This is a Pay Quantity Notes document for the City of Midland's D23-01 Jal Draw Excavation project, a drainage improvement initiative extending from Barton Creek to State Highway 158 in Texas. The project encompasses miscellaneous items including mobilization, erosion and sediment control, traffic control, job site safety, seeding and stabilization, and spray watering. Demolition work involves removal of concrete rip-rap, while paving work includes unclassified embankment placement (density controlled), unclassified channel excavation, channel excavation with church grade restoration embankment, articulated concrete block mattress with geotextile fabric installation, and six-inch concrete rip-rap placement. Additive alternate items consist of two-inch Type D HMAC asphalt pavement surface course, six-inch flexible base, and bituminous prime coat application. The project includes provisions for a shared use trail as an additive alternate.

Payment for all work items is structured on various measurement bases including lump sum, monthly billing, square yard, cubic yard, square foot, and gallon applied. Mobilization, erosion control, traffic control, and job site safety are billed monthly, with job site safety designated as the contractor's responsibility and subject to OSHA and City of Midland compliance requirements. Material placement items such as embankment, excavation, and paving are measured and paid by cubic yard or square yard of material placed along the ground surface. All work must comply with City of Midland standards and specifications as detailed in construction drawings, with comprehensive inclusion of equipment, labor, materials, and incidental costs for each pay item.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pay Quantity Note

Miscellaneous Items 1 Mobilization M1 2 Erosion/Sediment Control M2 3 Traffic Control M3 4 Job Site Safety M4 5 Seeding & Stabilization M5 6 Spray Watering M6

Demolition Items 1 Removal of Concrete Rip - Rap D1

Paving Items 1 Unclassified Embankment (Density Controlled) P1 2 Unclassified Channel Excavation P2 3 Unclassified Channel Excavation & Church Grade Restoration Embankement P3 4 Articulated Concrete Block Mattress and Geotextile Fabric P4 5 6" Concrete Rip - Rap P5

Additive Alternate Items

2" Type D HMAC Asphalt Pavement Surface Course (PG70-22, 110 LBS / SY @ 1" Thick) A1

2 6" Flexible Base (Type A, Grade 4) A2 3 Bituminous Prime Coat (MC-30, 0.20 Gal / SY) A3

PAY NOTES

D23-01 Bid Item

Jal Draw Excavation

M1

M2

M3

M4

M5

M6

D1

Includes the necessary equipment, labor, materials, and incidentals for Spray Watering per the construction drawings and City of Midland standards and specifications, including all appurtenances. Measurement and payment to be made per Lump Sum.

PAY QUANTITY NOTES

Includes the necessary equipment, labor, materials, and incidentals to implement the Erosion Control Plan per the construction drawings and City of Midland standards and specifications, including the placement, maintenance, and removal of all temporary erosion control measures and infrastructure. Measurement and payment to be made per month.

Includes the necessary equipment, labor, materials, and incidentals to implement the Traffic Control per the approved Traffic Control Plan , including the placement, maintenance, and removal of all temporary erosion control measures and devices. Any required traffic control devices are to meet the City of Midland Traffic Division Standards. Measurement and payment to be made per month.

Includes the necessary equipment, labor, materials, and incidentals to implement Job Site Safety and to provide a safe work environment for the project work area (including all personal protection equipment, trench safety, etc.) per the construction drawings and in compliance with all applicable Federal, State, and Local requirements or regulations including those of OSHA and the City of Midland. JOB SITE SAFETY IS THE

RESPONSABILITY OF THE CONTRACTOR. Measurement and payment to be made per month.

Includes the necessary equipment, labor, materials, and incidentals for Seeding & Stabilization per the construction drawings and City of Midland standards and specifications, including all removal, storage, and replacement of existing topsoil as well as all seeding and appurtenances. Watering is addressed in a separate pay note. Measurement and payment to be made per square yard measured along the ground surface.

Includes the necessary equipment, labor, materials, and incidentals for the Removal of Concrete Rip - Rap per the construction drawings and City of Midland standards and specifications, including all appurtenances.

Measurement and payment to be made per Square Yard measured.

Includes the necessary equipment, labor, materials, and incidentals for all Mobilization to the job site complete and in place. Measurement and payment to be made per month.

P1

P2

P3

P4

P5

A1

A2

A3

Includes the necessary equipment, labor, materials, and incidentals for placement of Flexible Base compacted to 95% Density, ASTM D1557, per the construction drawings and City of Midland standards and specifications including all placement, compaction, and appurtenances. Measurement and payment to be made per square yard of material placed measured along the ground surface.

Includes the necessary equipment, labor, materials, and incidentals for placement of Unclassified Channel Excavation per the construction drawings and City of Midland standards and specifications, including all existing pavement and substructure removal, unclassified excavation, material removal, rock removal and appurtenances. Measurement and payment to be made per each cubic yard of material removed.

Includes the necessary equipment, labor, materials, and incidentals for the placement of Type "D" HMAC Asphalt Pavement Surface Course (PG 70-22, 110 LBS / SY at 1" thick) per the construction drawings and City of Midland standards and specifications, including all placement, compaction, and appurtenances.

Measurement and payment to be made per square yard of material placed measured along the ground surface.

Includes the necessary equipment, labor, materials, and incidentals for placement of Articulated Concrete Block Mattress and Geotextile Fabric per the construction drawings and City of Midland standards and specifications, including all sprinkling, rolling, correction of soft spots, grading, sloping, compaction, and appurtenances. Measurement and payment to be made per each square foot placed.

Includes the Necessary equipment, labor, materials, and incidentals for the installation of Concrete Rip - Rap perr the construction drawings and City of Midland standards and specifications including all excavation, forms, reinforcement, placement, jointing, sealing, finishing, and appurtenances. Measurement and payment to be made per square yard placed measured along the ground surface.

Includes the necessary equipment, labor, materials, and incidentals for application of Bituminous Prime Coat (MC-30, 0.20 GAL / SY) per the construction drawings and City of Midland standards and specifications, including all appurtenances. Measurement and payment to be made per gallon of material applied at the designated rate.

Includes the necessary equipment, labor, materials, and incidentals for placement of Unclassified Channel Excavation & Church Grade Restoration Embankement per the construction drawings and City of Midland standards and specifications, including all existing pavement and substructure removal, unclassified excavation, material removal, rock removal, sprinkling, rolling, correction of soft spots, grading, sloping, compaction, and appurtenances. Measurement and payment to be made per each cubic yard placed.

Includes the necessary equipment, labor, materials, and incidentals for placement of Unclassified Embankment per the construction drawings and City of Midland standards and specifications, including all sprinkling, rolling, correction of soft spots, grading, sloping, compaction, and appurtenances. Measurement and payment to be made per each cubic yard placed.