rd. Suite D Northbrook, IL 60062
T: 847.952.9362
VA CONTRACT NO. 36C77621N281535% SCHEMATIC DESIGN SUBMISSION 07-15-21
75% DESIGN DEVELOPMENT SUBMISSION 08-19-21
95% CONSTRUCTION DOCUMENTS SUBMISSION 10-21-21
100% CONSTRUCTION DOCUMENTS SUBMISSION 11-09-21
CONSTRUCTION BID DOCUMENTS 04-08-2022
04/08/2022
FIRE PROTECTION - ENLARGED
PLAN - BUILDING 1 - NINTH FLOOR
JPK RRR 01-FX409
HAZARDOUS
NON-RATED SMOKE PARTITION
1 HOUR SMOKE PARTITION
2 HOUR SMOKE PARTITION
1 HOUR FIRE BARRIER
2 HOUR FIRE BARRIER
HEALTHCARE OCCUPANCY
ADDENDUM #1 05-27-2022
NOT ALL KEYNOTES APPLICABLE TO THIS DRAWING.
1. EXISTING AUTOMATIC SPRINKLER HEAD - TO REMAIN
2. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED.
3. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW
UPRIGHT SPRINKLER TO BE INSTALLED IN SAME LOCATION.
4. EXISTING AUTOMATIC SPRINKLER HEAD LOCATION - TO BE RELOCATED AS INDICATED WITH NEW
UPRIGHT AUTOMATIC SPRINKLER HEAD.
5. INSTALL NEW SEMI-RECESSED AUTOMATIC SPRINKLER HEAD.
6. INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD..
7. EXISTING LAY-IN TILE CEILING TO REMAIN, OR BE ADJUSTED BY GENERAL CONTRACTOR PER
ARCHITECTURAL DRAWING.
8. EXISTING LAY IN CEILING TO BE REMOVED BY GENERAL CONTRACTOR
9. EXISTING PLASTER CEILING TO BE REMOVED BY GENERAL CONTRACTOR.
10. ROOM SHALL HAVE NO CEILING.
11. NEW ROOM CONFIGURATION WILL REQUIRE FIELD ADJUSTMENT TO EXISTING SPRINKLER LAYOUT.
12. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW SEMI
RECESSED SPRINKLER HEAD TO BE INSTALLED IN SAME LOCATION.
13. SEE ARCHITECTURAL DRAWING FOR WORK IN ROOM(S) BELOW THIS AREA. ARCHITECTURAL AND
STRUCTURAL WORK MAY INCLUDE FIRE PROTECTION ADJUSTMENT DUE TO FIELD CONDITIONS.
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL, FOR GENERAL INFORMATION ONLY AND
SHALL NOT BE CONSTRUED AS FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE DESIGN BUILD FIRE
PROTECTION CONTRACTOR. THIS INCLUDES THE RELOCATION OF SPRINKLER MAINS, BRANCH
PIPING AND HEADS AS NECESSARY FOR THE NEW DESIGN. REFER TO SPECIFICATION FOR DESIGN
CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION DESIGN MANUAL, DATED JUNE 1, 2021.
C. CONTRACTOR TO PROTECT EXISTING HEADS FROM DAMAGE DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS, AND FEED MAINS, SERVING NEW
SPRINKLER LOCATIONS WITH MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET.
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN VERTICAL POSITION OF BRANCH 90 DEGREE FITTING FROM FACING
DOWNWARD TO UPWARD AND INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD TO MAINTAIN
FIRE SUPPRESSION PIPING ACTIVE DURING THE CONSTRUCTION. AT THE CONCLUSION OF THE
CONSTRUCTION, REVERSE THE 90 DEGREE FITTING TO ITS ORIGINAL CONFIGURATION, AND
PENDENT AUTOMATIC SPRINKLER HEADS WILL BE INSTALLED, WHERE REQUIRE.
F. AT LOCATIONS WHERE THE EXISTING AUTOMATIC SPRINKLERS ARE REMOVED, RELOCATED, OR
RE-INSTALLED, ONLY NEW AUTOMATIC SPRINKLER HEADS SHALL BE USED. NO AUTOMATIC
SPRINKLER HEADS SHALL BE RE-USED, IN ACCORDANCE WITH THE NFPA #13 REQUIREMENTS.
G. SEE ARCHITECTURAL DRAWINGS GENERAL NOTES AND KEY NOTING TO COORDINATE WORK.
H. VERIFY IN FIELD ALL EXISTING CONDITIONS ILLUSTRATED ON THESE DRAWINGS. CONSTRUCTION DRAWINGS HAVE BEEN DEVELOPED REFERENCING AS-BUILT DRAWINGS PROVIDED BY THE VA. AND FIELD VERIFICATION CONDUCTED THROUGH VISUAL INVESTIGATION. NO SELECTIVE DEMOLITION
OR EXPLORATORY INVESTIGATION WAS ABLE TO BE PERFORMED TO DISCOVER EXISTING
CONDITIONS HAS BEEN EXECUTED DURING THE CREATION OF THESE DRAWINGS. THIS ALSO
RESULTED IN LIMITED ACCESS TO HIDDEN WORK AREAS AND THEIR CONDITIONS DURING SITE
INVESTIGATION. ALL DIMENSIONS EXISTING COMPONENTS OF NEW AND EXISTING COLUMN
LOCATIONS MUST BE VERIFIED IN FIELD.
I. COORDINATE FINAL LOCATION OF AUTOMATIC SPRINKLER HEAD IN FIELD. ADJUST SO HEAD AND
FITTINGS ARE NOT DIRECTLY ABOVE DATA RACKS.
J. FIRE PROTECTION CONTRACTOR SHALL REVIEW WORK OF ALL TRADES TO VERIFY THE EXTENT OF
WORK IN ROOM AND COORDINATE.
K. REFER TO OVERALL ARCHITECTURAL FLOOR PLAN, OF THIS FLOOR, SHOWING EXTENT OR CABLE
AND CABLE TRAY MODIFICATIONS OF CEILING. COORDINATE FIRE PROTECTION WORK WITH
CEILING WORK. WHEREVER REQUIRED REMOVE EXISTING AUTOMATIC SPRINKLER HEAD
ASSEMBLY AND INSTALL A NEW A/S HEAD ASSEMBLY OF SAME TYPE IN REPAIRED CEILING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
8\
-1
6C
9D
V
IS
N
ID
IQ
(N or th D ak ot a
Io w
a) \3
6C
1R
EH
R M
Io w a
C ity
, I A\
0-
D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\A C
AD
\3
6C -1
8-
1-
-F X4
.d w g
5/
/2
3:
:5
PM
CONSTRUCTION BID
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
IOWA CITY, IA
636A8-21-700
Project Director
Revisions: Date:
www. bancroft-ae.com
BAE PROJECT NO. 18-121
3300 Dundee Rd. Suite D Northbrook, IL 60062
T: 847.952.9362
VA CONTRACT NO. 36C77621N281535% SCHEMATIC DESIGN SUBMISSION 07-15-21
75% DESIGN DEVELOPMENT SUBMISSION 08-19-21
95% CONSTRUCTION DOCUMENTS SUBMISSION 10-21-21
100% CONSTRUCTION DOCUMENTS SUBMISSION 11-09-21
CONSTRUCTION BID DOCUMENTS 04-08-2022
04/08/2022
FIRE PROTECTION - ENLARGED
PLAN - BUILDING 1 - NINTH FLOOR
JPK RRR 01-FX409
HAZARDOUS
NON-RATED SMOKE PARTITION
1 HOUR SMOKE PARTITION
2 HOUR SMOKE PARTITION
1 HOUR FIRE BARRIER
2 HOUR FIRE BARRIER
HEALTHCARE OCCUPANCY
ADDENDUM #1 05-27-2022
NOT ALL KEYNOTES APPLICABLE TO THIS DRAWING.
1. EXISTING AUTOMATIC SPRINKLER HEAD - TO REMAIN
2. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED.
3. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW
UPRIGHT SPRINKLER TO BE INSTALLED IN SAME LOCATION.
4. EXISTING AUTOMATIC SPRINKLER HEAD LOCATION - TO BE RELOCATED AS INDICATED WITH NEW
UPRIGHT AUTOMATIC SPRINKLER HEAD.
5. INSTALL NEW SEMI-RECESSED AUTOMATIC SPRINKLER HEAD.
6. INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD..
7. EXISTING LAY-IN TILE CEILING TO REMAIN, OR BE ADJUSTED BY GENERAL CONTRACTOR PER
ARCHITECTURAL DRAWING.
8. EXISTING LAY IN CEILING TO BE REMOVED BY GENERAL CONTRACTOR
9. EXISTING PLASTER CEILING TO BE REMOVED BY GENERAL CONTRACTOR.
10. ROOM SHALL HAVE NO CEILING.
11. NEW ROOM CONFIGURATION WILL REQUIRE FIELD ADJUSTMENT TO EXISTING SPRINKLER LAYOUT.
12. EXISTING AUTOMATIC SPRINKLER HEAD - TO BE REMOVED DURING CONSTRUCTION AND NEW SEMI
RECESSED SPRINKLER HEAD TO BE INSTALLED IN SAME LOCATION.
13. SEE ARCHITECTURAL DRAWING FOR WORK IN ROOM(S) BELOW THIS AREA. ARCHITECTURAL AND
STRUCTURAL WORK MAY INCLUDE FIRE PROTECTION ADJUSTMENT DUE TO FIELD CONDITIONS.
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL, FOR GENERAL INFORMATION ONLY AND
SHALL NOT BE CONSTRUED AS FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE DESIGN BUILD FIRE
PROTECTION CONTRACTOR. THIS INCLUDES THE RELOCATION OF SPRINKLER MAINS, BRANCH
PIPING AND HEADS AS NECESSARY FOR THE NEW DESIGN. REFER TO SPECIFICATION FOR DESIGN
CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION DESIGN MANUAL, DATED JUNE 1, 2021.
C. CONTRACTOR TO PROTECT EXISTING HEADS FROM DAMAGE DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS, AND FEED MAINS, SERVING NEW
SPRINKLER LOCATIONS WITH MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET.
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN VERTICAL POSITION OF BRANCH 90 DEGREE FITTING FROM FACING
DOWNWARD TO UPWARD AND INSTALL NEW UPRIGHT AUTOMATIC SPRINKLER HEAD TO MAINTAIN
FIRE SUPPRESSION PIPING ACTIVE DURING THE CONSTRUCTION. AT THE CONCLUSION OF THE
CONSTRUCTION, REVERSE THE 90 DEGREE FITTING TO ITS ORIGINAL CONFIGURATION, AND
PENDENT AUTOMATIC SPRINKLER HEADS WILL BE INSTALLED, WHERE REQUIRE.
F. AT LOCATIONS WHERE THE EXISTING AUTOMATIC SPRINKLERS ARE REMOVED, RELOCATED, OR
RE-INSTALLED, ONLY NEW AUTOMATIC SPRINKLER HEADS SHALL BE USED. NO AUTOMATIC
SPRINKLER HEADS SHALL BE RE-USED, IN ACCORDANCE WITH THE NFPA #13 REQUIREMENTS.
G. SEE ARCHITECTURAL DRAWINGS GENERAL NOTES AND KEY NOTING TO COORDINATE WORK.
H. VERIFY IN FIELD ALL EXISTING CONDITIONS ILLUSTRATED ON THESE DRAWINGS. CONSTRUCTION DRAWINGS HAVE BEEN DEVELOPED REFERENCING AS-BUILT DRAWINGS PROVIDED BY THE VA. AND FIELD VERIFICATION CONDUCTED THROUGH VISUAL INVESTIGATION. NO SELECTIVE DEMOLITION
OR EXPLORATORY INVESTIGATION WAS ABLE TO BE PERFORMED TO DISCOVER EXISTING
CONDITIONS HAS BEEN EXECUTED DURING THE CREATION OF THESE DRAWINGS. THIS ALSO
RESULTED IN LIMITED ACCESS TO HIDDEN WORK AREAS AND THEIR CONDITIONS DURING SITE
INVESTIGATION. ALL DIMENSIONS EXISTING COMPONENTS OF NEW AND EXISTING COLUMN
LOCATIONS MUST BE VERIFIED IN FIELD.
I. COORDINATE FINAL LOCATION OF AUTOMATIC SPRINKLER HEAD IN FIELD. ADJUST SO HEAD AND
FITTINGS ARE NOT DIRECTLY ABOVE DATA RACKS.
J. FIRE PROTECTION CONTRACTOR SHALL REVIEW WORK OF ALL TRADES TO VERIFY THE EXTENT OF
WORK IN ROOM AND COORDINATE.
K. REFER TO OVERALL ARCHITECTURAL FLOOR PLAN, OF THIS FLOOR, SHOWING EXTENT OR CABLE
AND CABLE TRAY MODIFICATIONS OF CEILING. COORDINATE FIRE PROTECTION WORK WITH
CEILING WORK. WHEREVER REQUIRED REMOVE EXISTING AUTOMATIC SPRINKLER HEAD
ASSEMBLY AND INSTALL A NEW A/S HEAD ASSEMBLY OF SAME TYPE IN REPAIRED CEILING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
8\
-1
6C
9D
V
IS
N
ID
IQ
(N or th D ak ot a
Io w
a) \3
6C
1R
EH
R M
Io w a
C ity
, I A\
0-
D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\A C
AD
\3
6C -1
8-
1-
-F X4
.d w g
5/
/2
3:
:5
PM
CONSTRUCTION BID
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
IOWA CITY, IA
636A8-21-700
Project Director
Revisions: Date:
www. bancroft-ae.com
BAE PROJECT NO. 18-121
3300 Dundee Rd. Suite D Northbrook, IL 60062
T: 847.952.9362
VA CONTRACT NO. 36C77621N281535% SCHEMATIC DESIGN SUBMISSION 07-15-21
75% DESIGN DEVELOPMENT SUBMISSION 08-19-21
95% CONSTRUCTION DOCUMENTS SUBMISSION 10-21-21
100% CONSTRUCTION DOCUMENTS SUBMISSION 11-09-21
CONSTRUCTION BID DOCUMENTS 04-08-2022
04/08/2022
FIRE PROTECTION - ENLARGED
PLAN - BUILDING 1 - NINTH FLOOR
JPK RRR 01-FX409
HAZARDOUS
NON-RATED SMOKE PARTITION
1 HOUR SMOKE PARTITION
2 HOUR SMOKE PARTITION
1 HOUR FIRE BARRIER
2 HOUR FIRE BARRIER
HEALTHCARE OCCUPANCY
ADDENDUM #1 05-27-2022
| Sheets and Views |
| 01-FX409 |
File details come from the government source that posted it. Updated .