This solicitation requests proposals for the construction of a new four-story barracks building at Fort Eustis, Virginia. The project includes design and construction of the 139,500 square foot building along with supporting site work and utilities. Proposals are due by July 28, 2020 through the DoD SAFE system. The award date is unspecified. The solicitation is set aside for small businesses and provides a small business subcontracting plan template. The Army Corps of Engineers is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to AIT Barracks Fort Eustis VA (Amendment 0004), newest first.
File Type Posted
B.01.02_ KO signed IFB Abstract of Offerors.pdf PDF
Amendment 4.pdf PDF
W9123620B0015 Amendment 0003.pdf PDF
A0002 SHEET A423.pdf PDF
A0002 SPEC 09 30 10.pdf PDF
A0002 SPEC 06 61 16.pdf PDF
A0002 SHEET I002.pdf PDF
A0002 SHEET F103.pdf PDF
A0002 SHEET A407.pdf PDF
A0002 SHEET A401.pdf PDF
W91236-20-B-0015 Amend 0002.pdf PDF
A0002 SPECS TOC.pdf PDF
A0002 Revised FFE Package.pdf PDF
A0002 SPEC 08 33 23.pdf PDF
A0002 SPEC 07 26 30.pdf PDF
A0002 SHEET F104.pdf PDF
A0002 SHEET A402.pdf PDF
A0002 SHEET A406.pdf PDF
A0002 SHEET A006.pdf PDF
A0002 SPEC 12 31 00.pdf PDF
A0002 SHEET A331.pdf PDF
A0002 SHEET A405.pdf PDF
A0002 SUBMITTAL REGISTER.pdf PDF
A0002 SHEET A404.pdf PDF
A0002 SHEET A114.pdf PDF
A0002 SHEET A002.pdf PDF
A0002 SPEC 10 11 00 .pdf PDF
A0002 SHEET A605.pdf PDF
A0002 SHEET MI802.pdf PDF
A0002 SHEET A611.pdf PDF
A0002 SHEET A601.pdf PDF
A0001 SHEET C516.pdf PDF
A0001 SHEET A401.pdf PDF
A0001 SPEC 28 31 76.pdf PDF
A0001 SHEET EG501.pdf PDF
A0001 SHEET A602.pdf PDF
A0001 SHEET LP501.pdf PDF
A0001 SHEET A406.pdf PDF
A0001 SHEET A402.pdf PDF
A0001 SHEET A114.pdf PDF
A0001 SHEET A121 THRU A151.pdf PDF
A0001 SHEET A601.pdf PDF
Amendment 1.pdf PDF
A0001 SHEET I002 AND I221.pdf PDF
A0001 SHEET A322.pdf PDF
A0001 SPEC 07 61 1400 20.pdf PDF
A0001 SHEET A611.pdf PDF
H.01.01 794_AIT_PH4_SID_RTA_SUBMITTAL.pdf PDF
H.01.01 794_AIT_PH4_SPEC_RTA_SUBMITTAL.pdf PDF
H.01.01 794_AIT_PH4_FFE_RTA_SUBMITTAL.pdf PDF
Show all 50

AIT Barracks Fort Eustis VA (Amendment 0004) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A. AIT Barracks Complex Phase IV, Barracks Only, Fort Eustis, VA (Construction)

B. Project consist of Design-Bid-Build construction of a 148,000 square foot, four story barracks building w ith provisions to include: special foundation, f ire protection, and alarm systems and Energy Monitoring Control Systems (EMCS) connection.

C. In accordance w ith FAR 36.205 the statutory cost limitation for AIT Barracks Complex PH 4-Barracks Only (Clins 0001 - 0006) $49,565,000.00

D. This acquisition is a IFB Sealed bid w ith DRC requirements. The NAICS code is 236220, Commercial and Institutional Building Constructions. Small Business Size Standard of $39,500.000

e. Contracting POC is Alexander. L .Loi, phone (757) 201-7797 email alexander.l.loi@usace.army.mil

X

ALEXANDER LOI 757-201-7797

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

12-Jun-2020

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________730 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________28 Jul 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USA ENGINEER DISTRICT, NORFOLK

803 FRONT STREET

NORFOLK VA 23510

W91236

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

05:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

757-201-7183FAX:TEL: TEL: FAX:

W9123620B0015 51

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W9123620B0015

Section 00 10 00 - Solicitation

NOTICE TO BIDDERS

NOTICE TO BIDDER

PROJECT DESCRIPTION

This project will construct a 139,500 square foot, Four-story Barracks Building with provisions to include: special foundation, fire protection and alarm systems and Energy Monitoring Control Systems (EMCS) connection.

Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage, and site improvements. Heating and air conditioning will be provided by self-contained systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. The project will provide a building that will be safe to personnel, protect mission critical assets and comply with current design criteria and all applicable codes.

1. SPECIAL BID SUBMISSION INSTRUCTIONS DUE TO COVID-19

The Norfolk District anticipates the possibility that its building will be closed during the time for bid submission due to the evolving requirements arising in response to COVID-19. Accordingly, the Norfolk District will NOT accept bids my mail, hand-carry, or commercial courier (that is, no physical bids will be accepted in response to this solicitation. All bids must be submitted by electronic commerce only.

Electronic Bid Submission in DoD SAFE or Electronic Mail (E-Mail)

In accordance with (IAW) FAR 52.214-7, LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS, all bids must be uploaded to the Government system described below not later than 05:00 p.m. Eastern Day Time (EDT) July 28, 2020. Bids will be submitted through DoD Secure Access File Exchange (DoD SAFE) (https://safe.apps.mil/).

DoD SAFE will serve as the Government point of entry to submit bid.

All bids may be uploaded into DoD SAFE infrastructure as early as June 15, 2020, but in no event later than the date and time provided above

Bidders will require a unique “request code” to upload proposals into DoD SAFE, which will obtained by email only to POC: Alexander L. Loi at alexander.l.loi@usace.army.mil, and cc: PPMDContracts@usace.army.mil. The bidder should submit the email request for the “request code” NLT July 28, 2020, at 5:00 p.m. EDT. Bidders should note that the unique request code will provide only a one-time access. If the bidder needs to re-access DoD SAFE, it will need to re-request another code.

If the bidder encounters technical challenges uploading, it may elect to transmit the files via e-mail to the addresses provided in the paragraph above. The subject line of the email must include: Bid – W91236-20-B- 0015. The body of the email must not include any procurement sensitive information from the bid to avoid that information being disclosed prior to bid opening.

Bidders are strongly encouraged to avoid waiting until the last minute to attempt to transmit their bids.

The electronic bid submittal contents shall conform to the details of the solicitation and subsequent amendments.

Electronic Bid Opening

There will be a “public” bid opening conducted by the Government via teleconference on July 29, 2020, at 1000 a.m. EDT for participating bidders. The teleconference phone number, and access codes will be emailed to participants once bid submission due date and time have lapsed. Bidders will be able to participate in the reading of the bids through this teleconference.

In the event the Norfolk District building is closed at the time of bid opening, a bid abstract containing bid results will be distributed to participating bidders within twenty-fours (24) hours of the bid opening. Upon request, the Norfolk District will make the opened bids available for examination.

A copy of the duly executed bid guarantee (signed by principal and surety with raised seal) must also be included in the attachment labeled “Bid.20B0015_”Bidder Name”.” A physical copy of the bid guarantee in proper form with evident raised seal must be submitted within seventy-two (72) hours to the Government upon request from the apparent low bidder. Additionally, the bid submission shall provide signed BID by letter to include SF1442 and SF 30 acknowledgement of all Amendments.

Please be advised that in accordance with FAR Deviation 2020-o0016, Class Deviation – Original Documents, Signatures, Seals and Notarizations - Electronic signatures and electronic, mechanically-applied, or printed dates may be used and shall be considered original signatures and dates, without regard to the order in which they are affixed for all of part 28 instruments as requested by this solicitation

Electronic Bid Uploading Offerors are responsible for ensuring electronic copies are virus-free and shall run an anti-virus scan before upload into DoD SAFE. Electronic copies shall be compatible with the following software products: Adobe Acrobat Reader 11 and Microsoft Office Suite (Excel and Project) 2010. The electronic copies shall be in Adobe Acrobat (except for Microsoft Excel documents) portable document file (pdf) searchable text format. Electronic files shall be clearly identified for each section and item as detailed in the solicitation. It is the Offeror’s responsibility to obtain written confirmation of receipt of all electronic files of the bid submitted into DoD SAFE.

Any questions regarding bid submission should be directed to Mr. Alexander Loi in ProjNet.

Any questions regarding bid submission should be directed to Mr. Alexander Loi in ProjNet.

_1__. EVIDENCE OF AUTHORITY TO SIGN OFFERS

Evidence of the authority of individuals signing offers to submit firm offers on behalf of the offeror is required except where the offer is signed, and shows that it is so signed, by: the President, Vice-President, or Secretary of an incorporated offeror; a partner in the case of a partnership; or the owner in the case of a sole proprietorship. Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.

_2__. PREAWARD SAFETY CONFERENCE

a. Where an apparent low bidder, in performance of contracts during the previous three-year period, incurred one or more accidents, or where, in the opinion of the Contracting Officer, there is any question regarding this compliance with any safety or accident prevention requirement, such bidder, on request of the Contracting Officer prior to any award under this solicitation, shall attend a conference with representatives of the Contracting Officer to discuss any such accidents or non-compliance, the reason for their occurrence, and measures which will be taken to preclude any recurrence thereof.

b. Information elicited at this conference will be used by the Contracting Officer, in conjunction with other information obtained in a preaward survey, in determining the bidder's responsibility.

c. The items discussed, the preventive measures considered, and any conclusions reached in this conference shall be recorded in minutes of the meeting, which shall be authenticated by the signatures of representatives of the bidder and the Contracting Officer, and any procedures noted therein as agreed upon shall become an obligation of the bidder, along with all other safety and accident prevention requirements of the contract, if award is made to him.

_3_. AWARD TO RESPONSIBLE BIDDERS (FAR 9.1)

Responsibility will be determined, prior to award, by the Contracting Officer, either by performing a pre-award survey or conclusions based on a previous pre-award survey and/or any performance data available. A pre-award survey maybe performed in determining the bidders responsibility in accordance with FAR 9.104 and 9.106. The bidder will be required to show that he has the necessary capital, experience, and owns or can procure the necessary plant or other resources to commence the work at the time prescribed in the specifications and thereafter to prosecute and complete the work safely and satisfactorily within the time specified. If the bidder is unable to comply with the request for preaward survey, the bidder will no longer be considered for award.

To be determined responsible, a bidder must demonstrate the following –

a. Have adequate financial resources to perform the contract, or the ability to obtain them;

b. Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;

c. Have a satisfactory performance record. A prospective contractor shall not be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history;

d. Have a satisfactory record of integrity and business ethics;

e. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors);

f. Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them;

and

g. Be otherwise qualified and eligible to receive an award under applicable laws and regulations **NOTE - The Government is not liable for any costs incurred by the bidder submitting an offer in response to this solicitation.

Additionally, in accordance with FAR Part 9.1, prior to awarding a contract, the Government will conduct a Responsibility Determination of the firm selected for award. The below information will be requested of the apparent low bidder. This information is not required to be responsive to the invitation for bid. Too efficiently and expeditious award the resultant contract, it is HIGHLY recommended that bidders provide the below information with their bid. If bidders wish to shield this information from public view at the bid opening, the information may be placed in an envelope with the following legend:

PRE-AWARD SURVEY INFORMATION

SOLICITATION NO. W91236-20-B-0015

This information is not required to be responsive to the invitation for bid.

a) Current commitments and expected dates of completion.

b) One (1) signed bank reference demonstrating adequate financial resources. If bidder’s firm has a line of credit – provide information on how many figures bidder can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).

c) The bidder shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization.

Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the bidder.

IMPORTANT NOTE, this solicitation requires apparent low bidder to submit DRC criteria as defined below:

DEFINITIVE RESPONSIBILITY CRITERIA (DRC)

The apparent low bidder will be required to submit project information to establish that it meets the DRCs within 24 hours of bid opening. Failure to provide the DRC information may result in a negative responsibility determination that will render the bidder ineligible for award.

The low bidder must submit examples of prior contract performance that demonstrate the elements listed below to be deemed responsible as measured inagainst the definitive responsibility criteria.

The project submission shall describe the owner name, contract number (if applicable), contract value, a description of the work performed, which should address the mandatory project elements set out below, and a point of contact for the owner.

The bidder shall submit projects in which it has performed as the prime contractor, in a joint venture, or as subcontractor. If work performed as a joint venture partner or subcontractor, the bidder should describe the scope of work performed under the general contract.

a. Bidder shall provide three example projects that each demonstrates completion of new construction of a facility involving a minimum of 125,000 square feet of enclosed climate-controlled space.

b. Bidder shall provide three example projects that each demonstrates vertical construction of a permanent facility with a minimum of four floors whose primary purpose, or a substantial secondary benefit, is to provide housing or lodging space.

c. Bidder shall provide three example projects that were constructed within a United States Military Installation.

Review of this criteria will be on a pass/fail basis. After bids are opened, the apparent low bidder will be required to submit narratives describing projects that substantiate the Definitive Responsibility Criteria. If they do not satisfy the criteria listed above, the second low bidder will be requested to provide their example projects, and so on until a bidder satisfies the requirements.

The example project description of each project shall be one page or less, and shall include a description of the project, to include how the example project meets the requirement listed above. Each example project may, but need not, satisfy more than one of the DRCs listed above. Example: a 150,000 SF Dormitory on a U.S. Military Installation would satisfy one project in all three categories.

_4__. INSPECTION OF THE SITE

Prospective bidders are invited to visit the site of the work in order to acquaint themselves as to site conditions and other problems incident to the prosecution of the work. Arrangements for inspection of the site shall be made through the Office the Area Engineer identified in the clause 52.236-27, entitled "SITE VISIT

(CONSTRUCTION)."

_5__. SUBCONTRACTING PLAN (CONSTRUCTION)

In accordance with clause 52.219-9 Alt I (as prescribed by FAR 19.708(b) if the bidder is a large business a SMALL BUSINESS SUBCONTRACTING PLAN is required to be submitted with your DRC. The subcontracting plan shall be reviewed and approved by the Contracting Officer prior to award in accordance with the FAR 19.704-5

_6__. BASIS OF AWARD

All blanks must be filled in by the bidder, the bidder must insert a value for each CLIN or the bid will be deemed non-responsive . A single award will be made to the lowest responsible, responsive bidder on the basis of the total price bid. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s). Prior to making an award, a pre-award survey will be made and the low bidder will be required to show that he has the necessary capital, experience, and owns or can procure the necessary plant to commence the work at the time prescribed in the specifications and thereafter to prosecute and complete the work safely and satisfactorily within the time specified.

_7__. INCURRING COSTS

The Government is not liable for any costs incurred by the offeror submitting an offer in response to this solicitation.

_8__. AGENTS

Offers signed by an Agent must be made in the name of the Principal and must be accompanied by evidence of said Agent’s authority to act on behalf of its Principal.

_9__. UNBALANCED BIDS

Any offer which is materially unbalanced as to prices for the Contract Line Item Schedule (as defined in FAR 14.408) may be rejected as non-responsive or otherwise not considered for award. An unbalanced offer is one which is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

_10__. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL

The contractor shall not accept instructions issued by any person, employed by the U.S. Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the limits of his/her authority as defined in the Designation of Authority letter. A copy of the Designation of Authority letter will be furnished to the contractor at time of contract award.

_11__. STATUTORY COST LIMITATION

The Statutory Cost Limintation in accordance with FAR 36.205 is $49,565,000 for CLINs 0001- through 0006.

_12__. OFFEROR'S QUESTIONS AND COMMENTS

Note: All questions and/or comments should reach the above referenced Contracting Office via ProjNet 10 days prior to bid closing, in order that they may be given consideration or actions taken prior to receipt of offers. ProjNet will close at 8am EDT on 10 days prior to bid closing.

1.5.1 Bidder Inquiry

1.5.1.1 Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet.

1.5.1.1.1 To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

1.5.1.1.2 From this page you may view all bidder inquiries or add inquiry.

1.5.1.1.3 Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

1.5.1.1.4 The Solicitation Number is: W91236-20-B-0015

1.5.1.1.5 The Bidder Inquiry Key is: QVUS9F-QRZH5J.

1.5.1.2 The Bidder Inquiry System will be unavailable for new inquires 10 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

1.5.1.3 Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

1.5.1.4 The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job AIT Barracks 4-Story

FFP

All costs in connection with construction of a new 4-story AIT Barracks, building construciton only as shown on drawings and specifications, excluding the work descriped in CLIN 0002 - 0007. Source of funds is MILCON.

FOB: Destination

PSC CD: Y1FC

NET AMT

0002 1 Job Support Facilities

FFP

All costs in connection with construction of all site work improvements complete as shown on the drawings and specification, excluding the work described in CLIN 0001 & 0003 - 0007. Source of funds is MILCON

0003 1 Job OPTION Parking Area Reference Drawings

FFP

Bid Option 001 - All costs in connection with constuction of parking lot as referenced on Reference drawings CS101 and 101A and specification, excluding the work described in CLIN 0001-0002 & 0004 - 0007. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.

0004 1 Job OPTION Privatized Utility-Water&Sanitary Sewer

FFP

Bid Option 002 - Construction of new and demolition of existing sewer and water on the project sites in conflict with proposed buildings and the installation of new services, outside the 5 – foot line, excluding the work described in CLINs 0001 - 0003 & 0005 - 0007. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.

0005 1 Job OPTION Privatized Utility- Electric

FFP

Bid Option 003 - Construction of new and demolition of existing electrical lines on the project site in conflict with proposed buildings and the installation of new services, outside the 5 – foot line, excluding the work described in CLINs 0001 - 0004 & 0006 - 0007. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.

0006 1 Job OPTION Privatized Utility-Natural Gas

FFP

Bid Option 004 - Construction of new and demolition of existing gas lines on the project site in conflict with proposed buildings and the installation of new services, outside the 5 – foot line, excluding the work described in CLINs 0001 - 0005 & 0007. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.

0007 1 Job OPTION Furniture, Fixtures and Equipment

FFP

All costs in connection with providing Furniture, Fixtures & Equipment (FF&E) complete as shown on the drawings and specififications, excluding the work described in CLIN 0001-0006. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7. If this option is exercised, the overall contract completion date will be extended by 30 days.

BID TOTAL

BID BASE SUBTOTAL (CLINS 0001 and 0002) ________________

BID OPTIONS SUBTOTAL (CLINS 0003 – 0007) ________________

TOTAL BID PLUS OPTIONS (CLINS 0001-00007) _________________

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 730 dys. ANP 1 ENGINEERING BRANCH

JONATHAN A JONES

US ARMY ENGR DIST NORFOLK ATTN:

CENAO-TS-E 80

REET

NORFOLK VA 23510-1011

(757) 201-7254

W91236

0002 730 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0003 730 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0004 730 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0005 730 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0006 730 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0007 730 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-27 Price Reduction for Defective Certified Cost or Pricing Data -

Modifications - Sealed Bidding

AUG 2011

52.214-28 Subcontracting Certified Cost Or Pricing Data-- Modifications--Sealed Bidding

OCT 2010

52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.217-5 Evaluation Of Options JUL 1990 52.222-24 Preaward On-Site Equal Opportunity Compliance Evaluation FEB 1999 52.232-14 Notice Of Availability Of Progress Payments Exclusively For

Small Business Concerns

APR 1984

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a FIRM FIXED PRICE CONSTRUCTION contract resulting from this solicitation.

(End of provision)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from US ARMY CORP OF ENGINEERS, ATTN: DIANNE K. GRIMES 803 FRONT STREET NORFOLK, VA 23510 Email: dianne.k.grimes@usace.army.mil

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer's notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.

(End of clause)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visit will be 23 June 2020 at 10:00am EDT

POC: Karen Perocier, email: Karen.D.Perocier@usace.army.mil

(c) All participants will meet in the parking lot on Jackson Street closest to the corner Washington BLVD and Jackson (adjacent to AIT Phase III Barracks).

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

www.acquisition.gov/far

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any DFAR (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 45 00 - Representations and Certifications

52.209-5 Certification Regarding Responsibility Matters OCT 2015 52.209-7 Information Regarding Responsibility Matters OCT 2018 52.209-12 Certification Regarding Tax Matters FEB 2016 52.209-13 Violation of Arms Control Treaties or Agreements --

Certification.

JUN 2018

52.222-38 Compliance With Veterans' Employment Reporting Requirements

FEB 2016

52.223-1 Biobased Product Certification MAY 2012 52.223-4 Recovered Material Certification MAY 2008 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-22 Public Disclosure of Greenhouse Gas Emissions and

Reduction Goals -- Representation.

DEC 2016

52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan--Certification

AUG 2009

52.225-22 Notice of Required Use of American Iron, Steel, and Manufactured Goods--Buy American Statute--Construction Materials

MAY 2014

52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.

AUG 2018

252.203-7005 Representation Relating to Compensation of Former DoD Officials

NOV 2011

252.204-7007 Alternate A, Annual Representations and Certifications JUN 2019 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

252.225-7031 Secondary Arab Boycott Of Israel JUN 2005

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $39,500,000.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

( ) Paragraph (d) applies.

( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2; Prohibition on Contracting with Inverted Domestic Corporations--Representation.

(vii) 52.209-5; Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225- 5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.]

(i) 52.204-17, Ownership or Control of Offeror.

(ii) 52.204-20, Predecessor of Offeror.

(iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

(iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.

(v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Certification.

(vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA- Designated Products (Alternate I only).

(vii) 52.227-6, Royalty Information.

(A) Basic.

(B) Alternate I.

(viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [ offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS--

REPRESENTATION (NOV 2015)

(a) Definitions. Inverted domestic corporation and subsidiary have the meaning given in the clause of this contract entitled Prohibition on Contracting with Inverted Domestic Corporations (52.209-10).

(b) Government agencies are not permitted to use appropriated (or otherwise made available) funds for contracts with either an inverted domestic corporation, or a subsidiary of an inverted domestic corporation, unless the exception at 9.108-2(b) applies or the requirement is waived in accordance with the procedures at 9.108-4.

(c) Representation. The Offeror represents that--

(1) It [ ___ ] is, [ ___ ] is not an inverted domestic corporation; and

(2) It [ ___ ] is, [ ___ ] is not a subsidiary of an inverted domestic corporation.

52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER

TRADE AGREEMENTS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-- (i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

Section 00 70 00 - Conditions of the Contract

CONTRACT REQUIREMENTS

_1__. REQUIRED INSURANCE

The contractor shall procure and maintain during the entire period of performance under this contract, the following minimum insurance:

TYPE AMOUNT

Workers Compensation As required by State law Employer's Liability $100,000 per person General Liability $500,000 per occurrence

Motor Vehicle Liability (for each motor vehicle):

Bodily injury or death $200,000 per person $500,000 per occurrence Property damage $20,000 per occurrence

Prior to commencement of work hereunder, the contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective for such period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than 30 days after written notice thereof to the Contracting Officer.

__2_. PERFORMANCE OF WORK BY CONTRACTOR

Bidder’s attention is directed to FAR 52.236-1, "Performance of Work by Contractor." Contractor is required to furnish a description of the work which will be performed by his own organization, (e.g., earthwork, paving, etc.), the percentage of the total work this represents, and the estimated cost thereof. Such description of work to be performed by the contractor's own organization shall be provided to the Contracting Officer within 10 days of contract award.

__3_. PERFORMANCE EVALUATION OF CONTRACTOR

As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work.