26Q0018 - SCHEDULE TEMPLATE -60_Day.pdf

PDF 64 KB Posted

Attached to
NEC - Warehouse Parking Lot
Solicitation number
19PM0726Q0018
Issued by

About this file

This is a 60-day construction schedule bar chart for a warehouse concrete parking lot project at the U.S. Embassy in Panama City, managed by the Facility Management Office (FAC). The schedule is preliminary and conceptual, requiring finalization by the contractor upon receipt of the Notice to Proceed.

The project encompasses 17 sequential and concurrent construction activities scheduled over 60 business days to achieve substantial completion. Initial mobilization, submittals, and security coordination span 4 days, followed by site preparation including clearing and grubbing (4 days), excavation and grading to subgrade (8 days), and proof-rolling with undercut allowance (4 days). Infrastructure work includes geotextile separator installation (4 days), storm drainage structures, piping, and tie-in (10 days), and aggregate base course placement and compaction (9 days). Concrete work comprises curb and wheel stop formwork (5 days), Portland cement concrete pavement placement (15 days), and small concrete works such as ramps and sidewalks (5 days), followed by a mandatory 7-day minimum curing period per ACI 308 standards (19 days total). Final activities include wheel stop installation (3 days), pavement markings and signage (4 days), quality control testing for soil, aggregate, and concrete cylinders (48 days as a continuous support activity), traffic control and barricades (60 days continuous), final cleanup and site restoration (4 days), and final inspection, closeout, and as-built submission (3 days). The schedule is based on the IGCE/GSO Annex Parking Lot documentation for the U.S. Embassy Panama 2026.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. EMBASSY PANAMA CITY

Facility Management Office (FAC) | NEC - Warehouse Parking Lot

60-DAY CONSTRUCTION SCHEDULE

Bar Chart Schedule Preliminary / For Planning Purposes

0 5 10 15 20 25 30 35 40 45 50 55 60 Business Day

4d

4d

8d

4d

4d

10d

9d

5d

15d

5d

19d

3d

4d

48d

60d

4d

3d

Day 60 Substantial Completion

1. Mobilization, Submittals & Security Coordination

2. Clearing & Grubbing

3. Excavation & Grading to Subgrade

4. Proof-Rolling & Undercut Allowance

5. Geotextile Separator Installation

6. Storm Drainage (Structures, Piping & Tie-In)

7. Aggregate Base Course Placement & Compaction

8. Concrete Curb & Wheel Stop Formwork

9. Portland Cement Concrete Pavement Placement

10. Small Concrete Works (Ramps / Sidewalk / Patch)

11. Concrete Curing (Min. 7 Days per ACI 308)

12. Wheel Stop Installation

13. Pavement Markings & Signage

14. QC Testing (Soil, Aggregate & Concrete Cylinders)

15. Traffic Control / Barricades / Flaggers

16. Final Cleanup & Site Restoration

17. Final Inspection, Closeout & As-Built Submission

Construction Activity Continuous / Recurring Support Activity Shaded bands denote successive 2-week work periods.

U.S. Embassy Panama City FAC | Warehouse Concrete Parking Lot Schedule is conceptual and shall be finalized by the Contractor upon Notice to Proceed. Basis: IGCE/GSO Annex Parking Lot, U.S. Embassy Panama 2026.