This is a Scope of Work document for the Rhode Island Army National Guard's Building T-18 renovation project at Camp Varnum in Narragansett, Rhode Island, procured through the State of Rhode Island Division of Purchases under RFQ26006763. The project encompasses comprehensive energy-efficient renovation and modernization of the facility, including life safety devices, heating, electrical, plumbing, flooring, carpentry, utility room, bathroom, and sleeping area work. The scope of work specifies removal of exterior wall sheathing, installation of six-inch wall insulation, new electrical wiring and receptacles, gypsum board installation, ceiling replacement, vinyl flooring, new plumbing fixtures, mechanical and electrical systems, fire alarm systems, painting, stair railing replacement with vinyl treads and risers, and replacement of exterior porch flooring with PVC composite decking and railings. All work must follow approved construction design prints completed by Rowse Architects Inc. and comply with Rhode Island Building Code Commission and State Building and Fire Code standards. A non-mandatory pre-bid conference is scheduled for June 24, 2026 at 9:00 a.m. at Camp Varnum, with questions due July 1, 2026, and proposals due July 15, 2026 at 1:00 p.m. EDT. Construction is anticipated to commence in September 2026, with substantial completion required 16 months after start and final completion within 60 days thereafter.
Work is restricted to 7:00 a.m. to 4:00 p.m., Tuesday through Friday, with no work on Mondays, as the site remains under full owner occupancy during construction. A minimum 15% minority business enterprise (MBE) participation is required under Rhode Island law. Contractors must maintain valid registration certificates from the Rhode Island Contractors' Registration Board, comply with prevailing wage requirements, and obtain 100% payment and performance bonds. Required insurance includes general liability of $1,000,000 per occurrence, workers' compensation of $100,000, and automobile liability of $1,000,000. A lump-sum contingency allowance of $10,000 is included in the bid. Bid surety must equal 5% of the cost proposal, and liquidated damages are assessed at $400 per calendar day for delays beyond substantial completion. A contract administrative fee of 0.33% will be withheld from invoices. All contractor and subcontractor personnel must obtain background clearances and BCI certification for base access; no workers with outstanding warrants or felonies are permitted. The State reserves the right to make one or multiple awards or reject all bids.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
24029A– 01 50 00 Camp Varnum Building T-18 Renovations
Rhode Island Army National Guard
Narragansett, Rhode Island
07.14.26 TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 1
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
B. The Owner will allow the contractor to selectively utilize a space in the back by the boiler room which includes a small office and large area for a table to layout plans of the “Notre Dame
Ambulatory Center” located in the property for construction offices. The Owner will pay for energy used in heating, lighting and cooling the office of the Notre Dame Ambulatory Center.
1. All areas utilized will be as approved by the Owner.
2. Contractor to provide “daily” janitorial services for the areas utilized.
C. Related Requirements:
1. Division 01 Section "Summary" for work restrictions and limitations on utility interruptions.
1.3 INFORMATIONAL SUBMITTALS
A. Site Plan: Show temporary facilities, utility hookups and staging areas.
1. Show phasing of access roads to limit the amount of time the “north” access road will be closed to the adjacent property occupants.
2. Show the “path of egress from the adjacent properties that will be maintained during the construction period. If relocation will be needed show the phasing.
B. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.
C. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire-prevention program.
D. Moisture-Protection Plan: Describe procedures and controls for protecting materials and construction from water absorption and damage.
1. Describe delivery, handling, and storage provisions for materials subject to water absorption or water damage.
2. Indicate procedures for discarding water-damaged materials, protocols for mitigating water intrusion into completed Work, and replacing water-damaged Work.
3. Indicate sequencing of work that requires water and describe plans for dealing with water from these operations. Show procedures for verifying that wet construction has dried sufficiently to permit installation of finish materials.
01 50 00 - 2 TEMPORARY FACILITIES AND CONTROLS 07.14.26
1.4 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.
1.5 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Portable Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized-steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top and bottom rails. Provide concrete bases for supporting posts.
2.2 TEMPORARY FACILITIES
A. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.
1. Store combustible materials apart from building.
2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
1. ."
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
1. Locate facilities to limit site disturbance as specified in Division 01 Section "Summary."
07.14.26 TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 3
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
B. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
1. Toilets: Use of Owner's existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.
C. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.
D. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.
1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.
E. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel.
1. Post a list of important telephone numbers.
a. Police and fire departments.
b. Ambulance service.
c. Contractor's home office.
d. Contractor's emergency after-hours telephone number.
e. Architect's office.
f. Engineers' offices.
g. Owner's office.
h. Principal subcontractors' field and home offices.
2. Provide superintendent with cellular telephone.
3.3 SUPPORT FACILITIES INSTALLATION
A. Traffic Controls: Comply with requirements of authorities having jurisdiction.
1. Protect existing site improvements to remain including curbs, pavement, and utilities.
2. Maintain access for fire-fighting equipment and access to fire hydrants.
B. Parking: Onsite parking is not available. Contractor shall provide temporary parking areas for construction personnel.
C. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted.
1. Identification Signs: Provide Project identification signs as indicated on Drawings.
2. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project and the adjacent buildings.
01 50 00 - 4 TEMPORARY FACILITIES AND CONTROLS 07.14.26
D. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.
1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.
E. Temporary Elevator Use:
1. Do not load elevators beyond their rated weight capacity.
2. Provide protective coverings, barriers, devices, signs, or other procedures to protect elevator car and entrance doors and frame. If, despite such protection, elevators become damaged, engage elevator Installer to restore damaged work so no evidence remains of correction work. Return items that cannot be refinished in field to the shop, make required repairs and refinish entire unit, or provide new units as required.
F. Hoisting Facilities
1. Provide hoisting facilities as required for the vertical movement of all materials.
2. Comply with OSHA for all hoists, conveyers, and elevators and maintain the facilities in compliance with the law.
G. Scaffolding and Staging
1. Contractor shall furnish erect and maintain exterior staging and scaffolding for use during construction of building. Each subcontractor shall furnish, erect and maintain staging and scaffolding required in work under his subcontract. Staging shall conform to federal, state, and local requirements. On completion of his work, each subcontractor shall dismantle and remove his staging and scaffolding.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.
B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
1. Comply with work restrictions specified in Division 01 Section "Summary."
C. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each work day.
D. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
E. Temporary Egress: Maintain temporary egress from existing occupied facilities as required by authorities having jurisdiction.
F. Covered Walkway: Erect protective, covered walkway for passage of individuals through or adjacent to Project site. Coordinate with entrance gates, other facilities, and obstructions.
Comply with regulations of authorities having jurisdiction.
1. Construct covered walkways using scaffold or shoring framing.
07.14.26 TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 5
2. Provide overhead decking, protective enclosure walls, handrails, barricades, warning signs, exit signs, lights, safe and well-drained walkways, and similar provisions for protection and safe passage.
3. Paint and maintain appearance of walkway for duration of the Work.
G. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.
H. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241; manage fire-prevention program.
1. Prohibit smoking in construction areas.
2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.
3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.
4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed.
Match hose size with outlet size and equip with suitable nozzles.
3.5 MOISTURE AND MOLD CONTROL
A. Contractor's Moisture-Protection Plan: Avoid trapping water in finished work. Document visible signs of mold that may appear during construction.
B. Exposed Construction Phase: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect as follows:
1. Protect porous materials from water damage.
2. Protect stored and installed material from flowing or standing water.
3. Keep porous and organic materials from coming into prolonged contact with concrete.
4. Remove standing water from decks.
5. Keep deck openings covered or dammed.
C. Partially Enclosed Construction Phase: After installation of weather barriers but before full enclosure and conditioning of building, when installed materials are still subject to infiltration of moisture and ambient mold spores, protect as follows:
1. Do not load or install drywall or other porous materials or components, or items with high organic content, into partially enclosed building.
2. Keep interior spaces reasonably clean and protected from water damage.
3. Periodically collect and remove waste containing cellulose or other organic matter.
4. Discard or replace water-damaged material.
5. Do not install material that is wet.
6. Discard, replace, or clean stored or installed material that begins to grow mold.
7. Perform work in a sequence that allows any wet materials adequate time to dry before enclosing the material in drywall or other interior finishes.
D. Controlled Construction Phase of Construction: After completing and sealing of the building enclosure but prior to the full operation of permanent HVAC systems, maintain as follows:
1. Control moisture and humidity inside building by maintaining effective dry-in conditions.
2. Use permanent HVAC system to control humidity.
01 50 00 - 6 TEMPORARY FACILITIES AND CONTROLS 07.14.26
3. Comply with manufacturer's written instructions for temperature, relative humidity, and exposure to water limits.
a. Hygroscopic materials that may support mold growth, including wood and gypsum-based products, that become wet during the course of construction and remain wet for 48 hours are considered defective.
b. Measure moisture content of materials that have been exposed to moisture during construction operations or after installation. Record readings beginning at time of exposure and continuing daily for 48 hours. Identify materials containing moisture levels higher than allowed. Report findings in writing to Architect.
c. Remove materials that cannot be completely restored to their manufactured moisture level within 48 hours.
3.6 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.
C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.
D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are property of Contractor.
Owner reserves right to take possession of Project identification signs.
2. Remove temporary roads and paved areas not intended for or acceptable for integration into permanent construction. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil.
Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances that might impair growth of plant materials or lawns.
Repair or replace street paving, curbs, and sidewalks, as required by authorities having jurisdiction.
3. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 01 Section "Closeout Procedures."
END OF SECTION 01 50 00
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities. |
| B. The Owner will allow the contractor to selectively utilize a space in the back by the boiler room which includes a small office and large area for a table to layout plans of the “Notre Dame Ambulatory Center” located in the property for constructio... |
| 1. All areas utilized will be as approved by the Owner. |
| 2. Contractor to provide “daily” janitorial services for the areas utilized. |
| C. Related Requirements: |
| 1. Division 01 Section "Summary" for work restrictions and limitations on utility interruptions. |
| 1.3 INFORMATIONAL SUBMITTALS |
| A. Site Plan: Show temporary facilities, utility hookups and staging areas. |
| 1. Show phasing of access roads to limit the amount of time the “north” access road will be closed to the adjacent property occupants. |
| 2. Show the “path of egress from the adjacent properties that will be maintained during the construction period. If relocation will be needed show the phasing. |
| B. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent. |
| C. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire-prevention program. |
| D. Moisture-Protection Plan: Describe procedures and controls for protecting materials and construction from water absorption and damage. |
| 1. Describe delivery, handling, and storage provisions for materials subject to water absorption or water damage. |
| 2. Indicate procedures for discarding water-damaged materials, protocols for mitigating water intrusion into completed Work, and replacing water-damaged Work. |
| 3. Indicate sequencing of work that requires water and describe plans for dealing with water from these operations. Show procedures for verifying that wet construction has dried sufficiently to permit installation of finish materials. |
| 1.4 QUALITY ASSURANCE |
| A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70. |
| B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits. |
| 1.5 PROJECT CONDITIONS |
| A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, re... |
| PART 2 - PRODUCTS |
| 2.1 MATERIALS |
| A. Portable Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized-steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch-... |
| 2.2 TEMPORARY FACILITIES |
| A. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations. |
| 1. Store combustible materials apart from building. |
| 2.3 EQUIPMENT |
| A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures. |
| 1. ." |
| PART 3 - EXECUTION |
| 3.1 INSTALLATION, GENERAL |
| A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work. |
| 1. Locate facilities to limit site disturbance as specified in Division 01 Section "Summary." |
| 3.2 TEMPORARY UTILITY INSTALLATION |
| A. General: Install temporary service or connect to existing service. |
| 1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services. |
| B. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures ... |
| 1. Toilets: Use of Owner's existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use. |
| C. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations. |
| D. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions. |
| 1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system. |
| E. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel. |
| 1. Post a list of important telephone numbers. |
| a. Police and fire departments. |
| b. Ambulance service. |
| c. Contractor's home office. |
| d. Contractor's emergency after-hours telephone number. |
| e. Architect's office. |
| f. Engineers' offices. |
| g. Owner's office. |
| h. Principal subcontractors' field and home offices. |
2. Provide superintendent with cellular telephone.
| 3.3 SUPPORT FACILITIES INSTALLATION |
| A. Traffic Controls: Comply with requirements of authorities having jurisdiction. |
| 1. Protect existing site improvements to remain including curbs, pavement, and utilities. |
| 2. Maintain access for fire-fighting equipment and access to fire hydrants. |
| B. Parking: Onsite parking is not available. Contractor shall provide temporary parking areas for construction personnel. |
| C. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted. |
| 1. Identification Signs: Provide Project identification signs as indicated on Drawings. |
| 2. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project and the adjacent buildings. |
| D. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel. |
| 1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities. |
| E. Temporary Elevator Use: |
| 1. Do not load elevators beyond their rated weight capacity. |
| 2. Provide protective coverings, barriers, devices, signs, or other procedures to protect elevator car and entrance doors and frame. If, despite such protection, elevators become damaged, engage elevator Installer to restore damaged work so no eviden... |
| F. Hoisting Facilities |
| 1. Provide hoisting facilities as required for the vertical movement of all materials. |
| 2. Comply with OSHA for all hoists, conveyers, and elevators and maintain the facilities in compliance with the law. |
| G. Scaffolding and Staging |
| 1. Contractor shall furnish erect and maintain exterior staging and scaffolding for use during construction of building. Each subcontractor shall furnish, erect and maintain staging and scaffolding required in work under his subcontract. Staging sha... |
| 3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION |
| A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facili... |
| B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other und... |
| 1. Comply with work restrictions specified in Division 01 Section "Summary." |
| C. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end... |
| D. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting. |
| E. Temporary Egress: Maintain temporary egress from existing occupied facilities as required by authorities having jurisdiction. |
| F. Covered Walkway: Erect protective, covered walkway for passage of individuals through or adjacent to Project site. Coordinate with entrance gates, other facilities, and obstructions. Comply with regulations of authorities having jurisdiction. |
| 1. Construct covered walkways using scaffold or shoring framing. |
| 2. Provide overhead decking, protective enclosure walls, handrails, barricades, warning signs, exit signs, lights, safe and well-drained walkways, and similar provisions for protection and safe passage. |
| 3. Paint and maintain appearance of walkway for duration of the Work. |
| G. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for buildin... |
| H. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241; manage fire-prevention program. |
| 1. Prohibit smoking in construction areas. |
| 2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction. |
| 3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings ... |
| 4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles. |
| 3.5 MOISTURE AND MOLD CONTROL |
| A. Contractor's Moisture-Protection Plan: Avoid trapping water in finished work. Document visible signs of mold that may appear during construction. |
| B. Exposed Construction Phase: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect as follows: |
| 1. Protect porous materials from water damage. |
| 2. Protect stored and installed material from flowing or standing water. |
| 3. Keep porous and organic materials from coming into prolonged contact with concrete. |
| 4. Remove standing water from decks. |
| 5. Keep deck openings covered or dammed. |
| C. Partially Enclosed Construction Phase: After installation of weather barriers but before full enclosure and conditioning of building, when installed materials are still subject to infiltration of moisture and ambient mold spores, protect as follows: |
| 1. Do not load or install drywall or other porous materials or components, or items with high organic content, into partially enclosed building. |
| 2. Keep interior spaces reasonably clean and protected from water damage. |
| 3. Periodically collect and remove waste containing cellulose or other organic matter. |
| 4. Discard or replace water-damaged material. |
| 5. Do not install material that is wet. |
| 6. Discard, replace, or clean stored or installed material that begins to grow mold. |
| 7. Perform work in a sequence that allows any wet materials adequate time to dry before enclosing the material in drywall or other interior finishes. |
| D. Controlled Construction Phase of Construction: After completing and sealing of the building enclosure but prior to the full operation of permanent HVAC systems, maintain as follows: |
| 1. Control moisture and humidity inside building by maintaining effective dry-in conditions. |
| 2. Use permanent HVAC system to control humidity. |
| 3. Comply with manufacturer's written instructions for temperature, relative humidity, and exposure to water limits. |
| a. Hygroscopic materials that may support mold growth, including wood and gypsum-based products, that become wet during the course of construction and remain wet for 48 hours are considered defective. |
| b. Measure moisture content of materials that have been exposed to moisture during construction operations or after installation. Record readings beginning at time of exposure and continuing daily for 48 hours. Identify materials containing moisture... |
| c. Remove materials that cannot be completely restored to their manufactured moisture level within 48 hours. |
| 3.6 OPERATION, TERMINATION, AND REMOVAL |
| A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses. |
| B. Maintenance: Maintain facilities in good operating condition until removal. |
| 1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage. |
| C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion. |
| D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanen... |
| 1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs. |
| 2. Remove temporary roads and paved areas not intended for or acceptable for integration into permanent construction. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or su... |
| 3. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 01 Section "Closeout Procedures." |