This document contains a federal solicitation for interior lighting work and a related federal contract opportunity. The solicitation is for a construction project to relocate IT offices at the Cincinnati VA Medical Center, including demolition, renovation of existing space, and new construction for plumbing, HVAC, electrical, security and fire protection systems. The estimated value is between $500,000 to $1 million. The opportunity will be set aside for Service-Disabled Veteran Owned Small Businesses. The invitation for bids is expected to post on August 30th, 2021 with a bid opening 30-45 days later. The selected contractor must complete all work within 180 days of receiving the notice to proceed.

View the file

Other files

File Type Posted
36C25021B0065 0012.pdf PDF
36C25021B0065 0011.pdf PDF
VA Cincinnati IT Amendment 211119.docx DOCX document
General Requirements 010000 update.pdf PDF
36C25021B0065 0010.pdf PDF
RELOCATE IT UPDATED DRAWINGS 211102.pdf PDF
23 05 41.pdf PDF
23 37 00.pdf PDF
26 05 33.pdf PDF
23 36 00.pdf PDF
26 51 00.pdf PDF
36C25021B0065 0009.pdf PDF
010000.pdf PDF
23 21 13.pdf PDF
23 31 00.pdf PDF
270533.pdf PDF
230923 DDC Controls Amendment 1 211019.pdf PDF
130541 Non-Structural.pdf PDF
000100.pdf PDF
23 05 11.pdf PDF
36C25021B0065 0008.docx DOCX document
Honeywell Siemens JCI Sole Source Justification_Relocate IT (002) - Redacted.pdf PDF
Tridium Niagara Sole Source Justification_Relocate IT - Redacted (002).pdf PDF
36C25021B0065 0007.docx DOCX document
VAAR 852.219-77 SEPT 2021 Deviation.pdf PDF
36C25021B0065 0006.docx DOCX document
230511.pdf PDF
232113.pdf PDF
539 21 208 RELOCATE IT UPDATED DRAWINGS 211015.pdf PDF
36C25021B0065 0005.docx DOCX document
233700.pdf PDF
233100.pdf PDF
233600.pdf PDF
539 21 208 VA Cincinnati IT Amendment 01 211019.docx DOCX document
260533.pdf PDF
230541.pdf PDF
010000 General Requirements update.pdf PDF
230923 DDC Controls Amendment 211019.pdf PDF
36C25021B0065 0004.docx DOCX document
36C25021B0065 0003.docx DOCX document
36C25021B0065 0002.docx DOCX document
Site Visit -Sign-In.pdf PDF
36C25021B0065 0001.docx DOCX document
Attachment 4- RFI Form.pdf PDF
36C25021B0065_1.docx DOCX document
Attachment 5 - EMR Attachment.pdf PDF
Attahcment 1 -Specifications Updated.pdf PDF
Attachment 3- DBA OH20210082.pdf PDF
Attachment 2 Drawings Updated.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project #539-21-208 Relocate IT Offices 01-01-18 (Amendment 11/02/21 Revision)

26 51 00 - 1

INTERIOR LIGHTING

SECTION 26 51 00

INTERIOR LIGHTING

PART 1 - GENERAL

1.1 DESCRIPTION:

A. This section specifies the furnishing, installation, and connection of the interior lighting systems. The terms “lighting fixture,”

“fixture,” and “luminaire” are used interchangeably.

1.2 RELATED WORK

A. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT: Disposal of lamps.

B. Section 02 41 00, DEMOLITION: Removal and disposal of lamps and ballasts.

C. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL

COMPONENTS: Requirement for seismic restraint for nonstructural components.

D. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:

Requirements that apply to all sections of Division 26.

E. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:

Low-voltage conductors.

F. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:

Requirements for personnel safety and to provide a low impedance path to ground for possible ground fault currents.

G. Section 26 27 26, WIRING DEVICES: Wiring devices used for control of the lighting systems.

1.3 QUALITY ASSURANCE

A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS

(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS.

1.4 SUBMITTALS

A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:

1. Shop Drawings:

a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation.

b. Material and construction details, include information on housing and optics system.

26 51 00 - 2

INTERIOR LIGHTING

c. Physical dimensions and description.

d. Wiring schematic and connection diagram.

e. Installation details.

f. Energy efficiency data.

g. Photometric data based on laboratory tests complying with IES

Lighting Measurements testing and calculation guides.

h. Lamp data including lumen output (initial and mean), color rendition index (CRI), rated life (hours), and color temperature

(degrees Kelvin).

i. Ballast data including ballast type, starting method, ambient temperature, ballast factor, sound rating, system watts, and total harmonic distortion (THD).

j. For LED lighting fixtures, submit US DOE LED Lighting Facts label, and IES L70 rated life.

2. Manuals:

a. Submit, simultaneously with the shop drawings, complete maintenance and operating manuals, including technical data sheets, wiring diagrams, and information for ordering replacement parts.

b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.

3. Certifications: Two weeks prior to final inspection, submit the following.

a. Certification by the Contractor that the interior lighting systems have been properly installed and tested.

1.5 APPLICABLE PUBLICATIONS

A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.

B. American Society for Testing and Materials (ASTM):

C635/C635M REV A-13.....Manufacture, Performance, and Testing of Metal

Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings

C. Environmental Protection Agency (EPA):

40 CFR 261..............Identification and Listing of Hazardous Waste

D. Federal Communications Commission (FCC):

26 51 00 - 3

INTERIOR LIGHTING

CFR Title 47, Part 15...Radio Frequency Devices

CFR Title 47, Part 18...Industrial, Scientific, and Medical Equipment

E. Illuminating Engineering Society of North America (IESNA):

LM-79-08................Electrical and Photometric Measurements of

Solid-State Lighting Products

LM-80-15................Measuring Lumen Maintenance of LED Light

Sources

LM-82-12................Characterization of LED Light Engines and LED

Lamps for Electrical and Photometric Properties as a Function of Temperature

F. Institute of Electrical and Electronic Engineers (IEEE):

C62.41-91(R1995)........Surge Voltages in Low Voltage AC Power Circuits

G. International Code Council (ICC):

IBC-15..................International Building Code

H. National Electrical Manufacturer's Association (NEMA):

C78.376-14..............Chromaticity of Fluorescent Lamps

C82.1-04(R2015).........Lamp Ballasts – Line Frequency Fluorescent Lamp

Ballasts

C82.2-02(R2016).........Method of Measurement of Fluorescent Lamp

Ballasts

C82.4-17................Lamp Ballasts - Ballasts for High-Intensity

Discharge and Low-Pressure Sodium (LPS) Lamps

(Multiple-Supply Type)

C82.11-17...............Lamp Ballasts - High Frequency Fluorescent Lamp

Ballasts

LL 9-11.................Dimming of T8 Fluorescent Lighting Systems

SSL 1-16................Electronic Drivers for LED Devices, Arrays, or

Systems

I. National Fire Protection Association (NFPA):

70-17...................National Electrical Code (NEC)

101-18..................Life Safety Code

J. Underwriters Laboratories, Inc. (UL):

496-17..................Lampholders

542-05..................Fluorescent Lamp Starters

844-12..................Luminaires for Use in Hazardous (Classified)

Locations

924-16..................Emergency Lighting and Power Equipment

935-01..................Fluorescent-Lamp Ballasts

26 51 00 - 4

INTERIOR LIGHTING

1029-94.................High-Intensity-Discharge Lamp Ballasts

1029A-06................Ignitors and Related Auxiliaries for HID Lamp

Ballasts

1598-08.................Luminaires

1574-04.................Track Lighting Systems

2108-15.................Low-Voltage Lighting Systems

8750-15.................Light Emitting Diode (LED) Light Sources for

Use in Lighting Products

PART 2 - PRODUCTS

2.1 LIGHTING FIXTURES

A. Shall be in accordance with NFPA, UL, as shown on drawings, and as specified.

B. Sheet Metal:

1. Shall be formed to prevent warping and sagging. Housing, trim and lens frame shall be true, straight (unless intentionally curved), and parallel to each other as designed.

2. Wireways and fittings shall be free of burrs and sharp edges, and shall accommodate internal and branch circuit wiring without damage to the wiring.

3. When installed, any exposed fixture housing surface, trim frame, door frame, and lens frame shall be free of light leaks.

4. Hinged door frames shall operate smoothly without binding. Latches shall function easily by finger action without the use of tools.

C. Recessed fixtures mounted in an insulated ceiling shall be listed for use in insulated ceilings.

D. Mechanical Safety: Lighting fixture closures (lens doors, trim frame, hinged housings, etc.) shall be retained in a secure manner by captive screws, chains, aircraft cable, captive hinges, or fasteners such that they cannot be accidentally dislodged during normal operation or routine maintenance.

E. Metal Finishes:

1. The manufacturer shall apply standard finish (unless otherwise specified) over a corrosion-resistant primer, after cleaning to free the metal surfaces of rust, grease, dirt and other deposits. Edges of pre-finished sheet metal exposed during forming, stamping or shearing processes shall be finished in a similar corrosion resistant manner to match the adjacent surface(s). Fixture finish

26 51 00 - 5

INTERIOR LIGHTING

shall be free of stains or evidence of rusting, blistering, or flaking, and shall be applied after fabrication.

2. Interior light reflecting finishes shall be white with not less than

85 percent reflectances, except where otherwise shown on the drawing.

3. Exterior finishes shall be as shown on the drawings.

F. Lighting fixtures shall have a specific means for grounding metallic wireways and housings to an equipment grounding conductor.

G. Light Transmitting Components for Fluorescent Fixtures:

1. Shall be 100 percent virgin acrylic.

2. Flat lens panels shall have not less than 3 mm (1/8 inch) of average thickness.

3. Unless otherwise specified, lenses, reflectors, diffusers, and louvers shall be retained firmly in a metal frame by clips or clamping ring in such a manner as to allow expansion and contraction without distortion or cracking.

H. Lighting fixtures in hazardous areas shall be suitable for installation in Class and Division areas as defined in NFPA 70.

2.2 LED EXIT LIGHT FIXTURES

A. Exit light fixtures shall meet applicable requirements of NFPA and UL.

B. Housing and door shall be die-cast aluminum.

C. For general purpose exit light fixtures, door frame shall be hinged, with latch. For vandal-resistant exit light fixtures, door frame shall be secured with tamper-resistant screws.

D. Finish shall be satin or fine-grain brushed aluminum.

E. There shall be no radioactive material used in the fixtures.

F. Fixtures:

1. Inscription panels shall be black housing cast or stamped aluminum a minimum of 2.25 mm (0.090 inch) thick, stenciled with 150 mm (6 inch) high letters, baked with red color stable plastic or fiberglass. Lamps shall be luminous Light Emitting Diodes (LED) mounted in center of letters on red color stable plastic or fiberglass.

2. Double-Faced Fixtures: Provide double-faced fixtures where required or as shown on drawings.

3. Directional Arrows: Provide directional arrows as part of the inscription panel where required or as shown on drawings.

26 51 00 - 6

INTERIOR LIGHTING

Directional arrows shall be the "chevron-type" of similar size and width as the letters and meet the requirements of NFPA 101.

G. Voltage: Multi-voltage (120 – 277V).

2.3 LED LIGHT FIXTURES

A. General:

1. LED light fixtures shall be in accordance with IES, NFPA, UL, as shown on the drawings, and as specified.

2. LED light fixtures shall be Reduction of Hazardous Substances

(RoHS)-compliant.

3. LED drivers shall include the following features unless otherwise indicated:

a. Minimum efficiency: 85% at full load.

b. Minimum Operating Ambient Temperature: -20˚ C. (-4˚ F.)

c. Input Voltage: 120 - 277V (±10%) at 60 Hz.

d. Integral short circuit, open circuit, and overload protection.

e. Power Factor: ≥ 0.95.

f. Total Harmonic Distortion: ≤ 20%.

g. Comply with FCC 47 CFR Part 15.

4. LED modules shall include the following features unless otherwise indicated:

a. Comply with IES LM-79 and LM-80 requirements.

b. Minimum CRI 80 and color temperature 3000˚ K unless otherwise specified in LIGHTING FIXTURE SCHEDULE.

c. Minimum Rated Life: 50,000 hours per IES L70.

d. Light output lumens as indicated in the LIGHTING FIXTURE

SCHEDULE.

B. LED Downlights:

1. Housing, LED driver, and LED module shall be products of the same manufacturer.

C. LED Troffers:

1. LED drivers, modules, and reflector shall be accessible, serviceable, and replaceable from below the ceiling.

2. Housing, LED driver, and LED module shall be products of the same manufacturer.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation shall be in accordance with the NEC, manufacturer's instructions, and as shown on the drawings or specified.

26 51 00 - 7

INTERIOR LIGHTING

B. Align, mount, and level the lighting fixtures uniformly.

C. Wall-mounted fixtures shall be attached to the studs in the walls, or to a 20 gauge metal backing plate that is attached to the studs in the walls. Lighting fixtures shall not be attached directly to gypsum board.

D. Lighting Fixture Supports:

1. Shall provide support for all of the fixtures. Supports may be anchored to channels of the ceiling construction, to the structural slab or to structural members within a partition, or above a suspended ceiling.

2. Shall maintain the fixture positions after cleaning and relamping.

3. Shall support the lighting fixtures without causing the ceiling or partition to deflect.

Hardware for recessed fluorescent fixtures:

a. Where the suspended ceiling system is supported at the four corners of the fixture opening, hardware devices shall clamp the fixture to the ceiling system structural members, or plaster frame at not less than four points in such a manner as to resist spreading of the support members and safely lock the fixture into the ceiling system.

b. Where the suspended ceiling system is not supported at the four corners of the fixture opening, hardware devices shall independently support the fixture from the building structure at four points.

E. Furnish and install the new lamps as specified for all lighting fixtures installed under this project, and for all existing lighting fixtures reused under this project.

F. The electrical and ceiling trades shall coordinate to ascertain that approved lighting fixtures are furnished in the proper sizes and installed with the proper devices (hangers, clips, trim frames, flanges, etc.), to match the ceiling system being installed.

G. Bond lighting fixtures to the grounding system as specified in Section

26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.

H. At completion of project, replace all defective components of the lighting fixtures at no cost to the Government.

I. Dispose of lamps per requirements of Section 01 74 19, CONSTRUCTION

WASTE MANAGEMENT, and Section 02 41 00, DEMOLITION.

26 51 00 - 8

INTERIOR LIGHTING

3.2 ACCEPTANCE CHECKS AND TESTS

A. Perform the following:

1. Visual Inspection:

a. Verify proper operation by operating the lighting controls.

b. Visually inspect for damage to fixtures, lenses, reflectors, diffusers, and louvers. Clean fixtures, lenses, reflectors, diffusers, and louvers that have accumulated dust, dirt, or fingerprints during construction.

2. Electrical tests:

a. Exercise dimming components of the lighting fixtures over full range of dimming capability by operating the control devices(s) in the presence of the COR. Observe for visually detectable flicker over full dimming range, and replace defective components at no cost to the Government.

b. Burn-in all lamps that require specific aging period to operate properly, prior to occupancy by Government. Burn-in period shall be 40 hours minimum, unless specifically recommended otherwise by the lamp manufacturer. Burn-in dimmed fluorescent and compact fluorescent lamps for at least 100 hours at full voltage, unless specifically recommended otherwise by the lamp manufacturer.

Replace any lamps and ballasts which fail during burn-in.

3.3 FOLLOW-UP VERIFICATION

A. Upon completion of acceptance checks and tests, the Contractor shall show by demonstration in service that the lighting systems are in good operating condition and properly performing the intended function.