26Q0018 - SCHEDULE TEMPLATE.pdf

PDF 84 KB Posted

Attached to
NEC - Warehouse Parking Lot
Solicitation number
19PM0726Q0018
Issued by

About this file

This document is a 45-day preliminary construction schedule bar chart for a warehouse concrete parking lot project at the U.S. Embassy in Panama City, managed by the Facility Management Office (FAC). The schedule is conceptual and will be finalized by the contractor upon Notice to Proceed.

The construction project encompasses 17 primary activities spanning the full 45-working-day timeline, with substantial completion targeted for Day 45. Initial work includes mobilization and security coordination (3 days), followed by clearing and grubbing (3 days) and excavation and grading to subgrade (6 days). Mid-project activities focus on site preparation with proof-rolling, geotextile separator installation, and storm drainage system installation (structures, piping, and tie-in). The primary construction work involves aggregate base course placement and compaction (7 days), concrete curb and wheel stop formwork (4 days), and Portland cement concrete pavement placement (11 days). Concrete curing requires a minimum of 7 days per ACI 308 standards. Final activities include wheel stop installation, pavement markings and signage, small concrete works for ramps and sidewalks, and final cleanup and site restoration. Quality control testing (soil, aggregate, and concrete cylinders) and traffic control with barricades and flaggers are continuous support activities throughout the 45-day period. The schedule concludes with final inspection, closeout documentation, and as-built submission. The basis for this schedule is the IGCE/GSO Annex for the Parking Lot at the U.S. Embassy Panama 2026.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. EMBASSY PANAMA CITY

Facility Management Office (FAC) | NEC - Warehouse Parking Lot

45-DAY CONSTRUCTION SCHEDULE

Bar Chart Schedule Preliminary / For Planning Purposes

0 5 10 15 20 25 30 35 40 45 Working Day

3d

3d

6d

3d

3d

7d

7d

4d

11d

4d

14d

2d

3d

35d

45d

3d

3d

Day 45 Substantial Completion

1. Mobilization, Submittals & Security Coordination

2. Clearing & Grubbing

3. Excavation & Grading to Subgrade

4. Proof-Rolling & Undercut Allowance

5. Geotextile Separator Installation

6. Storm Drainage (Structures, Piping & Tie-In)

7. Aggregate Base Course Placement & Compaction

8. Concrete Curb & Wheel Stop Formwork

9. Portland Cement Concrete Pavement Placement

10. Small Concrete Works (Ramps / Sidewalk / Patch)

11. Concrete Curing (Min. 7 Days per ACI 308)

12. Wheel Stop Installation

13. Pavement Markings & Signage

14. QC Testing (Soil, Aggregate & Concrete Cylinders)

15. Traffic Control / Barricades / Flaggers

16. Final Cleanup & Site Restoration

17. Final Inspection, Closeout & As-Built Submission

Construction Activity Continuous / Recurring Support Activity Shaded bands denote successive 2-week work periods.

U.S. Embassy Panama City FAC | Warehouse Concrete Parking Lot Schedule is conceptual and shall be finalized by the Contractor upon Notice to Proceed. Basis: IGCE/GSO Annex Parking Lot, U.S. Embassy Panama 2026.

File details come from the government source that posted it. Updated .