26Q0018 - SCHEDULE TEMPLATE.pdf
PDF 84 KB Posted
- Attached to
- NEC - Warehouse Parking Lot
- Solicitation number
- 19PM0726Q0018
- Issued by
-
Department of State
About this file
This document is a 45-day preliminary construction schedule bar chart for a warehouse concrete parking lot project at the U.S. Embassy in Panama City, managed by the Facility Management Office (FAC). The schedule is conceptual and will be finalized by the contractor upon Notice to Proceed.
The construction project encompasses 17 primary activities spanning the full 45-working-day timeline, with substantial completion targeted for Day 45. Initial work includes mobilization and security coordination (3 days), followed by clearing and grubbing (3 days) and excavation and grading to subgrade (6 days). Mid-project activities focus on site preparation with proof-rolling, geotextile separator installation, and storm drainage system installation (structures, piping, and tie-in). The primary construction work involves aggregate base course placement and compaction (7 days), concrete curb and wheel stop formwork (4 days), and Portland cement concrete pavement placement (11 days). Concrete curing requires a minimum of 7 days per ACI 308 standards. Final activities include wheel stop installation, pavement markings and signage, small concrete works for ramps and sidewalks, and final cleanup and site restoration. Quality control testing (soil, aggregate, and concrete cylinders) and traffic control with barricades and flaggers are continuous support activities throughout the 45-day period. The schedule concludes with final inspection, closeout documentation, and as-built submission. The basis for this schedule is the IGCE/GSO Annex for the Parking Lot at the U.S. Embassy Panama 2026.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. EMBASSY PANAMA CITY
Facility Management Office (FAC) | NEC - Warehouse Parking Lot
45-DAY CONSTRUCTION SCHEDULE
Bar Chart Schedule Preliminary / For Planning Purposes
0 5 10 15 20 25 30 35 40 45 Working Day
3d
3d
6d
3d
3d
7d
7d
4d
11d
4d
14d
2d
3d
35d
45d
3d
3d
Day 45 Substantial Completion
1. Mobilization, Submittals & Security Coordination
2. Clearing & Grubbing
3. Excavation & Grading to Subgrade
4. Proof-Rolling & Undercut Allowance
5. Geotextile Separator Installation
6. Storm Drainage (Structures, Piping & Tie-In)
7. Aggregate Base Course Placement & Compaction
8. Concrete Curb & Wheel Stop Formwork
9. Portland Cement Concrete Pavement Placement
10. Small Concrete Works (Ramps / Sidewalk / Patch)
11. Concrete Curing (Min. 7 Days per ACI 308)
12. Wheel Stop Installation
13. Pavement Markings & Signage
14. QC Testing (Soil, Aggregate & Concrete Cylinders)
15. Traffic Control / Barricades / Flaggers
16. Final Cleanup & Site Restoration
17. Final Inspection, Closeout & As-Built Submission
Construction Activity Continuous / Recurring Support Activity Shaded bands denote successive 2-week work periods.
U.S. Embassy Panama City FAC | Warehouse Concrete Parking Lot Schedule is conceptual and shall be finalized by the Contractor upon Notice to Proceed. Basis: IGCE/GSO Annex Parking Lot, U.S. Embassy Panama 2026.