26Q0018 - SCHEDULE TEMPLATE -60_Day.pdf
PDF 64 KB Posted
- Attached to
- NEC - Warehouse Parking Lot
- Solicitation number
- 19PM0726Q0018
- Issued by
-
Department of State
About this file
This is a 60-day construction schedule bar chart for a warehouse concrete parking lot project at the U.S. Embassy in Panama City, managed by the Facility Management Office (FAC). The schedule is preliminary and conceptual, requiring finalization by the contractor upon receipt of the Notice to Proceed.
The project encompasses 17 sequential and concurrent construction activities scheduled over 60 business days to achieve substantial completion. Initial mobilization, submittals, and security coordination span 4 days, followed by site preparation including clearing and grubbing (4 days), excavation and grading to subgrade (8 days), and proof-rolling with undercut allowance (4 days). Infrastructure work includes geotextile separator installation (4 days), storm drainage structures, piping, and tie-in (10 days), and aggregate base course placement and compaction (9 days). Concrete work comprises curb and wheel stop formwork (5 days), Portland cement concrete pavement placement (15 days), and small concrete works such as ramps and sidewalks (5 days), followed by a mandatory 7-day minimum curing period per ACI 308 standards (19 days total). Final activities include wheel stop installation (3 days), pavement markings and signage (4 days), quality control testing for soil, aggregate, and concrete cylinders (48 days as a continuous support activity), traffic control and barricades (60 days continuous), final cleanup and site restoration (4 days), and final inspection, closeout, and as-built submission (3 days). The schedule is based on the IGCE/GSO Annex Parking Lot documentation for the U.S. Embassy Panama 2026.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. EMBASSY PANAMA CITY
Facility Management Office (FAC) | NEC - Warehouse Parking Lot
60-DAY CONSTRUCTION SCHEDULE
Bar Chart Schedule Preliminary / For Planning Purposes
0 5 10 15 20 25 30 35 40 45 50 55 60 Business Day
4d
4d
8d
4d
4d
10d
9d
5d
15d
5d
19d
3d
4d
48d
60d
4d
3d
Day 60 Substantial Completion
1. Mobilization, Submittals & Security Coordination
2. Clearing & Grubbing
3. Excavation & Grading to Subgrade
4. Proof-Rolling & Undercut Allowance
5. Geotextile Separator Installation
6. Storm Drainage (Structures, Piping & Tie-In)
7. Aggregate Base Course Placement & Compaction
8. Concrete Curb & Wheel Stop Formwork
9. Portland Cement Concrete Pavement Placement
10. Small Concrete Works (Ramps / Sidewalk / Patch)
11. Concrete Curing (Min. 7 Days per ACI 308)
12. Wheel Stop Installation
13. Pavement Markings & Signage
14. QC Testing (Soil, Aggregate & Concrete Cylinders)
15. Traffic Control / Barricades / Flaggers
16. Final Cleanup & Site Restoration
17. Final Inspection, Closeout & As-Built Submission
Construction Activity Continuous / Recurring Support Activity Shaded bands denote successive 2-week work periods.
U.S. Embassy Panama City FAC | Warehouse Concrete Parking Lot Schedule is conceptual and shall be finalized by the Contractor upon Notice to Proceed. Basis: IGCE/GSO Annex Parking Lot, U.S. Embassy Panama 2026.