This amendment to a solicitation provides answers to questions from vendors regarding a requirements contract opportunity. The Bureau of Land Management seeks to award a firm-fixed price contract to construct a new 3,100 square foot visitor center at the Little Sahara Recreation Area in Utah, including demolition of an existing 2,800 square foot building, by December 2021. Work includes site utilities, landscaping, a photovoltaic system, and applicable wage rates. The estimated value is between $1 million and $5 million. Interested vendors must register in the System for Award Management and monitor the solicitation website for amendments. A pre-proposal site visit will be held and questions should reference solicitation number 140L5721R0001.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L5721R0001 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LUA
SALT LAKE CITY UT 84101
440 WEST 200 SOUTH, SUITE 500
BLM UT-STATE OFC ADM SVCS BR(UT952)
02/23/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/23/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Little Sahara Visitor Center Construction & Demolition of Existing Visitor Center
Legacy Doc #: BLM
The purpose of this amendment is to post questions and answers relating to this solicitation. See section 11 of this form above for the amendment acknowledgement requirements. The date and time for submission of proposals has NOT been extended. All other terms and conditions remain unchanged.
Question 1: Could you please clarify the time for all items converted to daylight savings time. We switch on March 14th. Will the walk through be at 11:00 am MDT? It is currently listed at 11:00 am MT which would be 12 noon MDT.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Leslie B. Gunn
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L5721R0001/0001
Answer 1: The site visit will be held at 11:00 am MDT.
Question 2: Is this project tax exempt?
Answer 2: "Prime contractors and subcontractors shall not normally be designated as agents of the
Government for the purpose of claiming immunity from State or local sales or use taxes." -
Federal Acquisition Regulations (FAR) 29.303.
Offerors should not assume tax exemption for this specific project.
Question 3: Is there a woman owned preference?
Answer 3: No, this is a total small business set aside with no additional preference for woman-owned businesses.
Question 4: Is the site visit mandatory? If not, can pictures of the existing building (for demo) be provided?
Answer 4: No, the site visit is not mandatory, but vendors are expected to conduct all reasonable inspections/investigations of the site. See clause 52.236-3 - Site Investigations and Conditions Affecting the Work contained in the solicitation. Pictures alone would not be a substitute for that, however, the BLM will take a few photos of the existing building and post with the Q&As after the site visit and question submission deadline.
Question 5: Is there somewhere in the specifications that calls out the gauge of the steel studs?
Answer 5: See Specification Section 092216 -
Non-Structural Metal Framing.
Period of Performance: 05/01/2021 to 12/31/2021